Bridge Statistics for Tioga, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 23Number of bridges
  • 197ft / 59.9mTotal length
  • $28,779,000Total costs
  • 27,189Total average daily traffic
  • 2,509Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Tioga
  • No street view available for this location

New bridges in Tioga, NY - historical statistics
  • New bridges - historical statistics
  • 11910-1919
  • 21930-1939
  • 21940-1949
  • 21950-1959
  • 21960-1969
  • 11970-1979
  • 51980-1989
  • 41990-1999
  • 12000-2009
  • 22010-2019
  • 12020-2022
Reconstructed bridges in Tioga, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 21990-1999
  • 32000-2009
  • 12010-2019
Average Bridge Daily Traffic in Tioga, NY
Average Bridge Truck Traffic in Tioga, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.1%Excellent
  • 22.2%Very good
  • 38.9%Good
  • 16.7%Satisfactory
  • 11.1%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 11.1%Excellent
  • 16.7%Very good
  • 55.6%Good
  • 5.6%Satisfactory
  • 11.1%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 5.6%Excellent
  • 16.7%Very good
  • 44.4%Good
  • 11.1%Satisfactory
  • 16.7%Fair
  • 5.6%Critical
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 15.0%Good
  • 55.0%Satisfactory
  • 25.0%Fair
  • 5.0%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 33.3%Excellent
  • 66.7%Satisfactory
Find on map >>   Show street view

Structure Number: 10129,  Location: RTE 17C E TIOGA CENTER (Lat: 42.059536,  Lng: -76.345461),  Route carried "on" structure: State highway 17C,  Year Built: 2001,  Status: Open,  Structure Length: 4.66m (15.29ft),  Average Daily Traffic: 3,290 (year 2017),  Truck Traffic: 9%,  Average Future Daily Traffic: 3,432 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: PIPE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.933,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 46.3m (151.9ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Inventory Rating: 65.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.66m (15.29ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $1,651,000,  Roadway Improvement Cost: $967,000,  Total Project Cost: $2,618,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101291,  Location: 3.5 MI WEST OF OWEGO (Lat: 42.085711,  Lng: -76.320056),  Route carried "on" structure: State highway 17C,  Year Built: 1996,  Status: Open,  Structure Length: 5.21m (17.09ft),  Average Daily Traffic: 2,495 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 2,602 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: NORFOLK SOUTHERN RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 24.714,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 50.2m (164.7ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Inventory Rating: 66.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.21m (17.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $2,582,000,  Roadway Improvement Cost: $1,512,000,  Total Project Cost: $4,095,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101292,  Location: 3.0 MI W OF OWEGO (Lat: 42.086600,  Lng: -76.311392),  Route carried "on" structure: State highway 17C,  Year Built: 1995,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 2,495 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 2,602 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: THORNE HOLLOW CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 25.454,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Inventory Rating: 81.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.82m (2.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $371,000,  Roadway Improvement Cost: $218,000,  Total Project Cost: $589,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 101293,  Location: JCT RTE 17 & CATATONK (Lat: 42.096894,  Lng: -76.277447),  Route carried "on" structure: State highway 17C,  Year Built: 1993,  Status: Open,  Structure Length: 8.17m (26.80ft),  Average Daily Traffic: 6,011 (year 2020),  Truck Traffic: 12%,  Average Future Daily Traffic: 7,302 (year 2040),  Design Load: HS 20,  Features Intersected: OWEGO CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.705,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 40.5m (132.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 38.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 29.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.16m (26.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,983,000,  Roadway Improvement Cost: $1,161,000,  Total Project Cost: $3,144,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 109641,  Location: IN SMITHBORO ON S.H.17C (Lat: 42.033869,  Lng: -76.399961),  Route carried "on" structure: State highway 17C,  Year Built: 1932,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 2,103 (year 2020),  Truck Traffic: 14%,  Average Future Daily Traffic: 2,193 (year 2040),  Design Load: H 20,  Features Intersected: TRIB. SUSQUEHANNA RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.626,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.3m (37.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.0m (19.7ft),  Curb-To-Curb Width: 21.0m (68.9ft),  Out-to-Out Width: 22.3m (73.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 78.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $613,000,  Roadway Improvement Cost: $359,000,  Total Project Cost: $972,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221896,  Location: 0.5 MI N TIOGA CENTER (Lat: 42.062722,  Lng: -76.350825),  Route carried "on" structure: Other road ,  Year Built: 1987,  Year Reconstructed: 2014,  Status: Open,  Structure Length: 2.56m (8.40ft),  Average Daily Traffic: 386 (year 2016),  Truck Traffic: 7%,  Average Future Daily Traffic: 540 (year 2036),  Design Load: HS 20,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: ALLYN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.209,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.2m (82.7ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 48.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.56m (8.40ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Critical Feature Inspection Date: July 2021,  Bridge Improvement Cost: $1,471,000,  Roadway Improvement Cost: $862,000,  Total Project Cost: $2,333,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2219,  Location: 3.2 MI NE OF SMITHBORO (Lat: 42.073497,  Lng: -76.375647),  Route carried "on" structure: Other road ,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 247 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 346 (year 2039),  Features Intersected: NEIGER HOLLOW CRK,  Facility Carried by Structure: DIAMOND VALLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.188,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Critical,  Channel: Serious,  Operating Rating: 29.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 15.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.00m (3.28ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $299,000,  Roadway Improvement Cost: $175,000,  Total Project Cost: $474,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221901,  Location: 1.8 MI NW OF TIOGA CENTER (Lat: 42.074414,  Lng: -76.370706),  Route carried "on" structure: Other road ,  Year Built: 1983,  Status: Posted for load,  Structure Length: 1.80m (5.91ft),  Average Daily Traffic: 247 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 346 (year 2039),  Design Load: HS 20,  Features Intersected: DIAMOND VALLEY CK,  Facility Carried by Structure: DIAMOND VALLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.754,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 4 degrees,  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.0m (55.8ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 60.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.79m (5.87ft),  Designated Inspection Frequency: Every 12 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: March 2021,  Underwater Inspection Date: October 2017,  Bridge Improvement Cost: $571,000,  Roadway Improvement Cost: $334,000,  Total Project Cost: $905,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221903,  Location: 1 MI SW OF STRAITS CORNRS (Lat: 42.141422,  Lng: -76.395744),  Route carried "on" structure: Other road ,  Year Built: 1985,  Year Reconstructed: 2004,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 66 (year 2016),  Truck Traffic: 3%,  Average Future Daily Traffic: 92 (year 2036),  Features Intersected: EVELIEN HILL CRK,  Facility Carried by Structure: EVELIEN HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.754,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 5.0m (16.4ft),  Out-to-Out Width: 5.3m (17.4ft)

Condition: Deck: Very good,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 75.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $110,000,  Roadway Improvement Cost: $64,000,  Total Project Cost: $174,000 ( Estimate for 2021),  Deck Structure Type: Open Grating,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 221907,  Location: 3.0 MI N OF SMITHBORO (Lat: 42.074342,  Lng: -76.400892),  Route carried "on" structure: Other road ,  Year Built: 1934,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 98 (year 2016),  Truck Traffic: 8%,  Average Future Daily Traffic: 137 (year 2036),  Features Intersected: ALDER SWAMP CREEK,  Facility Carried by Structure: ROSS HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.583,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.0m (19.7ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.9m (22.6ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $267,000,  Roadway Improvement Cost: $156,000,  Total Project Cost: $423,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 227154,  Location: 2.9 MI NW OF TIOGA CENTER (Lat: 42.120689,  Lng: -76.395425),  Route carried "on" structure: County highway ,  Year Built: 2020,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 824 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 859 (year 2040),  Design Load: HL 93,  Features Intersected: TRIBUTARY TO PIPE CREEK,  Facility Carried by Structure: HALSEY VALLEY ROAD
Minimum Vertical Clearance: 32.69m (107.25ft),  Kilometerpoint: 8.158,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.7m (44.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.8m (35.4ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Good,  Operating Rating: 60.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $435,000,  Roadway Improvement Cost: $254,000,  Total Project Cost: $689,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333496,  Location: 2.6 MI NW OF TIOGA CENTER (Lat: 42.091864,  Lng: -76.366703),  Route carried "on" structure: County highway ,  Year Built: 1959,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 824 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 859 (year 2040),  Design Load: H 20,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: HALSEY VALLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.862,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $428,000,  Roadway Improvement Cost: $250,000,  Total Project Cost: $678,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 333497,  Location: 2.9 MI NW OF TIOGA CENTER (Lat: 42.091814,  Lng: -76.366653),  Route carried "on" structure: County highway ,  Year Built: 1959,  Year Reconstructed: 2011,  Status: Open,  Structure Length: 2.77m (9.09ft),  Average Daily Traffic: 824 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 859 (year 2040),  Design Load: HS 20,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: HALSEY VALLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.151,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 26.5m (86.9ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 81.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 63.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.77m (9.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $837,000,  Roadway Improvement Cost: $490,000,  Total Project Cost: $1,327,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333504,  Location: 5.8 MI NE OF SMITHBORO (Lat: 42.111794,  Lng: -76.382656),  Route carried "on" structure: County highway ,  Year Built: 2011,  Status: Open,  Structure Length: 3.41m (11.19ft),  Average Daily Traffic: 429 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 601 (year 2039),  Design Load: HL 93,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: STRAITS CORNERS RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.080,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 33.5m (109.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 75.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 48.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $807,000,  Roadway Improvement Cost: $473,000,  Total Project Cost: $1,280,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 333505,  Location: 6.7 MI NE OF SMITHBORO (Lat: 42.124239,  Lng: -76.383550),  Route carried "on" structure: County highway ,  Year Built: 1985,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 429 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 601 (year 2039),  Design Load: HS 20,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: STRAITS CORNRS RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.512,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.8m (61.7ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 92.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $614,000,  Roadway Improvement Cost: $360,000,  Total Project Cost: $974,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333506,  Location: IN STRAITS CORNERS (Lat: 42.150006,  Lng: -76.380531),  Route carried "on" structure: County highway ,  Year Built: 1996,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 257 (year 2017),  Truck Traffic: 19%,  Average Future Daily Traffic: 360 (year 2037),  Design Load: HS 25 or greater,  Features Intersected: CHAMBERS CREEK,  Facility Carried by Structure: STRAITS CORNERS R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.489,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $492,000,  Roadway Improvement Cost: $288,000,  Total Project Cost: $780,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 333511,  Location: 2.4 MI W OF OWEGO - CR906 (Lat: 42.096561,  Lng: -76.304958),  Route carried "on" structure: County highway ,  Year Built: 1985,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 1,170 (year 2016),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,220 (year 2040),  Design Load: HS 20,  Features Intersected: THORN HLLOW CREEK,  Facility Carried by Structure: GLEN MARY DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.883,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.5m (14.8ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Inventory Rating: 88.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.00m (3.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $300,000,  Roadway Improvement Cost: $176,000,  Total Project Cost: $476,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 333512,  Location: 1.2 MI SE OF CATATONK (Lat: 42.142808,  Lng: -76.294981),  Route carried "on" structure: Other road ,  Year Built: 1967,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 5.67m (18.60ft),  Average Daily Traffic: 1,178 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,457 (year 2040),  Design Load: H 20,  Features Intersected: CATATONK CREEK,  Facility Carried by Structure: GLEN MARY DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.914,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 72.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.66m (18.57ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,210,000,  Roadway Improvement Cost: $709,000,  Total Project Cost: $1,919,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 333514,  Location: 1 MILE NW OF OWEGO (Lat: 42.111542,  Lng: -76.278586),  Route carried "on" structure: County highway ,  Year Built: 1963,  Year Reconstructed: 2004,  Status: Open,  Structure Length: 9.97m (32.71ft),  Average Daily Traffic: 2,695 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,334 (year 2040),  Design Load: HS 20,  Features Intersected: OWEGO CREEK,  Facility Carried by Structure: TALCOTT STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 24.7m (81.0ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 9.96m (32.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $2,140,000,  Roadway Improvement Cost: $1,253,000,  Total Project Cost: $3,393,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333554,  Location: 1.5 MI NW OF TIOGA CENTER (Lat: 42.074400,  Lng: -76.359236),  Route carried "on" structure: Other road ,  Year Built: 1972,  Year Reconstructed: 2018,  Status: Open,  Structure Length: 4.54m (14.90ft),  Average Daily Traffic: 247 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 346 (year 2039),  Design Load: HS 20,  Features Intersected: PIPE CREEK,  Facility Carried by Structure: DIAMOND VALLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.708,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 21.9m (71.9ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Excellent,  Superstructure: Very good,  Substructure: Very good,  Channel: Fair,  Operating Rating: 95.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.54m (14.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $853,000,  Roadway Improvement Cost: $499,000,  Total Project Cost: $1,352,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 337119,  Location: Town of TIOGA (Lat: 42.142697,  Lng: -76.439592),  Route carried "on" structure: County highway ,  Year Built: 2015,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 824 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 859 (year 2040),  Design Load: HL 93,  Features Intersected: UN-NAMED STREAM,  Facility Carried by Structure: COUNTY ROAD 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.274,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 8.7m (28.5ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Channel: Satisfactory,  Culverts: Excellent,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 34.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $116,000,  Roadway Improvement Cost: $68,000,  Total Project Cost: $184,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 721898,  Location: 1.1 MI SE OF BARTON (Lat: 42.036486,  Lng: -76.428719),  Route carried "under" structure: Other road ,  Year Built: 1948,  Structure Length: 0. m,  Features Intersected: BARTON ROAD,  Facility Carried by Structure: NORFOLK SOUTHERN
Minimum Vertical Clearance: 3.75m (12.30ft),  Kilometerpoint: 0.000,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Length of Maximum Span: 10.3m (33.8ft)

Find on map >>   Show street view

Structure Number: 721899,  Location: 1.3 MI W OF SMITHBORO (Lat: 42.036519,  Lng: -76.428692),  Route carried "under" structure: Other road ,  Year Built: 1915,  Structure Length: 0. m,  Average Daily Traffic: 50 (year 2021),  Features Intersected: BARTON ROAD,  Facility Carried by Structure: NORFOLK SOUTHERN
Minimum Vertical Clearance: 3.14m (10.30ft),  Kilometerpoint: 0.000,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 9.7m (31.8ft)