Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Hoffman, North Carolina (NC)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 132Number of bridges
  • 627ft / 191mTotal length
  • $4,171,000Total costs
  • 112,551Total average daily traffic
  • 12,657Total average daily truck traffic
  • 259,470Total future (year 2036) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Hoffman
  • No street view available for this location

New bridges in Hoffman, NC - historical statistics
  • New bridges - historical statistics
  • 91950-1959
  • 481960-1969
  • 341970-1979
  • 21980-1989
  • 31990-1999
  • 82000-2009
  • 282010-2019
Reconstructed bridges in Hoffman, NC - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11980-1989
  • 11990-1999
  • 02000-2009
  • 22010-2019
Average Bridge Daily Traffic in Hoffman, NC
Average Bridge Truck Traffic in Hoffman, NC
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 8.5%Very good
  • 28.8%Good
  • 27.1%Satisfactory
  • 17.8%Fair
  • 8.5%Poor
  • 2.5%Serious
  • 2.5%Critical
  • 3.4%Imminent failure
  • 0.8%Failed
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 8.5%Very good
  • 47.5%Good
  • 19.5%Satisfactory
  • 11.0%Fair
  • 0.8%Poor
  • 5.1%Serious
  • 4.2%Critical
  • 3.4%Imminent failure
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 11.9%Very good
  • 22.0%Good
  • 19.5%Satisfactory
  • 13.6%Fair
  • 5.1%Poor
  • 9.3%Serious
  • 10.2%Critical
  • 8.5%Imminent failure
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 26.2%Very good
  • 33.3%Good
  • 22.2%Satisfactory
  • 10.3%Fair
  • 4.0%Poor
  • 2.4%Serious
  • 1.6%Critical
  • 0.8%Imminent failure
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 21.4%Good
  • 42.9%Satisfactory
  • 35.7%Fair
Find on map >>   Show street view

Structure Number: 510002,  Location: PU 833 899 (Lat: 35.135419,  Lng: -78.988550),  Route carried "on" structure: State highway ,  Year Built: 1976,  Status: Open,  Structure Length: 5.74m (18.83ft),  Average Daily Traffic: 14,260 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 40,000 (year 2042),  Design Load: HS 20+Mod,  Features Intersected: HONEYCUTT ROAD,  Facility Carried by Structure: SB ALL AMERICAN EX
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: Army,  Approaching Roadway Width: 12.3m (40.4ft),  Skew: 12 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.8m (101.0ft),  Curb-To-Curb Width: 12.3m (40.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 69.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.77m (22.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 510003,  Location: PU 828 899 (Lat: 35.135561,  Lng: -78.992781),  Route carried "on" structure: State highway ,  Year Built: 1976,  Status: Open,  Structure Length: 5.23m (17.16ft),  Average Daily Traffic: 14,260 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 36,500 (year 2042),  Features Intersected: REILLY ROAD,  Facility Carried by Structure: SB ALL AMERICAN EX
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Owner: Army,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 11 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.6m (84.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Inventory Rating: 61.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.24m (20.47ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 510231,  Location: PU 840 888 (Lat: 35.125831,  Lng: -78.980561),  Route carried "on" structure: Other road ,  Year Built: 1976,  Status: Open,  Structure Length: 7.25m (23.79ft),  Average Daily Traffic: 4,500 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 6,200 (year 2042),  Features Intersected: ALL AMERICAN EXPRESSWAY,  Facility Carried by Structure: GRUBER ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Lanes under structure: 5,  Owner: Army,  Approaching Roadway Width: 19.5m (64.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 37.9m (124.3ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 19.5m (64.0ft),  Out-to-Out Width: 23.3m (76.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 27.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 21.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 8.28m (27.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 510232,  Location: PU 837 897 (Lat: 35.132811,  Lng: -78.983819),  Route carried "on" structure: State highway ,  Year Built: 1976,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 37,000 (year 2020),  Truck Traffic: 13%,  Average Future Daily Traffic: 74,000 (year 2042),  Features Intersected: BEAVER CREEK,  Facility Carried by Structure: ALL AMERICAN EXP.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Owner: Army,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 54.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Underwater Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: 510233,  Location: PU 833 899 (Lat: 35.135639,  Lng: -78.988531),  Route carried "on" structure: State highway ,  Year Built: 1976,  Status: Open,  Structure Length: 5.74m (18.83ft),  Average Daily Traffic: 14,260 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 40,000 (year 2042),  Design Load: HS 20+Mod,  Features Intersected: HONEYCUTT ROAD,  Facility Carried by Structure: NB ALL AMERICAN EX
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 4,  Owner: Army,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 12 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.6m (100.4ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 60.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.77m (22.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 510234,  Location: PU 828 899 (Lat: 35.135831,  Lng: -78.993331),  Route carried "on" structure: State highway ,  Year Built: 1976,  Status: Open,  Structure Length: 5.24m (17.19ft),  Average Daily Traffic: 14,260 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 36,500 (year 2042),  Design Load: HS 20+Mod,  Features Intersected: REILLY ROAD,  Facility Carried by Structure: NB ALL AMERICAN EX
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Owner: Army,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 11 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.6m (84.0ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Inventory Rating: 61.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.27m (20.57ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1250016,  Location: 0.6 MI. W. JCT. SR1004 (Lat: 35.084075,  Lng: -79.582819),  Route carried "on" structure: State highway 1102,  Year Built: 1950,  Status: Posted for load,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 320 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 640 (year 2040),  Features Intersected: DROWNING CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 5.1m (16.7ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.4m (21.0ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.4m (17.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2021,  Underwater Inspection Date: March 2019,  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1250017,  Location: 0.7 MI. W. JCT. SR1004 (Lat: 35.083781,  Lng: -79.583403),  Route carried "on" structure: State highway 1102,  Year Built: 2011,  Status: Posted for load,  Structure Length: 1.06m (3.48ft),  Average Daily Traffic: 320 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 640 (year 2040),  Features Intersected: DROWNING CREEK OVERFLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 5.4m (17.7ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.1m (16.7ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 37.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1530052,  Location: 0.7 MI. S. JCT. SR1465 (Lat: 35.081997,  Lng: -79.589194),  Route carried "on" structure: State highway 1003,  Year Built: 1993,  Status: Open,  Structure Length: 2.49m (8.17ft),  Average Daily Traffic: 1,000 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,000 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: NAKED CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 11.8m (38.7ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1530056,  Location: 2.1 MI. N. JCT. US1 (Lat: 35.066056,  Lng: -79.549972),  Route carried "on" structure: State highway 1004,  Year Built: 2017,  Status: Open,  Structure Length: 3.20m (10.50ft),  Average Daily Traffic: 650 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,300 (year 2040),  Design Load: HL 93,  Features Intersected: DROWNING CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 20.4m (66.9ft),  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 57.1 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: Febuary 2021,  Underwater Inspection Date: July 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: DAPFORBRA00000G,  Location: PU 786 946 (Lat: 35.178300,  Lng: -79.037250),  Route carried "on" structure: Other road ,  Year Built: 1975,  Status: Open,  Structure Length: 0.93m (3.05ft),  Average Daily Traffic: 10 (year 2020),  Average Future Daily Traffic: 10 (year 2042),  Features Intersected: MCPHERSON CREEK,  Facility Carried by Structure: UNKNOWN RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.9m (12.8ft)

Condition: Channel: Good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.60m (5.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00000H,  Location: PU 799 988 (Lat: 35.217169,  Lng: -79.023131),  Route carried "on" structure: Other road ,  Year Built: 1975,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 2 (year 2020),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: MUDDY CREEK,  Facility Carried by Structure: NURSERY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 8.7 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 8.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00000I,  Location: PU 793 995 (Lat: 35.221581,  Lng: -79.030031),  Route carried "on" structure: Other road ,  Year Built: 2013,  Status: Open,  Structure Length: 1.44m (4.72ft),  Average Daily Traffic: 1 (year 2020),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: MUDDY CREEK,  Facility Carried by Structure: TRAIL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.5m (11.5ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.6m (41.3ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.12m (6.96ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: DAPFORBRA00000J,  Location: PU 783 000 (Lat: 35.226819,  Lng: -79.040831),  Route carried "on" structure: Other road ,  Year Built: 1960,  Status: Closed,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 1 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: MUDDY CREEK,  Facility Carried by Structure: TRAIL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Imminent failure,  Superstructure: Imminent failure,  Substructure: Imminent failure,  Channel: Good,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.22m (4.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2014,  Bridge Improvement Cost: $95,000,  Roadway Improvement Cost: $2,000,  Total Project Cost: $97,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA00000K,  Location: PU 790 998 (Lat: 35.224831,  Lng: -79.033000),  Route carried "on" structure: Other road ,  Year Built: 1960,  Status: Closed,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 2 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: OVERHILLS LAKE,  Facility Carried by Structure: ABANDON RAILROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 2.7m (8.9ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 3.3m (10.8ft),  Out-to-Out Width: 3.9m (12.8ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Critical,  Channel: Fair,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.89m (6.20ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: August 2014,  Underwater Inspection Date: August 2012,  Bridge Improvement Cost: $165,000,  Roadway Improvement Cost: $2,000,  Total Project Cost: $167,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA00000M,  Location: PU 741 821 (Lat: 35.066739,  Lng: -79.090850),  Route carried "on" structure: Other road ,  Year Built: 1955,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 2 (year 2020),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: LITTLE ROCKFISH CREEK,  Facility Carried by Structure: CHICKEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 15.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 15.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Underwater Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00000P,  Location: PU 703 899 (Lat: 35.138211,  Lng: -79.130650),  Route carried "on" structure: Other road ,  Year Built: 1970,  Year Reconstructed: 2019,  Status: Closed,  Structure Length: 0.78m (2.56ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 8 (year 2042),  Features Intersected: JUMPING RUN CREEK,  Facility Carried by Structure: FB6
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.6m (8.5ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 3.3m (10.8ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: October 2020,  Underwater Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA00000R,  Location: PU 701 822 (Lat: 35.068669,  Lng: -79.134000),  Route carried "on" structure: Other road ,  Year Built: 1960,  Status: Closed,  Structure Length: 1.08m (3.54ft),  Average Daily Traffic: 2 (year 2018),  Average Future Daily Traffic: 2 (year 2040),  Features Intersected: PUPPY CREEK,  Facility Carried by Structure: CHICKEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft)

Condition: Channel: Poor,  Culverts: Fair,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2018,  Underwater Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2018)
Find on map >>   Show street view

Structure Number: DAPFORBRA00000T,  Location: PU 702 815 (Lat: 35.062119,  Lng: -79.132731),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 2 (year 2020),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: PUPPY CREEK,  Facility Carried by Structure: FB5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Aluminum, Iron,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.0m (16.4ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 17.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.83m (6.00ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Underwater Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00003,  Location: PU 682 917 (Lat: 35.154661,  Lng: -79.153661),  Route carried "on" structure: Other road ,  Year Built: 1990,  Status: Closed,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FIREBREAK 15
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 3.8m (12.5ft),  Out-to-Out Width: 4.1m (13.5ft)

Condition: Deck: Serious,  Superstructure: Critical,  Substructure: Critical,  Channel: Poor,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.55m (8.37ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Critical Feature Inspection Date: July 2020,  Underwater Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000031,  Location: PU 680 924 (Lat: 35.160319,  Lng: -79.155169),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 2 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FB12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.0m (9.8ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Critical,  Superstructure: Fair,  Substructure: Critical,  Channel: Poor,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.74m (5.71ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2014,  Bridge Improvement Cost: $130,000,  Roadway Improvement Cost: $2,000,  Total Project Cost: $132,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000036,  Location: PU 788 821 (Lat: 35.067931,  Lng: -79.039300),  Route carried "on" structure: Other road ,  Year Built: 2015,  Status: Open,  Structure Length: 1.14m (3.74ft),  Average Daily Traffic: 10 (year 2014),  Average Future Daily Traffic: 10 (year 2042),  Design Load: Greater than HL93,  Features Intersected: BONES CREEK,  Facility Carried by Structure: F5B ASP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 2.7m (8.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 3.3m (10.8ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.81m (5.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: DAPFORBRA000037,  Location: PU 703 903 (Lat: 35.140969,  Lng: -79.130289),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 2 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: JUMPING RUN CREEK,  Facility Carried by Structure: FB 5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Serious,  Substructure: Imminent failure,  Channel: Fair,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: August 2014,  Underwater Inspection Date: August 2012,  Bridge Improvement Cost: $115,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $116,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000038,  Location: PU 709 919 (Lat: 35.155019,  Lng: -79.123161),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2038),  Features Intersected: JUMPING RUN CREEK,  Facility Carried by Structure: FB2
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 3.3m (10.8ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 13.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 9.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.07m (6.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000039,  Location: PU 680 931 (Lat: 35.167131,  Lng: -79.155389),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2038),  Features Intersected: MILL CREEK,  Facility Carried by Structure: FIREBREAK 10
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.2m (10.5ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Serious,  Superstructure: Serious,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 9.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 7.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000065,  Location: PU 681 921 (Lat: 35.157839,  Lng: -79.154339),  Route carried "on" structure: Other road ,  Year Built: 2015,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 2 (year 2020),  Average Future Daily Traffic: 8 (year 2042),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FB 13
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.7m (12.1ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.2m (43.3ft),  Curb-To-Curb Width: 3.3m (10.8ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 42.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.11m (6.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: DAPFORBRA00008,  Location: PU 680 926 (Lat: 35.162589,  Lng: -79.155500),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 1.30m (4.27ft),  Average Daily Traffic: 2 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FIREBREAK 11
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.1m (13.5ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Poor,  Superstructure: Critical,  Substructure: Serious,  Channel: Fair,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.97m (6.46ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2014,  Bridge Improvement Cost: $160,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $161,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000085,  Location: PU 680 929 (Lat: 35.165531,  Lng: -79.155539),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 0.89m (2.92ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2038),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FB 10
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.2m (10.5ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 7.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 5.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.56m (5.12ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000098,  Location: PU 681 912 (Lat: 35.149939,  Lng: -79.155111),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2038),  Features Intersected: DEEP CREEK,  Facility Carried by Structure: FB 17
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.2m (10.5ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 7.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 5.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 1.83m (6.00ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: June 2016,  Underwater Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000099,  Location: PU 711 925 (Lat: 35.160089,  Lng: -79.121269),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 1 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: JUMPING RUN CREEK,  Facility Carried by Structure: FB 1
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.8m (12.5ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Imminent failure,  Channel: Satisfactory,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.01m (6.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2014,  Bridge Improvement Cost: $135,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $136,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA0000U2,  Location: RANGE NTA6 (W) (Lat: 35.185419,  Lng: -79.055489),  Route carried "on" structure: Other road ,  Year Built: 1960,  Status: Open,  Structure Length: 5.94m (19.49ft),  Average Daily Traffic: 1 (year 2020),  Average Future Daily Traffic: 2 (year 2042),  Features Intersected: LITTLE RIVER,  Facility Carried by Structure: DELISHI ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 29.0m (95.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 20.7 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 15.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 7.01m (23.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: DAPFORBRA000101,  Location: PU 685 934 (Lat: 35.171350,  Lng: -79.149211),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 2 (year 2014),  Average Future Daily Traffic: 2 (year 2036),  Features Intersected: TRAINING AREA STREAM,  Facility Carried by Structure: FIRE BREAK L RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 4.1m (13.5ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.1m (10.2ft),  Curb-To-Curb Width: 4.1m (13.5ft),  Out-to-Out Width: 4.1m (13.5ft)

Condition: Deck: Imminent failure,  Superstructure: Critical,  Substructure: Critical,  Channel: Fair,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2014,  Bridge Improvement Cost: $126,000,  Roadway Improvement Cost: $2,000,  Total Project Cost: $128,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA000108,  Location: PU 702 819 (Lat: 35.066139,  Lng: -79.133000),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Closed,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 2 (year 2016),  Average Future Daily Traffic: 2 (year 2038),  Features Intersected: PUPPY CREEK,  Facility Carried by Structure: FB6
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 3.4m (11.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 1.5m (4.9ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.22m (4.00ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: June 2016,  Underwater Inspection Date: June 2016,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: DAPFORBRA00902,  Location: PU 653 959 (Lat: 35.192439,  Lng: -79.184169),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 3.81m (12.50ft),  Average Daily Traffic: 1,000 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: LITTLE RIVER,  Facility Carried by Structure: MORRISON BRIDGE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.7m (44.9ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 42.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 4.75m (15.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: DAPFORBRA009702,  Location: PU 743 944 (Lat: 35.177439,  Lng: -79.086000),  Route carried "on" structure: Other road ,  Year Built: 1990,  Status: Posted for load,  Structure Length: 3.05m (10.01ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 30%,  Average Future Daily Traffic: 100 (year 2042),  Features Intersected: LITTLE RIVER,  Facility Carried by Structure: JOHN NEILL SHAW RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Army,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 4.1m (13.5ft),  Out-to-Out Width: 5.4m (17.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 43.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 33.9 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.89m (12.76ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Critical Feature Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Steel plate,  Wearing Surface/Protective System: Wearing Surface: Other,  Membrane: Other,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR01,  Location: PU 784 843 (Lat: 35.085689,  Lng: -79.042419),  Route carried "on" structure: Other road ,  Year Built: 1955,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 1,000 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: BONES CREEK,  Facility Carried by Structure: CHICKEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 9.6m (31.5ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 97.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 97.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.35m (4.43ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Underwater Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR02,  Location: PU 741 808 (Lat: 35.054719,  Lng: -79.091111),  Route carried "on" structure: Other road ,  Year Built: 1952,  Status: Open,  Structure Length: 1.53m (5.02ft),  Average Daily Traffic: 1,000 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: LITTLE ROCKFISH CREEK,  Facility Carried by Structure: PLANK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 13.6m (44.6ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 8,  Length of Maximum Span: 1.5m (4.9ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 42.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.21m (7.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR03,  Location: PU 706 802 (Lat: 35.049719,  Lng: -79.129439),  Route carried "on" structure: Other road ,  Year Built: 1955,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 1,000 (year 2020),  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: PUPPY CREEK,  Facility Carried by Structure: PLANK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 54.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR04,  Location: PU 594 808 (Lat: 35.058331,  Lng: -79.252219),  Route carried "on" structure: Other road ,  Year Built: 1952,  Year Reconstructed: 2019,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,000 (year 2020),  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: JUNIPER CREEK,  Facility Carried by Structure: PLANK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 7.4m (24.3ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 97.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 97.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR05,  Location: RANGE GG2 (S) AREA (Lat: 35.059111,  Lng: -79.278689),  Route carried "on" structure: Other road ,  Year Built: 1952,  Status: Open,  Structure Length: 1.45m (4.76ft),  Average Daily Traffic: 1,000 (year 2020),  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: ROCKFISH CREEK,  Facility Carried by Structure: PLANK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 97.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 97.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: DAPFORBRA00BR07,  Location: PU 632 836 (Lat: 35.081731,  Lng: -79.209761),  Route carried "on" structure: Other road ,  Year Built: 2014,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 1,000 (year 2020),  Average Future Daily Traffic: 2,000 (year 2042),  Features Intersected: NICHOLSON CREEK,  Facility Carried by Structure: CHICKEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.4m (44.0ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.04m (6.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels