Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Monroe, Georgia (GA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 51Number of bridges
  • 374ft / 114mTotal length
  • $23,764,000Total costs
  • 397,049Total average daily traffic
  • 12,538Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Monroe
  • No street view available for this location

New bridges in Monroe, GA - historical statistics
  • New bridges - historical statistics
  • 31930-1939
  • 11940-1949
  • 71950-1959
  • 111960-1969
  • 71970-1979
  • 71980-1989
  • 51990-1999
  • 22020-2022
Average Bridge Daily Traffic in Monroe, GA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.8%Very good
  • 58.8%Good
  • 29.4%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 17.6%Very good
  • 58.8%Good
  • 11.8%Satisfactory
  • 11.8%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 11.8%Very good
  • 47.1%Good
  • 29.4%Satisfactory
  • 5.9%Fair
  • 5.9%Serious
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 20.0%Very good
  • 17.1%Good
  • 54.3%Satisfactory
  • 8.6%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 61.5%Good
  • 30.8%Satisfactory
  • 7.7%Fair
Find on map >>   Show street view

Structure Number: 2970001,  Location: 2.5 MI E OF LOGANVILLE (Lat: 33.829628,  Lng: -83.858978),  Route carried "on" structure: US 78,  Year Built: 1985,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 23,380 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 35,070 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: BIG FLAT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Skew: 12 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.4m (11.2ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $139,000,  Roadway Improvement Cost: $14,000,  Total Project Cost: $208,000
Find on map >>   Show street view

Structure Number: 2970002,  Location: 3 MI E OF BETWEEN (Lat: 33.804639,  Lng: -83.759094),  Route carried "on" structure: US 78,  Year Built: 1950,  Status: Open,  Structure Length: 6.89m (22.60ft),  Average Daily Traffic: 19,650 (year 2012),  Truck Traffic: 5%,  Average Future Daily Traffic: 29,475 (year 2032),  Design Load: HS 20,  Features Intersected: ALCOVY RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.093,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 10 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 48.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 13.32m (43.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $883,000,  Roadway Improvement Cost: $88,000,  Total Project Cost: $1,325,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970003,  Location: 2 MI W OF MONROE (Lat: 33.802819,  Lng: -83.749319),  Route carried "on" structure: Business State highway 10,  Year Built: 1964,  Status: Open,  Structure Length: 6.46m (21.19ft),  Average Daily Traffic: 9,090 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 13,635 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 10 EBL (US 78)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 23.2m (76.1ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 8.0m (26.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 29.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $602,000,  Roadway Improvement Cost: $60,000,  Total Project Cost: $904,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970004,  Location: IN WEST MONROE (Lat: 33.791869,  Lng: -83.736139),  Route carried "on" structure: Business State highway 10,  Year Built: 1975,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 16,030 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 24,045 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: MOUNTAIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 59.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $102,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $152,000
Find on map >>   Show street view

Structure Number: 2970005,  Location: 1.9 MI E OF MONROE (Lat: 33.809975,  Lng: -83.687044),  Route carried "on" structure: US 78,  Year Built: 1978,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 21,140 (year 2012),  Truck Traffic: 10%,  Average Future Daily Traffic: 31,710 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: JACKS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 24.140,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 19.2m (63.0ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $193,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $290,000
Find on map >>   Show street view

Structure Number: 2970008,  Location: 1 MI NW OF MONROE (Lat: 33.801958,  Lng: -83.740447),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 9,670 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 14,505 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: MOUNTAIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.093,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $127,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $190,000
Find on map >>   Show street view

Structure Number: 2970009,  Location: IN WEST MONROE (Lat: 33.801989,  Lng: -83.736989),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 5.30m (17.39ft),  Average Daily Traffic: 18,920 (year 2012),  Truck Traffic: 8%,  Average Future Daily Traffic: 28,380 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 138
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.703,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 13 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $680,000,  Roadway Improvement Cost: $68,000,  Total Project Cost: $1,020,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 297001,  Location: IN WEST MONROE (Lat: 33.802169,  Lng: -83.736850),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 5.06m (16.60ft),  Average Daily Traffic: 18,920 (year 2012),  Truck Traffic: 8%,  Average Future Daily Traffic: 28,380 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 138
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.703,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 13 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.3m (60.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.3m (33.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $649,000,  Roadway Improvement Cost: $65,000,  Total Project Cost: $973,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970011,  Location: IN NORTH MONROE (Lat: 33.805428,  Lng: -83.709319),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 4.45m (14.60ft),  Average Daily Traffic: 17,520 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,280 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: M-3301 E MARABLE STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.312,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 12 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.9m (62.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 50.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $570,000,  Roadway Improvement Cost: $57,000,  Total Project Cost: $856,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970012,  Location: IN NORTH MONROE (Lat: 33.805589,  Lng: -83.709169),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 4.82m (15.81ft),  Average Daily Traffic: 17,520 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,280 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: M-3301 E MARABLE STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.312,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 12 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.9m (62.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 47.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $617,000,  Roadway Improvement Cost: $62,000,  Total Project Cost: $926,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970013,  Location: IN NW MONROE (Lat: 33.804208,  Lng: -83.696847),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 5.49m (18.01ft),  Average Daily Traffic: 17,520 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,280 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 10 BUS WBL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.921,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 13 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 20.7m (67.9ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 30.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $703,000,  Roadway Improvement Cost: $70,000,  Total Project Cost: $1,055,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970014,  Location: IN NW MONROE (Lat: 33.804408,  Lng: -83.696747),  Route carried "on" structure: US 78,  Year Built: 1964,  Status: Open,  Structure Length: 5.12m (16.80ft),  Average Daily Traffic: 17,520 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,280 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 10 BUS WBL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.921,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 13 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.9m (62.0ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 31.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $656,000,  Roadway Improvement Cost: $66,000,  Total Project Cost: $985,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970017,  Location: 1 MI NW OF MONROE (Lat: 33.806239,  Lng: -83.722528),  Route carried "on" structure: State highway 11,  Year Built: 1964,  Status: Open,  Structure Length: 7.77m (25.49ft),  Average Daily Traffic: 14,170 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 21,255 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SR 10 (US 78)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.921,  Lanes on structure: 4,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 25.9m (85.0ft),  Skew: 33 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 20.7m (67.9ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 17.1m (56.1ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 29.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,540,000,  Roadway Improvement Cost: $154,000,  Total Project Cost: $2,310,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970018,  Location: 4.75 MI N OF MONROE (Lat: 33.857878,  Lng: -83.721519),  Route carried "on" structure: State highway 11,  Year Built: 1934,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 9,410 (year 2012),  Truck Traffic: 10%,  Average Future Daily Traffic: 14,115 (year 2032),  Design Load: H 15,  Features Intersected: SHOALS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.359,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.62m (25.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $145,000,  Roadway Improvement Cost: $14,000,  Total Project Cost: $217,000
Find on map >>   Show street view

Structure Number: 297002,  Location: 1 MI NW OF LOGANVILLE (Lat: 33.848489,  Lng: -83.894700),  Route carried "on" structure: State highway 81,  Year Built: 1950,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 9,870 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 14,805 (year 2032),  Design Load: H 15,  Features Intersected: BIG FLAT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.312,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.4m (11.2ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 59.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $94,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $141,000
Find on map >>   Show street view

Structure Number: 2970025,  Location: 2.9 MI NW OF GOOD HOPE (Lat: 33.796558,  Lng: -83.654989),  Route carried "on" structure: State highway 83,  Year Built: 1948,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 3,700 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 5,550 (year 2032),  Design Load: H 15,  Features Intersected: GRUBBY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.265,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.1m (6.9ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $90,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $135,000
Find on map >>   Show street view

Structure Number: 2970027,  Location: 4.5 MI NE OF WALNUT GROVE (Lat: 33.775739,  Lng: -83.787450),  Route carried "on" structure: State highway 138,  Year Built: 1958,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 15,100 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 22,650 (year 2032),  Design Load: H 15,  Features Intersected: LITTLE FLAT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.265,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $184,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $276,000
Find on map >>   Show street view

Structure Number: 2970028,  Location: 2 MI SW OF MONROE (Lat: 33.788208,  Lng: -83.751619),  Route carried "on" structure: State highway 138,  Year Built: 1958,  Status: Open,  Structure Length: 9.63m (31.59ft),  Average Daily Traffic: 15,340 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 23,010 (year 2032),  Design Load: HS 20,  Features Intersected: ALCOVY RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.484,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 9,  Length of Maximum Span: 11.3m (37.1ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 16.06m (52.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $1,235,000,  Roadway Improvement Cost: $123,000,  Total Project Cost: $1,852,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970029,  Location: 1 MI NW OF MONROE (Lat: 33.798219,  Lng: -83.740028),  Route carried "on" structure: State highway 138,  Year Built: 1964,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 15,040 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 22,560 (year 2032),  Design Load: HS 20,  Features Intersected: MOUNTAIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.093,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 89.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $113,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $170,000
Find on map >>   Show street view

Structure Number: 2970034,  Location: 3 MI NE OF JERSEY (Lat: 33.743478,  Lng: -83.754419),  Route carried "on" structure: County highway 920,  Year Built: 1976,  Status: Open,  Structure Length: 8.53m (27.99ft),  Average Daily Traffic: 2,030 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,045 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: ALCOVY RIVER,  Facility Carried by Structure: MONROE JERSEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.265,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 13.0m (42.7ft),  Out-to-Out Width: 14.2m (46.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 35.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2021,  Underwater Inspection Date: April 2020,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2970035,  Location: 3.25 MI S OF MONROE (Lat: 33.749678,  Lng: -83.736147),  Route carried "on" structure: County highway 920,  Year Built: 1975,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 2,030 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,045 (year 2032),  Design Load: HS 20,  Features Intersected: MOUNTAIN CREEK,  Facility Carried by Structure: MONROE JERSEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.875,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2021,  Underwater Inspection Date: April 2020
Find on map >>   Show street view

Structure Number: 2970036,  Location: 3 MI E OF MONROE (Lat: 33.806817,  Lng: -83.663600),  Route carried "on" structure: County highway 1049,  Year Built: 1954,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 1,040 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,560 (year 2032),  Design Load: H 15,  Features Intersected: JACKS CREEK,  Facility Carried by Structure: SNOWS MILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $172,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $258,000
Find on map >>   Show street view

Structure Number: 2970037,  Location: 4.5 MI E OF MONROE (Lat: 33.814108,  Lng: -83.639908),  Route carried "on" structure: County highway 1049,  Year Built: 1954,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 840 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,260 (year 2032),  Design Load: H 15,  Features Intersected: JACKS CREEK TRIB.,  Facility Carried by Structure: SNOWS MILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2021,  Underwater Inspection Date: April 2020
Find on map >>   Show street view

Structure Number: 2970047,  Location: 2.3 MI N OF MONROE (Lat: 33.823119,  Lng: -83.699458),  Route carried "on" structure: County highway 1434,  Year Built: 1938,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,710 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 2,565 (year 2032),  Design Load: H 15,  Features Intersected: JACKS CREEK,  Facility Carried by Structure: GRATIS ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $90,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $135,000
Find on map >>   Show street view

Structure Number: 2970048,  Location: .75 MI SW OF GRATIS (Lat: 33.877858,  Lng: -83.669739),  Route carried "on" structure: County highway 1434,  Year Built: 1989,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 1,310 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,965 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SHOALS CREEK,  Facility Carried by Structure: GRATIS ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.047,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $117,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $176,000
Find on map >>   Show street view

Structure Number: 297005,  Location: 1 MI N OF MONROE (Lat: 33.813358,  Lng: -83.708658),  Route carried "on" structure: City street 3301,  Year Built: 1938,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 5,120 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,680 (year 2032),  Design Load: H 15,  Features Intersected: JACKS CREEK TRIB.,  Facility Carried by Structure: MARABLE STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $105,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $158,000
Find on map >>   Show street view

Structure Number: 2970051,  Location: 3 MI E OF BETWEEN (Lat: 33.804811,  Lng: -83.759011),  Route carried "on" structure: US 78,  Year Built: 1986,  Status: Open,  Structure Length: 7.50m (24.61ft),  Average Daily Traffic: 19,650 (year 2012),  Truck Traffic: 5%,  Average Future Daily Traffic: 29,475 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: ALCOVY RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.093,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 12 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 16.5m (54.1ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.5m (41.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 61.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: August 2021,  Underwater Inspection Date: April 2020,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2975003,  Location: 2.3 MI SW OF GRATIS (Lat: 33.862919,  Lng: -83.695589),  Route carried "on" structure: County highway 3,  Year Built: 1989,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: SHOALS CREEK,  Facility Carried by Structure: JOHN STOWE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $125,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $188,000
Find on map >>   Show street view

Structure Number: 2975007,  Location: 3.5 MI SE OF BOLD SPRINGS (Lat: 33.856997,  Lng: -83.775450),  Route carried "on" structure: County highway 20,  Year Built: 1959,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 60 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 90 (year 2032),  Design Load: H 15,  Features Intersected: BEAVERDAM CREEK,  Facility Carried by Structure: DEWEY HOGAN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 5.9m (19.4ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Serious,  Channel: Satisfactory,  Operating Rating: 20.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 10.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 42.67m (139.99ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 12 months,  Inspection Date: August 2021,  Underwater Inspection Date: April 2021,  Bridge Improvement Cost: $87,000,  Roadway Improvement Cost: $149,000,  Total Project Cost: $265,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 297501,  Location: 2 MI NE OF MONROE (Lat: 33.818058,  Lng: -83.695119),  Route carried "on" structure: County highway 25,  Year Built: 1985,  Status: Open,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 250 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 375 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: JACKS CREEK,  Facility Carried by Structure: OLD ATHENS HWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $234,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $352,000
Find on map >>   Show street view

Structure Number: 297503,  Location: 2.3 MI SW OF MONROE (Lat: 33.766469,  Lng: -83.735769),  Route carried "on" structure: County highway 170,  Year Built: 1993,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 830 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,245 (year 2032),  Features Intersected: MOUNTAIN CREEK,  Facility Carried by Structure: AMMONS BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $129,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $193,000
Find on map >>   Show street view

Structure Number: 2975031,  Location: 1 MI SW OF MONROE (Lat: 33.784256,  Lng: -83.735786),  Route carried "on" structure: County highway 172,  Year Built: 1970,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 1,760 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 2,640 (year 2032),  Design Load: H 15,  Features Intersected: MOUNTAIN CREEK,  Facility Carried by Structure: MCDANIEL STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $133,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $199,000
Find on map >>   Show street view

Structure Number: 2975033,  Location: 3.3 MI S OF MONROE (Lat: 33.746869,  Lng: -83.729669),  Route carried "on" structure: County highway 179,  Year Built: 1990,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: MOUNTAIN CREEK TRIB.,  Facility Carried by Structure: DEAN HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $129,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $193,000
Find on map >>   Show street view

Structure Number: 2975047,  Location: 1.3 MI SW OF GRATIS (Lat: 33.873058,  Lng: -83.681208),  Route carried "on" structure: County highway 261,  Year Built: 1989,  Status: Open,  Structure Length: 1.31m (4.30ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: H 15,  Features Intersected: SHOALS CREEK,  Facility Carried by Structure: DRY POND ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $252,000
Find on map >>   Show street view

Structure Number: 2975048,  Location: 2.5 MI NE OF BETWEEN (Lat: 33.843008,  Lng: -83.775439),  Route carried "on" structure: County highway 271,  Year Built: 1993,  Status: Open,  Structure Length: 2.53m (8.30ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: BEAVERDAM CREEK,  Facility Carried by Structure: DOUBLE SPRINGS RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 4.9m (16.1ft)

Condition: Channel: Very good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: August 2021,  Underwater Inspection Date: April 2020
Find on map >>   Show street view

Structure Number: 2975061,  Location: 1.2 MI S OF GRATIS (Lat: 33.865297,  Lng: -83.661100),  Route carried "on" structure: County highway 336,  Year Built: 1963,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: H 15,  Features Intersected: SHOALS CREEK,  Facility Carried by Structure: MOUNT VERNON RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $129,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $193,000
Find on map >>   Show street view

Structure Number: 2975062,  Location: IN SOUTH MONROE (Lat: 33.768728,  Lng: -83.719897),  Route carried "on" structure: County highway 347,  Year Built: 1976,  Status: Posted for load,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 20 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 30 (year 2032),  Features Intersected: MOUNTAIN CREEK TRIB.,  Facility Carried by Structure: OAKLAND RIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 4.8m (15.7ft),  Out-to-Out Width: 4.8m (15.7ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 11.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 6.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 41.54m (136.29ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $117,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $175,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2975064,  Location: 1.3 MI SE OF GRATIS (Lat: 33.871208,  Lng: -83.644889),  Route carried "on" structure: County highway 431,  Year Built: 1970,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: H 15,  Features Intersected: SHOALS CREEK,  Facility Carried by Structure: MICHAEL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $195,000,  Roadway Improvement Cost: $20,000,  Total Project Cost: $293,000
Find on map >>   Show street view

Structure Number: 2975067,  Location: 2.5 MI E OF MONROE (Lat: 33.804739,  Lng: -83.673778),  Route carried "on" structure: State highway 83,  Year Built: 1985,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 5,700 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 8,550 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: JACKS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.875,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Fair,  Culverts: Fair,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $113,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $170,000
Find on map >>   Show street view

Structure Number: 2975073,  Location: 1 MI W OF CAMPTON (Lat: 33.877519,  Lng: -83.739228),  Route carried "on" structure: County highway 4,  Year Built: 1995,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 9%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: H 15,  Features Intersected: WILDCAT CREEK,  Facility Carried by Structure: FANNIE THOMPSON RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.1m (6.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $94,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $141,000
Find on map >>   Show street view

Structure Number: 2975081,  Location: 3.5 MI SW OF MONROE (Lat: 33.763758,  Lng: -83.756308),  Route carried "on" structure: County highway 170,  Year Built: 1995,  Status: Open,  Structure Length: 4.27m (14.01ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: ALCOVY RIVER,  Facility Carried by Structure: AMMONS BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2021,  Underwater Inspection Date: April 2020,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2975106,  Location: 2.5 MI W OF GRATIS (Lat: 33.867697,  Lng: -83.700539),  Route carried "on" structure: County highway 251,  Year Built: 2020,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 250 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 300 (year 2041),  Design Load: HL 93,  Features Intersected: SHOAL CREEK TRIB.,  Facility Carried by Structure: CLARENCE ODEM RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.6m (47.9ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 86.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $4,292,000,  Roadway Improvement Cost: $429,000,  Total Project Cost: $6,438,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2975107,  Location: 4 MI S OF BOLD SPRINGS (Lat: 33.853108,  Lng: -83.766647),  Route carried "on" structure: County highway 20,  Year Built: 2020,  Status: Open,  Structure Length: 2.19m (7.19ft),  Average Daily Traffic: 490 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 735 (year 2032),  Design Load: HS 20,  Features Intersected: WOLF CREEK,  Facility Carried by Structure: DEWEY HOGAN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.9m (71.9ft),  Curb-To-Curb Width: 10.1m (33.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2970003,  Location: 2 MI W OF MONROE (Lat: 33.802819,  Lng: -83.749319),  Route carried "under" structure: US 78,  Structure Length: 0. m,  Average Daily Traffic: 8,500 (year 2009),  Truck Traffic: 1%,  Features Intersected: SR 10 BUS WBL,  Facility Carried by Structure: SR 10 BUS WBL
Minimum Vertical Clearance: 5.33m (17.49ft),  Kilometerpoint: 16.093,  Lanes on structure: 1,  Length of Maximum Span: 0.0m