Bridge Statistics for Doraville, Georgia (GA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 100Number of bridges
  • 1,693ft / 516mTotal length
  • $117,596,000Total costs
  • 5,644,449Total average daily traffic
  • 57,135Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Doraville
  • No street view available for this location

New bridges in Doraville, GA - historical statistics
  • New bridges - historical statistics
  • 51950-1959
  • 81960-1969
  • 41970-1979
  • 151980-1989
  • 71990-1999
  • 12000-2009
Reconstructed bridges in Doraville, GA - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 71980-1989
  • 21990-1999
Average Bridge Daily Traffic in Doraville, GA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 10.0%Very good
  • 73.3%Good
  • 16.7%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 20.0%Very good
  • 63.3%Good
  • 10.0%Satisfactory
  • 3.3%Fair
  • 3.3%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 13.3%Very good
  • 60.0%Good
  • 26.7%Satisfactory
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 23.5%Very good
  • 35.3%Good
  • 41.2%Satisfactory
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 90.0%Good
  • 10.0%Satisfactory
Find on map >>   Show street view

Structure Number: 890037,  Location: 1.6 MI N OF DORAVILLE (Lat: 33.924022,  Lng: -84.280356),  Route carried "on" structure: State highway 141,  Year Built: 1969,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 91,120 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 136,680 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: NANCY CREEK TRIB,  Facility Carried by Structure: P'TREE IND. BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.656,  Lanes on structure: 12,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 32.9m (107.9ft),  Skew: 31 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Very good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $393,000,  Roadway Improvement Cost: $39,000,  Total Project Cost: $590,000
Find on map >>   Show street view

Structure Number: 890066,  Location: 1.3 MI SE OF DORAVILLE (Lat: 33.904856,  Lng: -84.237839),  Route carried "on" structure: Interstate 85,  Year Built: 1957,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 294,370 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 441,555 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: N FORK PEACHTREE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 156.106,  Lanes on structure: 12,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 57.3m (188.0ft),  Skew: 30 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $364,000,  Roadway Improvement Cost: $36,000,  Total Project Cost: $546,000
Find on map >>   Show street view

Structure Number: 89007,  Location: 2.2 MI E OF DORAVILLE (Lat: 33.904125,  Lng: -84.239142),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1980,  Status: Open,  Structure Length: 8.41m (27.59ft),  Average Daily Traffic: 17,400 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,100 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- N FORK P'TREE CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 156.106,  Lanes on structure: 3,  Lanes under structure: 14,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 33.8m (110.9ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,372,000,  Roadway Improvement Cost: $137,000,  Total Project Cost: $2,059,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890075,  Location: IN DORAVILLE (Lat: 33.912847,  Lng: -84.286347),  Route carried "on" structure: Interstate 285,  Year Built: 1961,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 5.91m (19.39ft),  Average Daily Traffic: 239,000 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 358,500 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SR 141 P'TREE IND. BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 48.280,  Lanes on structure: 12,  Lanes under structure: 7,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 56.7m (186.0ft),  Skew: 31 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 17.7m (58.1ft),  Curb-To-Curb Width: 56.8m (186.4ft),  Out-to-Out Width: 67.4m (221.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 60.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $2,825,000,  Roadway Improvement Cost: $283,000,  Total Project Cost: $4,238,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 890076,  Location: IN DORAVILLE (Lat: 33.902925,  Lng: -84.273978),  Route carried "on" structure: Interstate 285,  Year Built: 1958,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 6.49m (21.29ft),  Average Daily Traffic: 233,470 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 350,205 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SR 13 BUFORD HIGHWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 51.499,  Lanes on structure: 13,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 50.3m (165.0ft),  Skew: 31 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 22.9m (75.1ft),  Curb-To-Curb Width: 50.6m (166.0ft),  Out-to-Out Width: 53.1m (174.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 60.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $3,329,000,  Roadway Improvement Cost: $333,000,  Total Project Cost: $4,993,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 890077,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.891842,  Lng: -84.259211),  Route carried "on" structure: Interstate 285,  Year Built: 1968,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 8.02m (26.31ft),  Average Daily Traffic: 173,399 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 260,099 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- I-85 RAMP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 53.108,  Lanes on structure: 7,  Lanes under structure: 11,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 31.7m (104.0ft),  Skew: 31 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 22.3m (73.2ft),  Curb-To-Curb Width: 44.2m (145.0ft),  Out-to-Out Width: 45.2m (148.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 33.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $2,429,000,  Roadway Improvement Cost: $243,000,  Total Project Cost: $3,643,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 890078,  Location: IN I-285/I-85 INT-CHANGE (Lat: 33.889672,  Lng: -84.257847),  Route carried "on" structure: Interstate 285,  Year Built: 1959,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 1.68m (5.51ft),  Average Daily Traffic: 116,740 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 175,110 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: N FORK PEACHTREE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 53.108,  Lanes on structure: 7,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 31.7m (104.0ft),  Skew: 39 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $508,000,  Roadway Improvement Cost: $51,000,  Total Project Cost: $762,000
Find on map >>   Show street view

Structure Number: 890198,  Location: 1.8 MI S OF CHAMBLEE (Lat: 33.878553,  Lng: -84.268653),  Route carried "on" structure: City street 9265,  Year Built: 1998,  Status: Open,  Structure Length: 1.62m (5.31ft),  Average Daily Traffic: 13,070 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 19,605 (year 2031),  Design Load: H 15,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: CHAM.-TUCKER ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 7,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 29.9m (98.1ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $489,000,  Roadway Improvement Cost: $49,000,  Total Project Cost: $734,000
Find on map >>   Show street view

Structure Number: 890204,  Location: IN DORAVILLE (Lat: 33.904419,  Lng: -84.276778),  Route carried "on" structure: City street 9267,  Year Built: 1977,  Status: Open,  Structure Length: 10.03m (32.91ft),  Average Daily Traffic: 12,180 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 18,270 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SR 13 CONN- I-285,  Facility Carried by Structure: NEW P'TREE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.047,  Lanes on structure: 4,  Lanes under structure: 18,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 33.8m (110.9ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 20.2m (66.3ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,987,000,  Roadway Improvement Cost: $199,000,  Total Project Cost: $2,980,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890205,  Location: 1.5 MI N OF DORAVILLE (Lat: 33.923956,  Lng: -84.281886),  Route carried "on" structure: City street 9269,  Year Built: 1977,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 1.89m (6.20ft),  Average Daily Traffic: 5,210 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,815 (year 2031),  Design Load: H 15,  Features Intersected: NANCY CREEK,  Facility Carried by Structure: TILLY MILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 20.3m (66.6ft),  Out-to-Out Width: 24.7m (81.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 34.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 21.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $374,000,  Roadway Improvement Cost: $37,000,  Total Project Cost: $562,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 890206,  Location: 2.1 MI SE OF DORAVILLE (Lat: 33.897278,  Lng: -84.242669),  Route carried "on" structure: City street 9271,  Year Built: 1960,  Year Reconstructed: 1990,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 22,670 (year 2011),  Truck Traffic: 3%,  Average Future Daily Traffic: 34,005 (year 2031),  Design Load: HS 20,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: PLEASANTDALE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 19.5m (64.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $227,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $341,000
Find on map >>   Show street view

Structure Number: 890207,  Location: 2 MI E OF DORAVILLE (Lat: 33.901153,  Lng: -84.244094),  Route carried "on" structure: City street 9271,  Year Built: 1985,  Status: Open,  Structure Length: 7.38m (24.21ft),  Average Daily Traffic: 22,670 (year 2011),  Truck Traffic: 3%,  Average Future Daily Traffic: 34,005 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85,  Facility Carried by Structure: PLEASANTDALE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 6,  Lanes under structure: 14,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Skew: 21 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 36.9m (121.1ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 24.4m (80.1ft),  Out-to-Out Width: 29.4m (96.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,977,000,  Roadway Improvement Cost: $198,000,  Total Project Cost: $2,966,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890208,  Location: 1.7 MI SE OF DORAVILLE (Lat: 33.893858,  Lng: -84.250658),  Route carried "on" structure: City street 9273,  Year Built: 1958,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 9,200 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 13,800 (year 2031),  Design Load: H 15,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: NORTHCREST ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 9 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $270,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $405,000
Find on map >>   Show street view

Structure Number: 890209,  Location: 1.7 MI E OF DORAVILLE (Lat: 33.897142,  Lng: -84.250714),  Route carried "on" structure: City street 9273,  Year Built: 1985,  Status: Open,  Structure Length: 12.74m (41.80ft),  Average Daily Traffic: 13,960 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 20,940 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I85- 3 I85 RMP- 2 I285 R,  Facility Carried by Structure: NORTHCREST ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 6,  Lanes under structure: 21,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 55.8m (183.1ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 24.4m (80.1ft),  Out-to-Out Width: 29.4m (96.5ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $3,415,000,  Roadway Improvement Cost: $341,000,  Total Project Cost: $5,122,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 89021,  Location: 2 MI S OF DORAVILLE (Lat: 33.876919,  Lng: -84.267000),  Route carried "on" structure: City street 9275,  Year Built: 1967,  Status: Posted for load,  Structure Length: 3.05m (10.01ft),  Average Daily Traffic: 16,550 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 24,825 (year 2031),  Design Load: H 10,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: MERCER UNIV. DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 0.9m (3.0ft),  Right: 0.9m (3.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 9.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 5.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 9.48m (31.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $391,000,  Roadway Improvement Cost: $39,000,  Total Project Cost: $586,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 890212,  Location: 2.3 MI E OF DORAVILLE (Lat: 33.902858,  Lng: -84.240447),  Route carried "on" structure: City street 9278,  Year Built: 1957,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 8,550 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 12,825 (year 2031),  Design Load: H 15,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: ACCESS ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 59.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $113,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $170,000
Find on map >>   Show street view

Structure Number: 890269,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.891417,  Lng: -84.260075),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1985,  Status: Open,  Structure Length: 52.85m (173.39ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- I-285- 4 RAMPS
Minimum Vertical Clearance: 5.53m (18.14ft),  Kilometerpoint: 152.888,  Lanes on structure: 2,  Lanes under structure: 19,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 9,  Length of Maximum Span: 68.9m (226.0ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $6,775,000,  Roadway Improvement Cost: $678,000,  Total Project Cost: $10,163,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 89027,  Location: 2.7 MI E OF CHAMBLEE (Lat: 33.889864,  Lng: -84.258067),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1985,  Status: Open,  Structure Length: 9.24m (30.31ft),  Average Daily Traffic: 33,360 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 50,040 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: SR407(US 23RMP TO M9265)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 152.888,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 39.0m (128.0ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 60.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,184,000,  Roadway Improvement Cost: $118,000,  Total Project Cost: $1,776,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 890271,  Location: 2.5 MI E OF CHAMBLEE (Lat: 33.892553,  Lng: -84.256819),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1985,  Status: Open,  Structure Length: 4.30m (14.11ft),  Average Daily Traffic: 10,530 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 15,795 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-285 RMP CB TO I-85 NB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 154.497,  Lanes on structure: 1,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 43.0m (141.1ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $401,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $601,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 890272,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.893161,  Lng: -84.260675),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1986,  Status: Open,  Structure Length: 50.17m (164.60ft),  Average Daily Traffic: 17,690 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 26,535 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: 3 I-85 RMPS-2 I-285 RMPS
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 154.497,  Lanes on structure: 1,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 13,  Length of Maximum Span: 50.3m (165.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $4,677,000,  Roadway Improvement Cost: $468,000,  Total Project Cost: $7,016,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890273,  Location: 2.3 MI E OF CHAMBLEE (Lat: 33.891447,  Lng: -84.258200),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1987,  Status: Open,  Structure Length: 47.91m (157.19ft),  Average Daily Traffic: 29,750 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 44,625 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- I-285- 2 RAMPS
Minimum Vertical Clearance: 5.15m (16.90ft),  Kilometerpoint: 154.497,  Lanes on structure: 2,  Lanes under structure: 17,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 9,  Length of Maximum Span: 65.5m (214.9ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $6,142,000,  Roadway Improvement Cost: $614,000,  Total Project Cost: $9,213,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890274,  Location: 2.8 MI E OF CHAMBLEE (Lat: 33.894186,  Lng: -84.256794),  Route carried "on" structure: Ramp Interstate 85,  Year Built: 1987,  Status: Open,  Structure Length: 16.00m (52.49ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85 RMP SB TO I-285 CCB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 154.497,  Lanes on structure: 1,  Lanes under structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 52.7m (172.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,492,000,  Roadway Improvement Cost: $149,000,  Total Project Cost: $2,238,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890275,  Location: 2.3 MI E OF CHAMBLEE (Lat: 33.894019,  Lng: -84.263358),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1986,  Status: Open,  Structure Length: 9.45m (31.00ft),  Average Daily Traffic: 22,920 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 34,380 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-285 RMP CB FROM US 23
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 51.499,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 41.5m (136.2ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 46.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,211,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $1,817,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 890276,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.892294,  Lng: -84.259236),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1987,  Status: Open,  Structure Length: 72.33m (237.30ft),  Average Daily Traffic: 40,290 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 60,435 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: 2 I-85 RMPS-4 I-285 RMPS
Minimum Vertical Clearance: 6.37m (20.90ft),  Kilometerpoint: 51.499,  Lanes on structure: 2,  Lanes under structure: 11,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 14,  Length of Maximum Span: 69.2m (227.0ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $9,272,000,  Roadway Improvement Cost: $927,000,  Total Project Cost: $13,908,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890277,  Location: 2.3 MI E OF CHAMBLEE (Lat: 33.893478,  Lng: -84.263194),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1987,  Status: Open,  Structure Length: 15.61m (51.21ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-285 RMP CB TO I-85 SB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 51.499,  Lanes on structure: 1,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 59.4m (194.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,455,000,  Roadway Improvement Cost: $145,000,  Total Project Cost: $2,182,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890278,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.891508,  Lng: -84.259750),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1984,  Status: Open,  Structure Length: 7.96m (26.12ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- I-85 RAMP,  Facility Carried by Structure: RMP US 23 TO M9265
Minimum Vertical Clearance: 6.01m (19.72ft),  Kilometerpoint: 53.108,  Lanes on structure: 1,  Lanes under structure: 11,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 41.5m (136.2ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $742,000,  Roadway Improvement Cost: $74,000,  Total Project Cost: $1,112,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890279,  Location: 2.4 MI E OF CHAMBLEE (Lat: 33.893014,  Lng: -84.259644),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1985,  Status: Open,  Structure Length: 33.83m (110.99ft),  Average Daily Traffic: 8,310 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 12,465 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I-85- 2 I-85 RAMP
Minimum Vertical Clearance: 5.74m (18.83ft),  Kilometerpoint: 53.108,  Lanes on structure: 1,  Lanes under structure: 13,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 50.0m (164.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 59.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $3,154,000,  Roadway Improvement Cost: $315,000,  Total Project Cost: $4,731,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 89028,  Location: 2.7 MI E OF CHAMBLEE (Lat: 33.891322,  Lng: -84.259086),  Route carried "on" structure: Ramp Interstate 285,  Year Built: 1986,  Status: Open,  Structure Length: 66.54m (218.31ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: 2 I-85 RMPS- 1 I-285 RMP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 53.108,  Lanes on structure: 2,  Lanes under structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 12,  Length of Maximum Span: 65.5m (214.9ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $8,529,000,  Roadway Improvement Cost: $853,000,  Total Project Cost: $12,794,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 890321,  Location: 1.35 MI N OF DORAVILLE (Lat: 33.918711,  Lng: -84.283992),  Route carried "on" structure: State highway 141,  Year Built: 1990,  Status: Open,  Structure Length: 2.93m (9.61ft),  Average Daily Traffic: 109,510 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 164,265 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: CR 3106 N CARVER CIRCLE,  Facility Carried by Structure: P'TREE IND. BLVD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.656,  Lanes on structure: 8,  Lanes under structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 37.8m (124.0ft),  Skew: 30 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.3m (96.1ft),  Curb-To-Curb Width: 36.0m (118.1ft),  Out-to-Out Width: 37.7m (123.7ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $989,000,  Roadway Improvement Cost: $99,000,  Total Project Cost: $1,483,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 890322,  Location: 1.4 MI N OF DORAVILLE (Lat: 33.923197,  Lng: -84.281528),  Route carried "on" structure: State highway 141,  Year Built: 1990,  Status: Open,  Structure Length: 13.35m (43.80ft),  Average Daily Traffic: 91,120 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 136,680 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: M-9269 - CR6517 - CR6518,  Facility Carried by Structure: P'TREE IND. BLVD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.656,  Lanes on structure: 6,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 32.9m (107.9ft),  Skew: 30 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 48.2m (158.1ft),  Curb-To-Curb Width: 31.7m (104.0ft),  Out-to-Out Width: 33.4m (109.6ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 35.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $3,578,000,  Roadway Improvement Cost: $358,000,  Total Project Cost: $5,367,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 895049,  Location: 1 MI E OF DORAVILLE (Lat: 33.889400,  Lng: -84.260919),  Route carried "on" structure: County highway 1574,  Year Built: 1967,  Status: Open,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: H 15,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: PRES. PARKWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 4 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 32.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $313,000,  Roadway Improvement Cost: $31,000,  Total Project Cost: $469,000,  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 895072,  Location: 0.5 MI SE OF DORAVILLE (Lat: 33.886761,  Lng: -84.261803),  Route carried "on" structure: County highway 3273,  Year Built: 1967,  Status: Open,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: H 15,  Features Intersected: N FORK PEACHTREE CREEK,  Facility Carried by Structure: PRESIDENTIAL DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 48.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $313,000,  Roadway Improvement Cost: $31,000,  Total Project Cost: $469,000,  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 895073,  Location: 1.7 MI E OF DORAVILLE (Lat: 33.906239,  Lng: -84.248808),  Route carried "on" structure: County highway 4196,  Year Built: 1964,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: HS 15,  Features Intersected: N FORK P'TREE CREEK TRIB,  Facility Carried by Structure: OAKCLIFF IND. CT.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 34.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 20.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $160,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $240,000,  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 89511,  Location: 1.6 MI SE OF DORAVILLE (Lat: 33.882847,  Lng: -84.266428),  Route carried "on" structure: County highway 5670,  Year Built: 1975,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 2,202 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 3,303 (year 2031),  Design Load: H 15,  Features Intersected: N. FORK P'TREE CRK TRIB,  Facility Carried by Structure: MARJAN DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $109,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $164,000
Find on map >>   Show street view

Structure Number: 895139,  Location: IN NORTH EAST DORAVILLE (Lat: 33.914142,  Lng: -84.265550),  Route carried "on" structure: County highway 9273,  Year Built: 1997,  Status: Open,  Structure Length: 13.11m (43.01ft),  Average Daily Traffic: 13,210 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 19,815 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: NS RAILROAD,  Facility Carried by Structure: OAKCLIFF RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 17.1m (56.1ft),  Skew: 22 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 3,  Length of Maximum Span: 51.2m (168.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 21.9m (71.9ft),  Out-to-Out Width: 26.4m (86.6ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $2,597,000,  Roadway Improvement Cost: $260,000,  Total Project Cost: $3,895,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 89514,  Location: IN NORTH EAST DORAVILLE (Lat: 33.916069,  Lng: -84.266192),  Route carried "on" structure: County highway 9273,  Year Built: 1997,  Status: Open,  Structure Length: 5.12m (16.80ft),  Average Daily Traffic: 13,210 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 19,815 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: MURPHEY DRIVE,  Facility Carried by Structure: OAKCLIFF RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 17.1m (56.1ft),  Skew: 23 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.5m (100.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 26.4m (86.6ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 47.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,014,000,  Roadway Improvement Cost: $101,000,  Total Project Cost: $1,522,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 895141,  Location: IN NORTH EAST DORAVILLE (Lat: 33.919811,  Lng: -84.269667),  Route carried "on" structure: Ramp City street 9273,  Year Built: 1997,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 13,210 (year 2011),  Truck Traffic: 1%,  Average Future Daily Traffic: 19,815 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: NANCY CREEK TRIB,  Facility Carried by Structure: WINTERS CHAPEL CN
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.1m (6.9ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 89.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $196,000,  Roadway Improvement Cost: $20,000,  Total Project Cost: $294,000
Find on map >>   Show street view

Structure Number: 1350087,  Location: 2 MI S OF NORCROSS (Lat: 33.908700,  Lng: -84.234089),  Route carried "on" structure: City street 9277,  Year Built: 1971,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 4,880 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,320 (year 2032),  Design Load: H 15,  Features Intersected: NORTH P'TREE CRK TRIB,  Facility Carried by Structure: CRESCENT DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.4m (11.2ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $90,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $135,000
Find on map >>   Show street view

Structure Number: 1350112,  Location: @ GWINNETT-DEKALB C L (Lat: 33.930928,  Lng: -84.264897),  Route carried "on" structure: State highway 141,  Year Built: 1990,  Status: Open,  Structure Length: 11.80m (38.71ft),  Average Daily Traffic: 83,670 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 125,505 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: M-9268- CR 3693- CR 3695,  Facility Carried by Structure: P'TREE IND BLVD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 32.9m (107.9ft),  Skew: 39 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 71.6m (234.9ft),  Curb-To-Curb Width: 32.9m (107.9ft),  Out-to-Out Width: 34.4m (112.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 35.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Bridge Improvement Cost: $3,162,000,  Roadway Improvement Cost: $316,000,  Total Project Cost: $4,742,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 1355207,  Location: 2.3 MI. S. NORCROSS (Lat: 33.905850,  Lng: -84.225189),  Route carried "on" structure: County highway 569,  Year Built: 2007,  Status: Open,  Structure Length: 2.96m (9.71ft),  Average Daily Traffic: 7,080 (year 2012),  Truck Traffic: 1%,  Average Future Daily Traffic: 10,620 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: N. FORK PEACHTREE CREEK,  Facility Carried by Structure: GRAVES RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.6m (97.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 13.2m (43.3ft),  Out-to-Out Width: 18.3m (60.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $379,000,  Roadway Improvement Cost: $38,000,  Total Project Cost: $568,000,  Deck Structure Type: Concrete Cast-file-Place
Discuss Doraville, Georgia (GA) on our hugely popular Georgia forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.