Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Atlanta, Georgia (GA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 943Number of bridges
  • 11,804ft / 3,598mTotal length
  • $2,063,749,000Total costs
  • 46,196,877Total average daily traffic
  • 629,964Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Atlanta
  • No street view available for this location

New bridges in Atlanta, GA - historical statistics
  • New bridges - historical statistics
  • 31900-1909
  • 51910-1919
  • 271920-1929
  • 271930-1939
  • 121940-1949
  • 301950-1959
  • 1071960-1969
  • 271970-1979
  • 1181980-1989
  • 421990-1999
  • 162000-2009
  • 182010-2019
  • 82020-2022
Reconstructed bridges in Atlanta, GA - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 41940-1949
  • 31950-1959
  • 31960-1969
  • 461970-1979
  • 201980-1989
  • 31990-1999
  • 22000-2009
  • 12010-2019
  • 12020-2022
Average Bridge Daily Traffic in Atlanta, GA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 4.0%Very good
  • 72.6%Good
  • 18.6%Satisfactory
  • 4.5%Fair
  • 0.3%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 26.1%Very good
  • 59.6%Good
  • 8.8%Satisfactory
  • 4.5%Fair
  • 1.1%Poor
  • 0.3%Imminent failure
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 0.3%Excellent
  • 4.3%Very good
  • 79.5%Good
  • 11.2%Satisfactory
  • 4.8%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.5%Excellent
  • 36.0%Very good
  • 34.3%Good
  • 19.2%Satisfactory
  • 5.8%Fair
  • 1.2%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 73.3%Good
  • 21.7%Satisfactory
  • 5.0%Fair
Find on map >>   Show street view

Structure Number: 1210004,  Location: IN N ATLANTA (Lat: 33.779939,  Lng: -84.413078),  Route carried "on" structure: City street 9003,  Year Built: 1974,  Status: Open,  Structure Length: 5.79m (19.00ft),  Average Daily Traffic: 15,500 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 23,250 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: CSX RAILROAD- SOU. RR.,  Facility Carried by Structure: MARIETTA STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 6 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 57.9m (190.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 20.2m (66.3ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $1,147,000,  Roadway Improvement Cost: $115,000,  Total Project Cost: $1,721,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210005,  Location: IN N ATLANTA (Lat: 33.787189,  Lng: -84.428047),  Route carried "on" structure: City street 9003,  Year Built: 1953,  Status: Open,  Structure Length: 11.80m (38.71ft),  Average Daily Traffic: 13,670 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 20,505 (year 2031),  Design Load: H 20,  Features Intersected: CSX RAILROAD- SOU. RR.,  Facility Carried by Structure: MARIETTA BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 34.1m (111.9ft),  Skew: 20 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 48.5m (159.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 17.5m (57.4ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 34.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $2,337,000,  Roadway Improvement Cost: $234,000,  Total Project Cost: $3,505,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210006,  Location: IN N ATLANTA (Lat: 33.795408,  Lng: -84.432339),  Route carried "on" structure: City street 9003,  Year Built: 1952,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 13,670 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 20,505 (year 2031),  Design Load: H 20,  Features Intersected: SPUR RAILROAD TRACK,  Facility Carried by Structure: MARIETTA BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 17.1m (56.1ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 21.9m (71.9ft),  Out-to-Out Width: 26.1m (85.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $471,000,  Roadway Improvement Cost: $47,000,  Total Project Cost: $706,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210008,  Location: IN ATLANTA (Lat: 33.742558,  Lng: -84.406928),  Route carried "on" structure: City street 9124,  Year Built: 1990,  Status: Open,  Structure Length: 2.96m (9.71ft),  Average Daily Traffic: 7,740 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 11,610 (year 2031),  Design Load: HS 20,  Features Intersected: NS RAILROAD (718069H),  Facility Carried by Structure: WHITEHALL STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.3m (69.9ft),  Curb or Sidewalk Widths: Left: 2.7m (8.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 19.5m (64.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $586,000,  Roadway Improvement Cost: $59,000,  Total Project Cost: $879,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210009,  Location: IN ATLANTA (Lat: 33.746619,  Lng: -84.397850),  Route carried "on" structure: City street 9124,  Year Built: 1963,  Status: Open,  Structure Length: 6.55m (21.49ft),  Average Daily Traffic: 7,740 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 11,610 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: M-9073 SPRING STREET,  Facility Carried by Structure: WHITEHALL STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.047,  Lanes on structure: 4,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 20.3m (66.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,298,000,  Roadway Improvement Cost: $130,000,  Total Project Cost: $1,947,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 121001,  Location: DOWNTOWN ATLANTA (Lat: 33.755044,  Lng: -84.393828),  Route carried "on" structure: City street 9073,  Year Built: 1997,  Year Reconstructed: 2020,  Status: Posted for load,  Structure Length: 46.82m (153.61ft),  Average Daily Traffic: 17,350 (year 2018),  Truck Traffic: 1%,  Average Future Daily Traffic: 24,615 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: ALABAMA ST/CSX RR,  Facility Carried by Structure: TED TURNER DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.529,  Lanes on structure: 4,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 17,  Length of Maximum Span: 65.5m (214.9ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 18.2m (59.7ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 25.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 11.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 53.28m (174.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $9,281,000,  Roadway Improvement Cost: $928,000,  Total Project Cost: $13,922,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210011,  Location: IN N ATLANTA (Lat: 33.776569,  Lng: -84.406328),  Route carried "on" structure: US 41,  Year Built: 1974,  Status: Open,  Structure Length: 6.77m (22.21ft),  Average Daily Traffic: 28,050 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 42,075 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: M-9150 THIRD STREET,  Facility Carried by Structure: NORTHSIDE DR (NBL)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.093,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 22.3m (73.2ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 14.2m (46.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $867,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $1,301,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210012,  Location: IN NORTH ATLANTA (Lat: 33.802569,  Lng: -84.407803),  Route carried "on" structure: US 41,  Year Built: 1986,  Status: Open,  Structure Length: 5.64m (18.50ft),  Average Daily Traffic: 25,490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 38,235 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-75 (SBL) + I-75 RAMP,  Facility Carried by Structure: NORTHSIDE DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.312,  Lanes on structure: 7,  Lanes under structure: 7,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 26.8m (87.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 28.7m (94.2ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 27.4m (89.9ft),  Out-to-Out Width: 31.8m (104.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 45.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $1,709,000,  Roadway Improvement Cost: $171,000,  Total Project Cost: $2,563,000,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1210014,  Location: IN N ATLANTA (Lat: 33.853608,  Lng: -84.430978),  Route carried "on" structure: US 41,  Year Built: 1938,  Year Reconstructed: 1954,  Status: Posted for load,  Structure Length: 2.62m (8.60ft),  Average Daily Traffic: 22,330 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 33,495 (year 2032),  Design Load: H 20,  Features Intersected: NANCY CREEK,  Facility Carried by Structure: N'SIDE PARKWAY US
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 25.750,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 17.7m (58.1ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 1.3m (4.3ft),  Right: 1.3m (4.3ft),  Curb-To-Curb Width: 19.3m (63.3ft),  Out-to-Out Width: 22.2m (72.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $519,000,  Roadway Improvement Cost: $52,000,  Total Project Cost: $779,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1210016,  Location: IN ATLANTA (Lat: 33.703328,  Lng: -84.405019),  Route carried "on" structure: City street 9204,  Year Built: 1965,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 5,090 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,635 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SOUTH RIVER TRIB,  Facility Carried by Structure: FAIR DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Very good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $175,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $263,000
Find on map >>   Show street view

Structure Number: 1210017,  Location: IN SOUTH ATLANTA (Lat: 33.703089,  Lng: -84.403989),  Route carried "on" structure: City street 3483,  Year Built: 1986,  Status: Open,  Structure Length: 8.38m (27.49ft),  Average Daily Traffic: 5,080 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,620 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-75,  Facility Carried by Structure: FAIR DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 16,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 42.1m (138.1ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 15.9m (52.2ft),  Out-to-Out Width: 21.4m (70.2ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 37.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,661,000,  Roadway Improvement Cost: $166,000,  Total Project Cost: $2,491,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1210018,  Location: IN ATLANTA (Lat: 33.702639,  Lng: -84.400308),  Route carried "on" structure: City street 9204,  Year Built: 1965,  Status: Open,  Structure Length: 1.77m (5.81ft),  Average Daily Traffic: 5,090 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,635 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SOUTH RIVER TRIB,  Facility Carried by Structure: FAIR DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 6 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.5m (18.0ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 1.2m (3.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $412,000,  Roadway Improvement Cost: $41,000,  Total Project Cost: $618,000
Find on map >>   Show street view

Structure Number: 1210019,  Location: IN NW ATLANTA (Lat: 33.786858,  Lng: -84.493119),  Route carried "on" structure: US 78,  Year Built: 1964,  Year Reconstructed: 1987,  Status: Open,  Structure Length: 6.52m (21.39ft),  Average Daily Traffic: 27,200 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 40,800 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-285,  Facility Carried by Structure: BANKHEAD HIGHWAY U
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 6,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 21.3m (69.9ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 23.2m (76.1ft),  Out-to-Out Width: 26.3m (86.3ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 121002,  Location: IN W ATLANTA (Lat: 33.771928,  Lng: -84.429908),  Route carried "on" structure: US 78,  Year Built: 1930,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 13,940 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 20,910 (year 2032),  Design Load: H 15,  Features Intersected: PROCTOR CREEK,  Facility Carried by Structure: DONALD LEE HOLLOWA
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.047,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 18.7m (61.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 34.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $278,000,  Roadway Improvement Cost: $28,000,  Total Project Cost: $417,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1210022,  Location: IN ATLANTA (Lat: 33.771278,  Lng: -84.390028),  Route carried "on" structure: US 8,  Year Built: 1983,  Status: Open,  Structure Length: 7.71m (25.30ft),  Average Daily Traffic: 27,520 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 41,280 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-75,  Facility Carried by Structure: NORTH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.875,  Lanes on structure: 5,  Lanes under structure: 15,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 44.8m (147.0ft),  Curb or Sidewalk Widths: Left: 3.7m (12.1ft),  Right: 3.7m (12.1ft),  Curb-To-Curb Width: 21.3m (69.9ft),  Out-to-Out Width: 29.4m (96.5ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 47.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,797,000,  Roadway Improvement Cost: $180,000,  Total Project Cost: $2,696,000,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1210023,  Location: IN ATLANTA (Lat: 33.754300,  Lng: -84.366558),  Route carried "on" structure: City street 9184,  Year Built: 1941,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 9,800 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 14,700 (year 2031),  Design Load: H 20,  Features Intersected: CS 3474 AIRLINE STREET,  Facility Carried by Structure: EDGEWOOD AVE.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 4,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.7m (44.9ft),  Curb or Sidewalk Widths: Left: 2.9m (9.5ft),  Right: 2.9m (9.5ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 18.2m (59.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 84.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.80m (25.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $272,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $408,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210025,  Location: IN ATLANTA (Lat: 33.767483,  Lng: -84.388908),  Route carried "on" structure: City street 9073,  Year Built: 1983,  Status: Open,  Structure Length: 12.71m (41.70ft),  Average Daily Traffic: 7,750 (year 2010),  Truck Traffic: 2%,  Average Future Daily Traffic: 11,625 (year 2030),  Design Load: HS 20+Mod,  Features Intersected: I-75,  Facility Carried by Structure: SPRING STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 3,  Lanes under structure: 14,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 19 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 66.1m (216.9ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 21.5m (70.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 1210026,  Location: IN N ATLANTA (Lat: 33.799197,  Lng: -84.391989),  Route carried "on" structure: US 19,  Year Built: 1985,  Status: Open,  Structure Length: 11.37m (37.30ft),  Average Daily Traffic: 33,360 (year 2012),  Truck Traffic: 2%,  Average Future Daily Traffic: 50,040 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-85- SR 13 + RAILROAD,  Facility Carried by Structure: PEACHTREE STREET U
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 7,  Lanes under structure: 16,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 26.8m (87.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 57.0m (187.0ft),  Curb or Sidewalk Widths: Left: 3.7m (12.1ft),  Right: 2.7m (8.9ft),  Curb-To-Curb Width: 26.8m (87.9ft),  Out-to-Out Width: 34.0m (111.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $3,445,000,  Roadway Improvement Cost: $344,000,  Total Project Cost: $5,167,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1210028,  Location: IN N ATLANTA (Lat: 33.811619,  Lng: -84.392289),  Route carried "on" structure: US 19,  Year Built: 1914,  Status: Open,  Structure Length: 3.47m (11.38ft),  Average Daily Traffic: 40,210 (year 2012),  Truck Traffic: 2%,  Average Future Daily Traffic: 60,315 (year 2032),  Design Load: H 15,  Features Intersected: CSX RAILROAD,  Facility Carried by Structure: PEACHTREE STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.9m (39.0ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 18.3m (60.0ft),  Out-to-Out Width: 23.9m (78.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 34.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $931,000,  Roadway Improvement Cost: $93,000,  Total Project Cost: $1,397,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210029,  Location: IN N ATLANTA (Lat: 33.817619,  Lng: -84.389219),  Route carried "on" structure: US 19,  Year Built: 1931,  Status: Open,  Structure Length: 5.52m (18.11ft),  Average Daily Traffic: 40,210 (year 2012),  Truck Traffic: 2%,  Average Future Daily Traffic: 60,315 (year 2032),  Design Load: H 15,  Features Intersected: PEACHTREE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 11.9m (39.0ft),  Curb or Sidewalk Widths: Left: 2.9m (9.5ft),  Right: 2.9m (9.5ft),  Curb-To-Curb Width: 18.3m (60.0ft),  Out-to-Out Width: 24.1m (79.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 45.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,479,000,  Roadway Improvement Cost: $148,000,  Total Project Cost: $2,218,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1210036,  Location: IN N ATLANTA (Lat: 33.795169,  Lng: -84.370878),  Route carried "on" structure: City street 9007,  Year Built: 1936,  Status: Open,  Structure Length: 2.65m (8.69ft),  Average Daily Traffic: 20,160 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 30,240 (year 2031),  Design Load: H 15,  Features Intersected: ATLANTA BELTLINE,  Facility Carried by Structure: PIEDMONT AVE.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.047,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 8.8m (28.9ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 19.0m (62.3ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 52.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $525,000,  Roadway Improvement Cost: $53,000,  Total Project Cost: $788,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210037,  Location: IN N ATLANTA (Lat: 33.796128,  Lng: -84.369950),  Route carried "on" structure: City street 9007,  Year Built: 1964,  Status: Open,  Structure Length: 4.57m (14.99ft),  Average Daily Traffic: 20,140 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 30,210 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: CLEAR CREEK,  Facility Carried by Structure: PIEDMONT AVE.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.656,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 21.2m (69.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Very good,  Operating Rating: 45.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $906,000,  Roadway Improvement Cost: $91,000,  Total Project Cost: $1,359,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210038,  Location: IN N ATLANTA (Lat: 33.811147,  Lng: -84.357308),  Route carried "on" structure: City street 9213,  Year Built: 1937,  Status: Open,  Structure Length: 6.13m (20.11ft),  Average Daily Traffic: 19,790 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 29,685 (year 2031),  Design Load: H 15,  Features Intersected: CSX RAILROAD (639814N),  Facility Carried by Structure: CHESTER BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 4,  Length of Maximum Span: 18.6m (61.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.8m (51.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 45.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 12.56m (41.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $1,214,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $1,821,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210039,  Location: IN N ATLANTA (Lat: 33.812908,  Lng: -84.354258),  Route carried "on" structure: City street 9213,  Year Built: 1938,  Status: Closed,  Structure Length: 5.85m (19.19ft),  Average Daily Traffic: 19,790 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 29,685 (year 2031),  Design Load: H 15,  Features Intersected: SOUTH FORK P'TREE CREEK,  Facility Carried by Structure: CHESHIRE BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 12.2m (40.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.8m (51.8ft)

Condition: Deck: Satisfactory,  Superstructure: Imminent failure,  Substructure: Satisfactory,  Channel: Satisfactory,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: Febuary 2021,  Other Special Inspection Date: Febuary 2022,  Bridge Improvement Cost: $1,159,000,  Roadway Improvement Cost: $116,000,  Total Project Cost: $1,739,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 121004,  Location: IN N W ATLANTA (Lat: 33.824419,  Lng: -84.352308),  Route carried "on" structure: City street 9213,  Year Built: 1977,  Year Reconstructed: 1981,  Status: Open,  Structure Length: 4.63m (15.19ft),  Average Daily Traffic: 44,980 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 67,470 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: NORTH FORK P'TREE CREEK,  Facility Carried by Structure: LENOX ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 28.7m (94.2ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 23.2m (76.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 28.6m (93.8ft),  Out-to-Out Width: 33.0m (108.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $1,242,000,  Roadway Improvement Cost: $124,000,  Total Project Cost: $1,863,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210047,  Location: IN WEST ATLANTA (Lat: 33.727939,  Lng: -84.416947),  Route carried "on" structure: US 29,  Year Built: 1905,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 19,420 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 29,130 (year 2032),  Design Load: H 15,  Features Intersected: ATLANTA BELTLINE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.624,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.9m (62.0ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.5m (18.0ft),  Curb-To-Curb Width: 17.2m (56.4ft),  Out-to-Out Width: 60.0m (196.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1210048,  Location: IN W ATLANTA (Lat: 33.743286,  Lng: -84.408286),  Route carried "on" structure: State highway 14,  Year Built: 1953,  Status: Open,  Structure Length: 2.62m (8.60ft),  Average Daily Traffic: 4,090 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 6,135 (year 2032),  Design Load: H 20,  Features Intersected: SR 3(US 19) NORTHSIDE DR,  Facility Carried by Structure: PETERS STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 40.234,  Lanes on structure: 6,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 13.1m (43.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 18.1m (59.4ft),  Out-to-Out Width: 20.6m (67.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 36.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.14m (29.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $703,000,  Roadway Improvement Cost: $70,000,  Total Project Cost: $1,054,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210049,  Location: IN WEST ATLANTA (Lat: 33.750189,  Lng: -84.398408),  Route carried "on" structure: State highway 14,  Year Built: 1935,  Status: Temporarily open,  Structure Length: 27.35m (89.73ft),  Average Daily Traffic: 5,350 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 8,025 (year 2031),  Design Load: H 15,  Features Intersected: NS RAILROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 41.843,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Number Of Approach Spans: 20,  Length of Maximum Span: 36.6m (120.1ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 15.4m (50.5ft),  Out-to-Out Width: 20.3m (66.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 27.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 30.11m (98.79ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Critical Feature Inspection Date: April 2021,  Bridge Improvement Cost: $6,008,000,  Roadway Improvement Cost: $601,000,  Total Project Cost: $9,012,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210052,  Location: IN SOUTH ATLANTA (Lat: 33.652039,  Lng: -84.367075),  Route carried "on" structure: State highway 54,  Year Built: 1964,  Status: Open,  Structure Length: 9.20m (30.18ft),  Average Daily Traffic: 23,990 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 35,985 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-285,  Facility Carried by Structure: JONESBORO ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 17.1m (56.1ft),  Skew: 24 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 26.8m (87.9ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 19.5m (64.0ft),  Out-to-Out Width: 24.4m (80.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $2,145,000,  Roadway Improvement Cost: $215,000,  Total Project Cost: $3,218,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210055,  Location: IN CITY OF ATLANTA (Lat: 33.721606,  Lng: -84.388117),  Route carried "on" structure: State highway 54,  Year Built: 1936,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 11,080 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 16,620 (year 2032),  Design Load: H 15,  Features Intersected: ATLANTA BELTLINE,  Facility Carried by Structure: MCDONOUGH BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.656,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 9 degrees,  Material/Design: Masonry,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 45.7m (149.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $163,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $245,000
Find on map >>   Show street view

Structure Number: 1210056,  Location: IN ATLANTA (Lat: 33.729889,  Lng: -84.392669),  Route carried "on" structure: City street 9166,  Year Built: 1986,  Status: Open,  Structure Length: 13.14m (43.11ft),  Average Daily Traffic: 6,220 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 9,330 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-75,  Facility Carried by Structure: PRYOR STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 6,  Lanes under structure: 15,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 5 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 71.0m (232.9ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 23.1m (75.8ft),  Out-to-Out Width: 27.7m (90.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 49.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1210062,  Location: 9.3 MI N OF FAIRBURN (Lat: 33.700994,  Lng: -84.602144),  Route carried "on" structure: State highway 70,  Year Built: 1951,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 18,010 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 27,015 (year 2031),  Design Load: H 15,  Features Intersected: MORRIS CREEK,  Facility Carried by Structure: FULTON IND. BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 32.187,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.8m (5.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $127,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $190,000
Find on map >>   Show street view

Structure Number: 1210064,  Location: 2.7 MI S OF I-20 (Lat: 33.743281,  Lng: -84.562486),  Route carried "on" structure: State highway 70,  Year Built: 1969,  Status: Open,  Structure Length: 3.17m (10.40ft),  Average Daily Traffic: 32,990 (year 2011),  Truck Traffic: 15%,  Average Future Daily Traffic: 49,485 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: UTOY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.624,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 12 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $406,000,  Roadway Improvement Cost: $41,000,  Total Project Cost: $610,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210065,  Location: 2.7 MI S OF I-20 (Lat: 33.743328,  Lng: -84.562708),  Route carried "on" structure: State highway 70,  Year Built: 1956,  Status: Open,  Structure Length: 3.20m (10.50ft),  Average Daily Traffic: 14,380 (year 2008),  Truck Traffic: 1%,  Average Future Daily Traffic: 21,570 (year 2030),  Design Load: HS 20,  Features Intersected: UTOY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.624,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 12 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.7m (35.1ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 11.22m (36.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $410,000,  Roadway Improvement Cost: $41,000,  Total Project Cost: $615,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1210067,  Location: IN W ATLANTA (Lat: 33.799578,  Lng: -84.488378),  Route carried "on" structure: City street 9013,  Year Built: 1968,  Status: Open,  Structure Length: 15.64m (51.31ft),  Average Daily Traffic: 14,140 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 21,210 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-285- PROCTOR CREEK,  Facility Carried by Structure: BOLTON ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 2,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 41.1m (134.8ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 11.5m (37.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 56.02m (183.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $2,004,000,  Roadway Improvement Cost: $200,000,  Total Project Cost: $3,007,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210068,  Location: IN N W ATLANTA (Lat: 33.805597,  Lng: -84.482339),  Route carried "on" structure: City street 9013,  Year Built: 1978,  Status: Open,  Structure Length: 6.74m (22.11ft),  Average Daily Traffic: 14,220 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 21,330 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: NS RR (718026P),  Facility Carried by Structure: BOLTON ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 19.5m (64.0ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.2m (99.1ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 19.5m (64.0ft),  Out-to-Out Width: 22.7m (74.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $1,570,000,  Roadway Improvement Cost: $157,000,  Total Project Cost: $2,355,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1210082,  Location: IN W ATLANTA (Lat: 33.738978,  Lng: -84.433108),  Route carried "on" structure: State highway 139,  Year Built: 1906,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 13,060 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 19,590 (year 2032),  Design Load: H 15,  Features Intersected: ATLANTA BELTLINE,  Facility Carried by Structure: GORDON STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.484,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.5m (18.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 21.3m (69.9ft),  Out-to-Out Width: 26.5m (86.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 22.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 7.50m (24.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $249,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $373,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: 1210083,  Location: IN W ATLANTA (Lat: 33.753589,  Lng: -84.495539),  Route carried "on" structure: State highway 139,  Year Built: 1964,  Status: Open,  Structure Length: 7.13m (23.39ft),  Average Daily Traffic: 21,060 (year 2012),  Truck Traffic: 3%,  Average Future Daily Traffic: 31,590 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: I-285,  Facility Carried by Structure: M.L.K. JR. DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.921,  Lanes on structure: 5,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 25.0m (82.0ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 18.9m (62.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 30.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place
Discuss Atlanta, Georgia (GA) on our hugely popular Georgia forum.