  • National Bridge Inventory (NBI) Statistics
  • 29Number of bridges
  • 194ft / 58.9mTotal length
  • $23,031,000Total costs
  • 95,125Total average daily traffic
  • 7,224Total average daily truck traffic
  • 143,507Total future (year 2028) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Pollard
  • No street view available for this location

New bridges in Pollard, AL - historical statistics
  • New bridges - historical statistics
  • 51920-1929
  • 101930-1939
  • 21940-1949
  • 21950-1959
  • 21960-1969
  • 21970-1979
  • 11980-1989
  • 31990-1999
  • 22000-2009
Reconstructed bridges in Pollard, AL - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11930-1939
  • 41940-1949
  • 01950-1959
  • 11960-1969
  • 01970-1979
  • 21980-1989
  • 11990-1999
Average Bridge Daily Traffic in Pollard, AL
Average Bridge Truck Traffic in Pollard, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 7.1%Good
  • 64.3%Satisfactory
  • 28.6%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 21.4%Good
  • 35.7%Satisfactory
  • 35.7%Fair
  • 7.1%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 7.1%Very good
  • 21.4%Good
  • 28.6%Satisfactory
  • 35.7%Fair
  • 7.1%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 7.4%Very good
  • 33.3%Good
  • 48.1%Satisfactory
  • 11.1%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 13.3%Good
  • 80.0%Satisfactory
  • 6.7%Fair
Find on map >>   Show street view

Structure Number: 269,  Location: 1.4 MI. N. OF YORK (Lat: 32.508131,  Lng: -88.275453),  Route carried "on" structure: US 11,  Year Built: 1925,  Year Reconstructed: 1944,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 2,930 (year 2013),  Truck Traffic: 9%,  Average Future Daily Traffic: 3,915 (year 2041),  Design Load: H 15,  Features Intersected: WHITE HALL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.026,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 35.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.02m (6.63ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $664,000,  Roadway Improvement Cost: $66,000,  Total Project Cost: $730,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1104,  Location: .7 MI E CO C28 CO 28 JCT (Lat: 34.456786,  Lng: -88.091758),  Route carried "on" structure: County highway 28,  Year Built: 1934,  Status: Posted for load,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 120 (year 2000),  Truck Traffic: 5%,  Average Future Daily Traffic: 198 (year 2036),  Features Intersected: STREAM INTO MUD CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.4m (21.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 5.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 3.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: August 2020,  Other Special Inspection Date: August 2021,  Bridge Improvement Cost: $232,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $255,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1105,  Location: 1.1 MI N JCT SR 35*CO 17 (Lat: 34.680000,  Lng: -86.138333),  Route carried "on" structure: State highway 35,  Year Built: 1934,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 1,503 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,104 (year 2039),  Design Load: H 15,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 92.322,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $240,000,  Roadway Improvement Cost: $24,000,  Total Project Cost: $264,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1232,  Location: .1 MI. NO. BEAR CREEK (Lat: 33.460750,  Lng: -86.496022),  Route carried "on" structure: State highway 25,  Year Built: 1935,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 1,080 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,432 (year 2040),  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 255.902,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $648,000,  Roadway Improvement Cost: $65,000,  Total Project Cost: $713,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1609,  Location: 5.5 MI. N. OF LINDEN (Lat: 32.373617,  Lng: -87.731150),  Route carried "on" structure: State highway 69,  Year Built: 1937,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 1,450 (year 2013),  Truck Traffic: 13%,  Average Future Daily Traffic: 1,885 (year 2033),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 131.936,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 81.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.30m (4.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $263,000,  Roadway Improvement Cost: $26,000,  Total Project Cost: $289,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1624,  Location: 8.5 MI N JCT US431 * SR79 (Lat: 34.521897,  Lng: -86.176369),  Route carried "on" structure: State highway 79,  Year Built: 1937,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 3,716 (year 2019),  Truck Traffic: 13%,  Average Future Daily Traffic: 5,203 (year 2039),  Design Load: H 15,  Features Intersected: CREEK * LAKE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 128.635,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Underwater Inspection Date: May 2020,  Bridge Improvement Cost: $262,000,  Roadway Improvement Cost: $26,000,  Total Project Cost: $288,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1628,  Location: 0.2 MI E OF CO 81 (Lat: 34.884339,  Lng: -87.813611),  Route carried "on" structure: County highway 112,  Year Built: 1937,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 75 (year 1989),  Average Future Daily Traffic: 150 (year 2031),  Features Intersected: BURCHAM CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.4m (21.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 23.9 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.41m (4.63ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $203,000,  Roadway Improvement Cost: $20,000,  Total Project Cost: $223,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1629,  Location: 500 FT W CO 399 (Lat: 33.491356,  Lng: -86.019794),  Route carried "on" structure: County highway 82,  Year Built: 1937,  Year Reconstructed: 1992,  Status: Posted for load,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 385 (year 2018),  Truck Traffic: 3%,  Average Future Daily Traffic: 690 (year 2038),  Features Intersected: KELLY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 4.7m (15.4ft),  Out-to-Out Width: 4.7m (15.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 5.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 2.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2020,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $226,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $249,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1639,  Location: 0.4 OFF CO 26 (Lat: 34.855783,  Lng: -87.232675),  Route carried "on" structure: County highway 95,  Year Built: 1937,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 100 (year 1987),  Average Future Daily Traffic: 200 (year 2028),  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 7.1m (23.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.59m (5.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $250,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $275,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1646,  Location: 1.5 MI E CO RD 1116 (Lat: 34.902728,  Lng: -86.577717),  Route carried "on" structure: County highway 137,  Year Built: 1937,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 750 (year 1992),  Truck Traffic: 1%,  Average Future Daily Traffic: 2,208 (year 2035),  Design Load: H 15,  Features Intersected: GRIMWOOD BRANCH,  Facility Carried by Structure: GRIMWOOD RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 40.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $314,000,  Roadway Improvement Cost: $31,000,  Total Project Cost: $345,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2091,  Location: @ CO RD 52 (Lat: 33.282244,  Lng: -86.810708),  Route carried "on" structure: US 31,  Year Built: 1924,  Year Reconstructed: 1940,  Status: Temporarily open,  Structure Length: 14.30m (46.92ft),  Average Daily Traffic: 28,511 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 51,497 (year 2042),  Design Load: H 15,  Features Intersected: PEAVINE CK * ACL RR,  Facility Carried by Structure: AL - 3 NORTH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 412.963,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 11,  Length of Maximum Span: 13.4m (44.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.6m (34.8ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Poor,  Channel: Good,  Operating Rating: 50.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 15.09m (49.51ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: January 2021,  Other Special Inspection Date: January 2022,  Bridge Improvement Cost: $3,518,000,  Roadway Improvement Cost: $352,000,  Total Project Cost: $3,870,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2092,  Location: .1 MI. SO. AL 119 (Lat: 33.329744,  Lng: -86.792417),  Route carried "on" structure: US 31,  Year Built: 1924,  Year Reconstructed: 1940,  Status: Open,  Structure Length: 3.87m (12.70ft),  Average Daily Traffic: 15,675 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 20,135 (year 2041),  Design Load: H 15,  Features Intersected: CAHABA VALLEY CREEK,  Facility Carried by Structure: AL - 3 NORTH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 419.099,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.8m (42.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 61.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.81m (15.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $1,320,000,  Roadway Improvement Cost: $132,000,  Total Project Cost: $1,452,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2094,  Location: 2 MI N LINEVILLE (Lat: 33.356333,  Lng: -85.720000),  Route carried "on" structure: State highway 9,  Year Built: 1925,  Year Reconstructed: 1940,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 3,792 (year 2018),  Truck Traffic: 10%,  Average Future Daily Traffic: 5,309 (year 2038),  Design Load: H 15,  Features Intersected: FOX CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 308.896,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 84.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $316,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $348,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 2096,  Location: 6.5 MI N LINEVILLE (Lat: 33.415972,  Lng: -85.689500),  Route carried "on" structure: State highway 9,  Year Built: 1925,  Year Reconstructed: 1940,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 3,089 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,325 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 316.539,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 72.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $320,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $352,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 2692,  Location: 3 MI E JCT SR 36 & SR 67 (Lat: 34.463833,  Lng: -86.713028),  Route carried "on" structure: State highway 36,  Year Built: 1942,  Status: Open,  Structure Length: 4.82m (15.81ft),  Average Daily Traffic: 4,020 (year 2021),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,866 (year 2033),  Design Load: H 15,  Features Intersected: COTACO CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 55.566,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 12.2m (40.0ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 39.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 5.83m (19.13ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Underwater Inspection Date: June 2020,  Bridge Improvement Cost: $1,159,000,  Roadway Improvement Cost: $116,000,  Total Project Cost: $1,275,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2693,  Location: 5 MI E JCT SR 36 & SR 67 (Lat: 34.480000,  Lng: -86.690000),  Route carried "on" structure: State highway 36,  Year Built: 1942,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 4,070 (year 2021),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,927 (year 2033),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 58.645,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.5m (14.8ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 48.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.01m (6.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $400,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $440,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 4913,  Location: 1.4 MI. E. MT. OLIVE (Lat: 33.057800,  Lng: -86.118464),  Route carried "on" structure: County highway 66,  Year Built: 1954,  Status: Open,  Structure Length: 0.97m (3.18ft),  Average Daily Traffic: 398 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 459 (year 2041),  Design Load: HS 20,  Features Intersected: Unnamed Branch
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.63m (5.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $547,000,  Roadway Improvement Cost: $55,000,  Total Project Cost: $602,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 9591,  Location: 6.4 MI N US 29 (Lat: 31.044800,  Lng: -87.178411),  Route carried "on" structure: US 31,  Year Built: 1968,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 6,072 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 9,108 (year 2039),  Design Load: HS 20,  Features Intersected: JERNIGAN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 99.409,  Lanes on structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 22.0m (72.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.26m (7.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $2,468,000,  Roadway Improvement Cost: $247,000,  Total Project Cost: $2,715,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 9807,  Location: .1MI S POLLARD (Lat: 31.016667,  Lng: -87.171667),  Route carried "on" structure: ServiceCounty highway 253,  Year Built: 1992,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 320 (year 1988),  Truck Traffic: 5%,  Average Future Daily Traffic: 464 (year 2034),  Design Load: HS 20,  Features Intersected: BAY BRANCH,  Facility Carried by Structure: COUNTY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.7m (41.7ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 72.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $371,000,  Roadway Improvement Cost: $37,000,  Total Project Cost: $408,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10843,  Location: 1MI W MCCALL SCHOOL (Lat: 31.057900,  Lng: -87.182342),  Route carried "on" structure: County highway 35,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 3.66m (12.01ft),  Average Daily Traffic: 150 (year 1988),  Truck Traffic: 5%,  Average Future Daily Traffic: 234 (year 2034),  Design Load: H 20,  Features Intersected: LAMBETH CREEK,  Facility Carried by Structure: COUNTY HIGHWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 7.3m (24.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Very good,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 4.58m (15.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $785,000,  Roadway Improvement Cost: $79,000,  Total Project Cost: $864,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 14695,  Location: 1MI N MCCALL SCHOOL (Lat: 31.066667,  Lng: -87.168333),  Route carried "on" structure: ServiceCounty highway 23,  Year Built: 1937,  Year Reconstructed: 1989,  Status: Open,  Structure Length: 1.68m (5.51ft),  Average Daily Traffic: 320 (year 1988),  Truck Traffic: 5%,  Average Future Daily Traffic: 499 (year 2034),  Design Load: HS 20,  Features Intersected: LAMBETH CREEK,  Facility Carried by Structure: COUNTY HIGHWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 52.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.37m (7.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $657,000,  Roadway Improvement Cost: $66,000,  Total Project Cost: $723,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1618,  Location: 1.0 MI S MILLERVILLE (Lat: 33.172842,  Lng: -85.923786),  Route carried "on" structure: County highway 210,  Year Built: 1979,  Status: Posted for load,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 20 (year 2016),  Average Future Daily Traffic: 30 (year 2036),  Features Intersected: LITTLE HILLABEE,  Facility Carried by Structure: ALAWASHKY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 19.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 14.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.48m (4.86ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2021,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $178,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1622,  Location: 1.5 MI S NIXON CHAPEL (Lat: 34.183814,  Lng: -86.385925),  Route carried "on" structure: County highway 75,  Year Built: 1950,  Status: Closed,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 30 (year 1994),  Average Future Daily Traffic: 50 (year 2038),  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.7m (22.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 3.9m (12.8ft),  Out-to-Out Width: 4.3m (14.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Channel: Very good,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: High priority of replacement,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.41m (4.63ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: August 2018,  Other Special Inspection Date: August 2018,  Bridge Improvement Cost: $135,000,  Roadway Improvement Cost: $14,000,  Total Project Cost: $149,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1627,  Location: 0.2 MI S TENN ST LINE (Lat: 34.985472,  Lng: -85.722206),  Route carried "on" structure: US 72,  Year Built: 1995,  Status: Open,  Structure Length: 4.33m (14.21ft),  Average Daily Traffic: 6,764 (year 2019),  Truck Traffic: 22%,  Average Future Daily Traffic: 9,469 (year 2039),  Design Load: HS 20,  Features Intersected: SEQUATCHIE VALLEY RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 268.220,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Skew: 12 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 12.1m (39.7ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 63.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.31m (17.42ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,566,000,  Roadway Improvement Cost: $157,000,  Total Project Cost: $1,723,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 16461,  Location: 4.4 MI N US 29 (Lat: 31.020961,  Lng: -87.205997),  Route carried "on" structure: US 31,  Year Built: 2001,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 5,490 (year 2017),  Truck Traffic: 4%,  Average Future Daily Traffic: 8,910 (year 2037),  Design Load: HS 20,  Features Intersected: LITTLE ESC.CREEK RELIEF
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 95.643,  Lanes on structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $1,325,000,  Roadway Improvement Cost: $133,000,  Total Project Cost: $1,458,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1647,  Location: 1 MI E AL HWY 79 (Lat: 33.710517,  Lng: -86.644517),  Route carried "on" structure: County highway 356,  Year Built: 1975,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 835 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 900 (year 2041),  Design Load: HS 20,  Features Intersected: DRY CREEK,  Facility Carried by Structure: FAUCETT ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.80m (5.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $530,000,  Roadway Improvement Cost: $53,000,  Total Project Cost: $583,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1648,  Location: PARRISH (Lat: 33.760000,  Lng: -87.250000),  Route carried "on" structure: County highway ,  Year Built: 1985,  Status: Open,  Structure Length: 4.79m (15.72ft),  Average Daily Traffic: 2,900 (year 1995),  Truck Traffic: 20%,  Average Future Daily Traffic: 3,500 (year 2033),  Design Load: HS 20,  Features Intersected: SOUTHERN RAILWAY,  Facility Carried by Structure: NEW PARRISH HWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.047,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 16.5m (54.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Very good,  Operating Rating: 52.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 5.80m (19.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $1,193,000,  Roadway Improvement Cost: $119,000,  Total Project Cost: $1,312,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 17463,  Location: 0.5 MI W OF POLLARD (Lat: 31.027108,  Lng: -87.178322),  Route carried "on" structure: County highway 30,  Year Built: 1999,  Status: Open,  Structure Length: 0.75m (2.46ft),  Average Daily Traffic: 280 (year 1998),  Truck Traffic: 5%,  Average Future Daily Traffic: 420 (year 2034),  Design Load: HS 20,  Features Intersected: BAY BRANCH,  Facility Carried by Structure: COUNTY HIGHWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.9m (42.3ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 35.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $355,000,  Roadway Improvement Cost: $36,000,  Total Project Cost: $391,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 18676,  Location: .75 N POLLARD (Lat: 31.041675,  Lng: -87.175161),  Route carried "on" structure: County highway 30,  Year Built: 2003,  Status: Open,  Structure Length: 1.32m (4.33ft),  Average Daily Traffic: 280 (year 2003),  Truck Traffic: 5%,  Average Future Daily Traffic: 420 (year 2034),  Design Load: HS 20,  Features Intersected: JERNIGAN MILL CREEK,  Facility Carried by Structure: COUNTY HIGHWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 12.9m (42.3ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 84.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.99m (6.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $506,000,  Roadway Improvement Cost: $51,000,  Total Project Cost: $557,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Discuss Pollard, Alabama (AL) on our hugely popular Alabama forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.