Bridge Statistics for El Reno, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 103Number of bridges
  • 942ft / 287mTotal length
  • $110,698,000Total costs
  • 771,647Total average daily traffic
  • 297,177Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for El Reno
  • No street view available for this location

New bridges in El Reno, OK - historical statistics
  • New bridges - historical statistics
  • 51920-1929
  • 11930-1939
  • 31940-1949
  • 41950-1959
  • 451960-1969
  • 81970-1979
  • 71980-1989
  • 51990-1999
  • 142000-2009
  • 92010-2019
  • 22020-2022
Reconstructed bridges in El Reno, OK - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11950-1959
  • 01960-1969
  • 01970-1979
  • 01980-1989
  • 21990-1999
  • 32000-2009
Average Bridge Daily Traffic in El Reno, OK
Average Bridge Truck Traffic in El Reno, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 12.5%Very good
  • 32.8%Good
  • 40.6%Satisfactory
  • 6.3%Fair
  • 1.6%Poor
  • 6.3%Failed
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 7.8%Excellent
  • 20.3%Very good
  • 28.1%Good
  • 29.7%Satisfactory
  • 6.3%Fair
  • 1.6%Poor
  • 6.3%Failed
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 18.8%Very good
  • 21.9%Good
  • 26.6%Satisfactory
  • 23.4%Fair
  • 1.6%Poor
  • 1.6%Serious
  • 6.3%Failed
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 29.4%Very good
  • 29.4%Good
  • 29.4%Satisfactory
  • 8.8%Fair
  • 2.9%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 8.7%Very good
  • 52.2%Good
  • 34.8%Satisfactory
  • 4.3%Fair
Find on map >>   Show street view

Structure Number: 1511,  Location: E0990N2830009 (Lat: 35.580347,  Lng: -97.942267),  Route carried "on" structure: City street E0990,  Year Built: 1925,  Year Reconstructed: 1998,  Status: Temporarily open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.4m (21.0ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Fair,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.58m (11.75ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $183,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $290,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 1538,  Location: 4. N .1 S OF EL RENO (Lat: 35.579875,  Lng: -97.941208),  Route carried "on" structure: County highway N2840,  Year Built: 1925,  Status: Posted for load,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 7.0m (23.0ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 15.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 9.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.08m (13.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $208,000,  Roadway Improvement Cost: $115,000,  Total Project Cost: $331,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1633,  Location: .2W OF EL RENO (Lat: 35.561422,  Lng: -97.959250),  Route carried "on" structure: County highway N2830,  Year Built: 1925,  Status: Closed,  Structure Length: 14.94m (49.02ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: N. CANADIAN RIVER
Minimum Vertical Clearance: 4.66m (15.29ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 37.2m (122.0ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.8m (19.0ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Satisfactory,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 14.94m (49.02ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $763,000,  Roadway Improvement Cost: $420,000,  Total Project Cost: $1,200,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1778,  Location: 3.N 4.9W UNION CITY (Lat: 35.435122,  Lng: -98.024136),  Route carried "on" structure: County highway E1090,  Year Built: 1927,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft),  Curb-To-Curb Width: 4.4m (14.4ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 34.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $80,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 2255,  Location: 3.5 MI. E. JCT. I40 (Lat: 35.536950,  Lng: -97.994139),  Route carried "on" structure: Business State highway 40B,  Year Built: 1929,  Year Reconstructed: 1962,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 4,100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 6,560 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: I-40 BUS.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.824,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 47.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 3578,  Location: 1.E .1N 81; I40 (Lat: 35.504378,  Lng: -97.919297),  Route carried "on" structure: City street N2850,  Year Built: 1932,  Status: Posted for load,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.3m (17.4ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Poor,  Channel: Poor,  Operating Rating: 24.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 14.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $256,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 9575,  Location: N2890E1020009 (Lat: 35.523622,  Lng: -97.848744),  Route carried "on" structure: City street N2890,  Year Built: 1941,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 400 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 640 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 9989,  Location: E1030N2880007 (Lat: 35.522378,  Lng: -97.853900),  Route carried "on" structure: City street E1030,  Year Built: 1942,  Year Reconstructed: 2008,  Status: Posted for load,  Structure Length: 1.92m (6.30ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: SIXMILE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 5.4m (17.7ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 28.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 4.88m (16.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $249,000,  Roadway Improvement Cost: $137,000,  Total Project Cost: $397,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 12928,  Location: 3.3 MI. N. JCT. SH 66 (Lat: 35.580578,  Lng: -97.959028),  Route carried "on" structure: US 81,  Year Built: 1953,  Year Reconstructed: 2003,  Status: Open,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 5,900 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 9,440 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.229,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.7m (67.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 13568,  Location: IN EL-RENO (Lat: 35.532186,  Lng: -97.962778),  Route carried "on" structure: Business State highway 40B,  Year Built: 1956,  Status: Open,  Structure Length: 0.78m (2.56ft),  Average Daily Traffic: 10,000 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 16,000 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK,  Facility Carried by Structure: I-40 BUS.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.834,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 1.5m (4.9ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.82m (2.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 13636,  Location: 100' W. OF CNTRY CLUB RD (Lat: 35.532189,  Lng: -97.972797),  Route carried "on" structure: Business State highway 40B,  Year Built: 1956,  Status: Open,  Structure Length: 1.89m (6.20ft),  Average Daily Traffic: 8,600 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 13,760 (year 2040),  Design Load: HS 20,  Features Intersected: FOUR MILE CREEK,  Facility Carried by Structure: I-40 BUS.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.916,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.2m (17.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.95m (6.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $366,000,  Roadway Improvement Cost: $605,000,  Total Project Cost: $1,026,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14555,  Location: 2.5 MI N OF BANNER (Lat: 35.544161,  Lng: -97.848736),  Route carried "on" structure: City street 3961,  Year Built: 1960,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 10.459,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Serious,  Channel: Good,  Operating Rating: 82.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 2.98m (9.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $152,000,  Roadway Improvement Cost: $84,000,  Total Project Cost: $241,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 14653,  Location: .4 MI E US 81 (Lat: 35.529644,  Lng: -97.943847),  Route carried "on" structure: City street 3870,  Year Built: 1960,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.655,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.1m (3.6ft),  Right: 1.1m (3.6ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 15235,  Location: 13.7 MI. E. CADDO CO (Lat: 35.529522,  Lng: -98.070369),  Route carried "on" structure: Interstate 40,  Year Built: 1961,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 27,800 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 44,480 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 22.027,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 13 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15236,  Location: 13.8 MI. E. CADDO CO (Lat: 35.529519,  Lng: -98.068111),  Route carried "on" structure: Interstate 40,  Year Built: 1961,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 27,800 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 44,480 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 22.236,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 57.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15318,  Location: 12.2 MI. E. CADDO CO (Lat: 35.529667,  Lng: -98.096475),  Route carried "on" structure: County highway N2750,  Year Built: 1961,  Status: Open,  Structure Length: 3.35m (10.99ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: H 15,  Features Intersected: I-40 WB UNDER,  Facility Carried by Structure: COURTNEY RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.661,  Lanes on structure: 2,  Lanes under structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.4m (44.0ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 16.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 5.62m (18.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $488,000,  Roadway Improvement Cost: $805,000,  Total Project Cost: $1,365,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 15319,  Location: 12.2 MI. E. CADDO CO (Lat: 35.528342,  Lng: -98.096475),  Route carried "on" structure: County highway N2750,  Year Built: 1961,  Status: Open,  Structure Length: 3.35m (10.99ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: H 15,  Features Intersected: I-40 EB UNDER,  Facility Carried by Structure: COURTNEY RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.661,  Lanes on structure: 2,  Lanes under structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.4m (44.0ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 16.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.60m (18.37ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $486,000,  Roadway Improvement Cost: $802,000,  Total Project Cost: $1,362,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 15346,  Location: 14.2 MI. E. CADDO CO (Lat: 35.529544,  Lng: -98.061125),  Route carried "on" structure: County highway 948C,  Year Built: 1961,  Status: Open,  Structure Length: 5.24m (17.19ft),  Average Daily Traffic: 101 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 15,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: FORT RENO RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 22.880,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 16.8m (55.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of replacement,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 8.40m (27.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $689,000,  Roadway Improvement Cost: $1,137,000,  Total Project Cost: $1,929,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1536,  Location: JCT. US270 & I40 (Lat: 35.529153,  Lng: -98.114214),  Route carried "on" structure: US 270,  Year Built: 1961,  Status: Open,  Structure Length: 5.39m (17.68ft),  Average Daily Traffic: 2,800 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 4,480 (year 2040),  Design Load: H 20,  Features Intersected: I-40 UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 41.898,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 17.4m (57.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 8.40m (27.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $689,000,  Roadway Improvement Cost: $1,137,000,  Total Project Cost: $1,929,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 15366,  Location: 13.2 MI. E. CADDO CO (Lat: 35.529483,  Lng: -98.078836),  Route carried "on" structure: County highway 946C,  Year Built: 1961,  Status: Open,  Structure Length: 5.61m (18.41ft),  Average Daily Traffic: 265 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 424 (year 2040),  Design Load: H 15,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: HEASTON RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 21.271,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 18.0m (59.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 8.41m (27.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $690,000,  Roadway Improvement Cost: $1,138,000,  Total Project Cost: $1,931,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 15369,  Location: 15.2 MI. E. CADDO CO (Lat: 35.529331,  Lng: -98.044133),  Route carried "on" structure: Ramp State highway 40B,  Year Built: 1961,  Status: Open,  Structure Length: 6.64m (21.78ft),  Average Daily Traffic: 1,900 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,040 (year 2040),  Design Load: HS 20,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: I-40 BUS. RAMP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 7.4m (24.3ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 20.7m (67.9ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.0m (26.2ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.92m (29.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,259,000,  Roadway Improvement Cost: $2,078,000,  Total Project Cost: $3,526,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 15484,  Location: 1.9 MI. E. JCT. I40 (Lat: 35.537022,  Lng: -98.023731),  Route carried "on" structure: Business State highway 40B,  Year Built: 1962,  Status: Open,  Structure Length: 1.23m (4.04ft),  Average Daily Traffic: 2,300 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,680 (year 2040),  Design Load: HS 20,  Features Intersected: TARGET CREEK,  Facility Carried by Structure: I-40 BUS.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.154,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 22.1m (72.5ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Out-to-Out Width: 40.4m (132.5ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $356,000,  Roadway Improvement Cost: $588,000,  Total Project Cost: $998,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 16601,  Location: 1.6 MI N OF BANNER (Lat: 35.529994,  Lng: -97.848747),  Route carried "on" structure: City street 3961,  Year Built: 1970,  Status: Open,  Structure Length: 6.42m (21.06ft),  Average Daily Traffic: 400 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 640 (year 2040),  Design Load: HS 20,  Features Intersected: N. CANADIAN RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.528,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 23.9m (78.4ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.49m (31.14ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $484,000,  Roadway Improvement Cost: $266,000,  Total Project Cost: $755,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 16685,  Location: 15.8 MI. E. CADDO CO (Lat: 35.525958,  Lng: -98.033469),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 0.97m (3.18ft),  Average Daily Traffic: 27,300 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 43,680 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 25.469,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 90.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $326,000,  Roadway Improvement Cost: $538,000,  Total Project Cost: $913,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16687,  Location: 17.8 MI. E. CADDO CO (Lat: 35.514822,  Lng: -98.000314),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 13,200 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 21,120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.736,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.0m (42.7ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 61.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16688,  Location: 17.8 MI. E. CADDO CO (Lat: 35.514033,  Lng: -98.000658),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 14,900 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 23,840 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.736,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.9m (42.3ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 90.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16689,  Location: 2.05E OF I-40 & US81 (Lat: 35.500322,  Lng: -97.900881),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 40,700 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 65,120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.053,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 34.1m (111.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 56.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $579,000,  Total Project Cost: $982,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1669,  Location: 24.0 MI. E. CADDO CO (Lat: 35.500597,  Lng: -97.893425),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 1.03m (3.38ft),  Average Daily Traffic: 40,700 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 65,120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.745,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 75.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $392,000,  Roadway Improvement Cost: $647,000,  Total Project Cost: $1,098,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16724,  Location: 20.6 MI. E. CADDO CO (Lat: 35.501722,  Lng: -97.955061),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 13,200 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 21,120 (year 2040),  Design Load: HS 20,  Features Intersected: CHOCTAW RD. UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 33.128,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.75m (18.86ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $737,000,  Roadway Improvement Cost: $1,216,000,  Total Project Cost: $2,064,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 16725,  Location: 20.6 MI. E. CADDO CO (Lat: 35.501419,  Lng: -97.955064),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 13,200 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 21,120 (year 2040),  Design Load: HS 20,  Features Intersected: CHOCTAW RD. UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 33.128,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.75m (18.86ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $737,000,  Roadway Improvement Cost: $1,216,000,  Total Project Cost: $2,064,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 1674,  Location: 22.3 MI. E. CADDO CO (Lat: 35.501378,  Lng: -97.925225),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 3.66m (12.01ft),  Average Daily Traffic: 18,800 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 30,080 (year 2040),  Design Load: HS 20,  Features Intersected: SIX MILE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.832,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $579,000,  Roadway Improvement Cost: $955,000,  Total Project Cost: $1,621,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 16741,  Location: 22.3 MI. E. CADDO CO (Lat: 35.501086,  Lng: -97.925225),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 3.66m (12.01ft),  Average Daily Traffic: 20,350 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 32,560 (year 2040),  Design Load: HS 20,  Features Intersected: SIX MILE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.832,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $579,000,  Roadway Improvement Cost: $955,000,  Total Project Cost: $1,621,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 1675,  Location: 20.8 MI. E. CADDO CO (Lat: 35.501036,  Lng: -97.950331),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 4.63m (15.19ft),  Average Daily Traffic: 14,900 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 23,840 (year 2040),  Design Load: HS 20,  Features Intersected: UP R.R. UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 33.564,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $880,000,  Roadway Improvement Cost: $1,452,000,  Total Project Cost: $2,463,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 16772,  Location: 22.6 MI. E. CADDO CO (Lat: 35.500992,  Lng: -97.919361),  Route carried "on" structure: County highway N2850,  Year Built: 1966,  Status: Posted for load,  Structure Length: 5.52m (18.11ft),  Average Daily Traffic: 101 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 162 (year 2040),  Design Load: H 15,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: N285.0
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 36.363,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 17.7m (58.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 8.40m (27.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $689,000,  Roadway Improvement Cost: $1,137,000,  Total Project Cost: $1,929,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1678,  Location: I40 & US81 (Lat: 35.501039,  Lng: -97.937478),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 5.88m (19.29ft),  Average Daily Traffic: 14,900 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 23,840 (year 2040),  Design Load: HS 20,  Features Intersected: U.S. 81 UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 34.722,  Lanes on structure: 2,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 19.5m (64.0ft),  Curb-To-Curb Width: 13.6m (44.6ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.47m (21.23ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: April 2021,  Other Special Inspection Date: November 2021,  Bridge Improvement Cost: $830,000,  Roadway Improvement Cost: $1,369,000,  Total Project Cost: $2,323,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 16781,  Location: I40 & US81 (Lat: 35.501378,  Lng: -97.937478),  Route carried "on" structure: Interstate 40,  Year Built: 1966,  Status: Open,  Structure Length: 5.88m (19.29ft),  Average Daily Traffic: 15,550 (year 2020),  Truck Traffic: 43%,  Average Future Daily Traffic: 24,880 (year 2040),  Design Load: HS 20,  Features Intersected: U.S. 81 UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 34.722,  Lanes on structure: 2,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 19.5m (64.0ft),  Curb-To-Curb Width: 13.7m (44.9ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.47m (21.23ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: April 2021,  Other Special Inspection Date: November 2021,  Bridge Improvement Cost: $830,000,  Roadway Improvement Cost: $1,369,000,  Total Project Cost: $2,323,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Low Slump Concrete,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 16786,  Location: 16.6 MI. E. CADDO CO (Lat: 35.521647,  Lng: -98.021778),  Route carried "on" structure: City street N2790,  Year Built: 1966,  Status: Open,  Structure Length: 6.16m (20.21ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 15,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: ELM STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.644,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 20.4m (66.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 29.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.31m (27.26ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $683,000,  Roadway Improvement Cost: $1,127,000,  Total Project Cost: $1,912,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 16791,  Location: 19.5 MI. E. CADDO CO (Lat: 35.507614,  Lng: -97.972736),  Route carried "on" structure: City street 3861,  Year Built: 1966,  Status: Open,  Structure Length: 6.68m (21.92ft),  Average Daily Traffic: 300 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 480 (year 2040),  Design Load: HS 20,  Features Intersected: I-40 UNDER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 31.376,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 13.1m (43.0ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 22.9m (75.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 13.1m (43.0ft),  Out-to-Out Width: 14.1m (46.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.94m (26.05ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,019,000,  Roadway Improvement Cost: $1,682,000,  Total Project Cost: $2,853,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 16798,  Location: 25.6 MI. E. CADDO CO (Lat: 35.500169,  Lng: -97.866433),  Route carried "on" structure: County highway N2880,  Year Built: 1966,  Status: Open,  Structure Length: 7.38m (24.21ft),  Average Daily Traffic: 120 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 192 (year 2040),  Design Load: H 15,  Features Intersected: I-40 UNDER,  Facility Carried by Structure: MANNING RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 41.190,  Lanes on structure: 2,  Lanes under structure: 6,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 2,  Length of Maximum Span: 18.0m (59.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 31.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.43m (27.66ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $691,000,  Roadway Improvement Cost: $1,140,000,  Total Project Cost: $1,935,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete