Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Oklahoma City, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 1,901Number of bridges
  • 21,391ft / 6,520mTotal length
  • $2,061,419,000Total costs
  • 30,433,195Total average daily traffic
  • 3,708,300Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Oklahoma City
  • No street view available for this location

New bridges in Oklahoma City, OK - historical statistics
  • New bridges - historical statistics
  • 11900-1909
  • 71910-1919
  • 541920-1929
  • 491930-1939
  • 1831940-1949
  • 1481950-1959
  • 2111960-1969
  • 2811970-1979
  • 2861980-1989
  • 2571990-1999
  • 2292000-2009
  • 1382010-2019
  • 572020-2022
Reconstructed bridges in Oklahoma City, OK - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 21940-1949
  • 61950-1959
  • 151960-1969
  • 231970-1979
  • 521980-1989
  • 421990-1999
  • 372000-2009
  • 182010-2019
  • 22020-2022
Average Bridge Truck Traffic in Oklahoma City, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 9.0%Excellent
  • 44.8%Very good
  • 27.4%Good
  • 13.4%Satisfactory
  • 2.0%Fair
  • 3.1%Poor
  • 0.5%Serious
  • 3.1%Failed
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 3.1%Excellent
  • 26.6%Very good
  • 27.4%Good
  • 24.7%Satisfactory
  • 12.6%Fair
  • 2.1%Poor
  • 3.1%Serious
  • 0.5%Critical
  • 3.1%Failed
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 1.3%Excellent
  • 14.8%Very good
  • 29.6%Good
  • 23.4%Satisfactory
  • 20.5%Fair
  • 6.5%Poor
  • 3.1%Serious
  • 0.7%Critical
  • 3.1%Failed
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.3%Excellent
  • 19.5%Very good
  • 25.1%Good
  • 28.1%Satisfactory
  • 17.4%Fair
  • 5.3%Poor
  • 1.1%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 0.2%Excellent
  • 10.6%Very good
  • 38.1%Good
  • 38.9%Satisfactory
  • 7.7%Fair
  • 1.2%Poor
  • 3.4%Serious
Find on map >>   Show street view

Structure Number: 1991,  Location: 2.5 MI. E. JCT. US81 (Lat: 35.507897,  Lng: -97.894475),  Route carried "on" structure: State highway 66,  Year Built: 1928,  Year Reconstructed: 1940,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 5,700 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 9,120 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.846,  Lanes on structure: 3,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1992,  Location: 2.5 MI. N. JCT.US277 (Lat: 34.819572,  Lng: -98.387189),  Route carried "on" structure: US 62,  Year Built: 1928,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 3,500 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 5,600 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.102,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 25.5m (83.7ft),  Out-to-Out Width: 26.1m (85.6ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1993,  Location: 3.1 MI W ALFALFA CO (Lat: 36.797306,  Lng: -98.595589),  Route carried "on" structure: US 64,  Year Built: 1928,  Year Reconstructed: 2003,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 2,100 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 3,360 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.682,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Inventory Rating: 85.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1997,  Location: 3.5 MI E JCT SH 18 (Lat: 35.709692,  Lng: -96.834247),  Route carried "on" structure: State highway 66,  Year Built: 1928,  Year Reconstructed: 1955,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 4,400 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 7,040 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.744,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 18.9m (62.0ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 42.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2014,  Location: 10.3 MI E OF TURNPIKE (Lat: 36.219631,  Lng: -95.108994),  Route carried "on" structure: Alternate US 412A,  Year Built: 1928,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,900 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,040 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: U.S. 412 ALT.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.672,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Inventory Rating: 88.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 0.77m (2.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2016,  Location: 0.6 MI. S. JCT. SH3 (Lat: 35.686086,  Lng: -97.959006),  Route carried "on" structure: US 81,  Year Built: 1928,  Year Reconstructed: 2002,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 3,400 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 5,440 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.040,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2033,  Location: 4.5S 2.6E OF CALUMET (Lat: 35.536992,  Lng: -98.067900),  Route carried "on" structure: County highway 922C,  Year Built: 1928,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 970 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,552 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.511,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Channel: Poor,  Culverts: Serious,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.47m (11.38ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2123,  Location: 2.7 MI W US81 (Lat: 34.949178,  Lng: -97.996031),  Route carried "on" structure: US 277,  Year Built: 1928,  Year Reconstructed: 1974,  Status: Open,  Structure Length: 3.14m (10.30ft),  Average Daily Traffic: 2,000 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,200 (year 2040),  Design Load: H 15,  Features Intersected: SMITH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.526,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 38.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.33m (20.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $540,000,  Roadway Improvement Cost: $891,000,  Total Project Cost: $1,512,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2125,  Location: 0.2 MI W JCT S.H. 34 (Lat: 35.291306,  Lng: -99.510114),  Route carried "on" structure: State highway 152,  Year Built: 1928,  Year Reconstructed: 1978,  Status: Open,  Structure Length: 3.14m (10.30ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: INDIAN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.842,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 60.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 6.33m (20.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $540,000,  Roadway Improvement Cost: $891,000,  Total Project Cost: $1,512,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2126,  Location: 4.S 4.9W OF CALUMET (Lat: 35.536433,  Lng: -98.201100),  Route carried "on" structure: County highway 922C,  Year Built: 1928,  Status: Open,  Structure Length: 3.41m (11.19ft),  Average Daily Traffic: 350 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 560 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: E1020
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.380,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 6.7m (22.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.61m (21.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $338,000,  Roadway Improvement Cost: $186,000,  Total Project Cost: $539,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2139,  Location: 6.0 MI E OF SH 10 (Lat: 36.869444,  Lng: -96.012500),  Route carried "on" structure: County highway D0079,  Year Built: 1928,  Status: Posted for load,  Structure Length: 4.08m (13.39ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 15,  Features Intersected: MISSON CREEK
Minimum Vertical Clearance: 4.44m (14.57ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 39.8m (130.6ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 20.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 6.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 7.27m (23.85ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Critical Feature Inspection Date: May 2021,  Bridge Improvement Cost: $371,000,  Roadway Improvement Cost: $204,000,  Total Project Cost: $594,000 ( Estimate for 2016),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2154,  Location: 7 MI E JCT US177 (Lat: 36.306517,  Lng: -96.945725),  Route carried "on" structure: US 64,  Year Built: 1928,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 5.24m (17.19ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 15,  Features Intersected: OAK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 30.635,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 12.8m (42.0ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.30m (27.23ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $682,000,  Roadway Improvement Cost: $1,125,000,  Total Project Cost: $1,909,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 2156,  Location: .3E 1.3N OF CANEY (Lat: 34.251781,  Lng: -96.205344),  Route carried "on" structure: County highway N3825,  Year Built: 1928,  Status: Posted for load,  Structure Length: 6.28m (20.60ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CLEAR BOGGY CREEK
Minimum Vertical Clearance: 4.06m (13.32ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 36.6m (120.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Poor,  Channel: Poor,  Operating Rating: 21.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 3.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 9.14m (29.99ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Critical Feature Inspection Date: September 2020,  Other Special Inspection Date: September 2021,  Bridge Improvement Cost: $467,000,  Roadway Improvement Cost: $257,000,  Total Project Cost: $727,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2159,  Location: .3E .6N OF CANEY (Lat: 34.242022,  Lng: -96.208383),  Route carried "on" structure: County highway 356C,  Year Built: 1928,  Status: Posted for load,  Structure Length: 7.74m (25.39ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 10,  Features Intersected: BOGGY CREEK O'FLOW,  Facility Carried by Structure: S OLD HWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 11.0m (36.1ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 33.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 10.21m (33.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $521,000,  Roadway Improvement Cost: $287,000,  Total Project Cost: $814,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2168,  Location: 3W 3.8N OF LELA (Lat: 36.374272,  Lng: -96.978503),  Route carried "on" structure: County highway N3380,  Year Built: 1929,  Status: Posted for load,  Structure Length: 0.74m (2.43ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Design Load: HS 20,  Features Intersected: TURKEY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.8m (22.3ft),  Curb-To-Curb Width: 5.6m (18.4ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 10.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 6.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $256,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 2171,  Location: 1.2N 1.0E OKFUSKEE (Lat: 35.615619,  Lng: -96.210428),  Route carried "on" structure: County highway N3820,  Year Built: 1929,  Status: Temporarily open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Fair,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.66m (8.73ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $136,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2172,  Location: 2 E. 4 N of Boley (Lat: 35.482669,  Lng: -96.423586),  Route carried "on" structure: County highway N3700,  Year Built: 1929,  Year Reconstructed: 1952,  Status: Temporarily open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Fair,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $143,000,  Roadway Improvement Cost: $78,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2185,  Location: 1/2 BLK E HUDSON AVE (Lat: 35.505728,  Lng: -97.518497),  Route carried "on" structure: City street D1041,  Year Built: 1929,  Status: Open,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 800 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,280 (year 2040),  Design Load: H 20,  Features Intersected: CREEK,  Facility Carried by Structure: NW 35TH ST.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 14.9m (48.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 46.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $256,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2208,  Location: 6.75 E JCT US-62 (Lat: 35.501578,  Lng: -95.865394),  Route carried "on" structure: US 266,  Year Built: 1929,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,300 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,080 (year 2040),  Design Load: HS 20,  Features Intersected: GRAYSON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 10.861,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 55.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2209,  Location: 11.4 MI S JCT US 62B (Lat: 35.594250,  Lng: -95.348628),  Route carried "on" structure: US 64,  Year Built: 1929,  Year Reconstructed: 2004,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 6,600 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 10,560 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.467,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 21.3m (69.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 54.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2213,  Location: 1.5 MI.E.JCT.SH8 (Lat: 36.666508,  Lng: -98.333425),  Route carried "on" structure: US 64,  Year Built: 1929,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 2,000 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,200 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.088,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 55.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2215,  Location: 1.35 SW LE FLORE C/L (Lat: 34.672856,  Lng: -95.069611),  Route carried "on" structure: US 271,  Year Built: 1929,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 990 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,584 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 24.683,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Very good,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2221,  Location: .3S 5.6W .5N OF ORLANDO (Lat: 36.152631,  Lng: -97.460786),  Route carried "on" structure: County highway N3110,  Year Built: 1929,  Status: Posted for load,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 24 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 38 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Poor,  Channel: Fair,  Operating Rating: 16.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 12.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.34m (10.96ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Other Special Inspection Date: July 2021,  Bridge Improvement Cost: $171,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $270,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 2241,  Location: 3.5N 2.9E OF CIM TPK/SH18 (Lat: 36.275253,  Lng: -96.729139),  Route carried "on" structure: County highway E0510,  Year Built: 1929,  Status: Posted for load,  Structure Length: 1.20m (3.94ft),  Average Daily Traffic: 75 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 120 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Poor,  Channel: Poor,  Operating Rating: 25.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 15.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.78m (12.40ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: April 2021,  Critical Feature Inspection Date: April 2021,  Other Special Inspection Date: October 2021,  Bridge Improvement Cost: $97,000,  Roadway Improvement Cost: $53,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2476,  Location: 1.8S&.6E DUKE (Lat: 34.637725,  Lng: -99.552669),  Route carried "on" structure: County highway E1640,  Year Built: 1930,  Status: Posted for load,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Poor,  Channel: Fair,  Operating Rating: 15.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 7.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $231,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2477,  Location: 4.2 MI N OF US 70 & SH76N (Lat: 34.232758,  Lng: -97.474947),  Route carried "on" structure: City street N3100,  Year Built: 1992,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 260 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 416 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2496,  Location: 4.7 W OF ARAPAHO (Lat: 35.580550,  Lng: -99.038586),  Route carried "on" structure: County highway 2002,  Year Built: 1930,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 250 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 400 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.597,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.8m (5.9ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $149,000,  Roadway Improvement Cost: $82,000,  Total Project Cost: $236,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2528,  Location: 3 N 3.7 E JCT 281 SH9 (Lat: 35.116983,  Lng: -98.187892),  Route carried "on" structure: County highway 810,  Year Built: 1930,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 80 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 128 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: 0834C
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.286,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Serious,  Culverts: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.58m (11.75ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2532,  Location: 3.2N 2.8E OF DRUMMOND (Lat: 36.347283,  Lng: -97.984886),  Route carried "on" structure: County highway E0460,  Year Built: 1930,  Status: Posted for load,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 29.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $143,000,  Roadway Improvement Cost: $78,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 2533,  Location: 0.6 MI E SH 81 (Lat: 34.085689,  Lng: -97.948381),  Route carried "on" structure: County highway 3410C,  Year Built: 1930,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 38 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 61 (year 2040),  Design Load: H 20,  Features Intersected: HACKBERRY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.3m (17.4ft),  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 5.3m (17.4ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $256,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 2544,  Location: .8 E OF SARA RD (Lat: 35.493333,  Lng: -97.691667),  Route carried "on" structure: City street E1050,  Year Built: 1930,  Year Reconstructed: 2002,  Status: Open,  Structure Length: 0.84m (2.76ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: H 10,  Features Intersected: CREEK,  Facility Carried by Structure: NW 23RD ST.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 1.5m (4.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Inventory Rating: 69.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2586,  Location: 4.5W .5N OF SLICK (Lat: 35.784278,  Lng: -96.342583),  Route carried "on" structure: County highway E0850,  Year Built: 1930,  Status: Posted for load,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: MORGAN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.183,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 5.0m (16.4ft),  Out-to-Out Width: 5.0m (16.4ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Poor,  Channel: Fair,  Operating Rating: 19.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 11.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.11m (10.20ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $159,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $251,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2618,  Location: 0.2 MI N WASHITA C/L (Lat: 35.467836,  Lng: -98.975506),  Route carried "on" structure: US 183,  Year Built: 1930,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 5,800 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 9,280 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.290,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 25.6m (84.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2711,  Location: .3N OF NW 10TH STREET (Lat: 35.483317,  Lng: -97.671511),  Route carried "on" structure: City street N2990,  Year Built: 1991,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 2,300 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 3,680 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: COUNTY LINE RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 14.0m (45.9ft),  Out-to-Out Width: 14.0m (45.9ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.52m (11.55ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2721,  Location: .7S .5W OF BESSIE (Lat: 35.376078,  Lng: -98.993831),  Route carried "on" structure: County highway N2240,  Year Built: 1930,  Status: Posted for load,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.2m (17.1ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Poor,  Channel: Fair,  Operating Rating: 9.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 5.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.58m (11.75ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $183,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $290,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2723,  Location: 2 BLOCKS E MEMORIAL&SEGER (Lat: 35.348464,  Lng: -98.673156),  Route carried "on" structure: County highway N2422,  Year Built: 1930,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2728,  Location: 3.E 1.2N OF RETROP (Lat: 35.176692,  Lng: -99.307653),  Route carried "on" structure: County highway N2060,  Year Built: 1930,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.3m (17.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.52m (11.55ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $180,000,  Roadway Improvement Cost: $99,000,  Total Project Cost: $285,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2871,  Location: 12.8 MI NE TEXAS S/L (Lat: 36.604786,  Lng: -101.607033),  Route carried "on" structure: US 54,  Year Built: 1930,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 6,900 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 11,040 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.032,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.8m (78.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 30.5m (100.1ft),  Out-to-Out Width: 53.0m (173.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 89.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 2875,  Location: .2N .7E 4.7S OF RENFROW (Lat: 36.856322,  Lng: -97.642517),  Route carried "on" structure: County highway N3010,  Year Built: 1930,  Status: Temporarily open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: POLECAT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Satisfactory,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.31m (14.14ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $220,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $350,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2879,  Location: 4.7E 6.2N OF NASH (Lat: 36.755739,  Lng: -97.965850),  Route carried "on" structure: County highway N2830,  Year Built: 1930,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 1.23m (4.04ft),  Average Daily Traffic: 173 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 277 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.976,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.9m (19.4ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.84m (12.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $196,000,  Roadway Improvement Cost: $108,000,  Total Project Cost: $312,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Discuss Oklahoma City, Oklahoma (OK) on our hugely popular Oklahoma forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.