Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Hooverson Heights, West Virginia (WV)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 12Number of bridges
  • 89ft / 27.2mTotal length
  • $3,869,000Total costs
  • 8,950Total average daily traffic
  • 267Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Hooverson Heights
  • No street view available for this location

New bridges in Hooverson Heights, WV - historical statistics
  • New bridges - historical statistics
  • 31900-1909
  • 11960-1969
  • 31980-1989
  • 51990-1999
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 62.5%Good
  • 12.5%Satisfactory
  • 25.0%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 75.0%Good
  • 12.5%Satisfactory
  • 12.5%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 37.5%Good
  • 50.0%Fair
  • 12.5%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 11.1%Good
  • 11.1%Satisfactory
  • 55.6%Fair
  • 22.2%Poor
Find on map >>   Show street view

Structure Number: 5A016,  Location: 0.28 mi. East jct WV 2 (Lat: 40.306261,  Lng: -80.594811),  Route carried "on" structure: County highway 7,  Year Built: 1960,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 3.87m (12.70ft),  Average Daily Traffic: 3,000 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 4,470 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: Cross Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.451,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 15.0m (49.2ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Poor,  Channel: Poor,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.63m (15.19ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: July 2020,  Underwater Inspection Date: August 2020,  Bridge Improvement Cost: $506,000,  Roadway Improvement Cost: $486,000,  Total Project Cost: $992,000 ( Estimate for 2018),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 5A02,  Location: 0.01 mi. West jct CR 7/2 (Lat: 40.309969,  Lng: -80.571781),  Route carried "on" structure: County highway 7,  Year Built: 1989,  Status: Open,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 900 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,341 (year 2040),  Design Load: HS 20,  Features Intersected: Bosley Run
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.65m (5.41ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: April 2021,  Other Special Inspection Date: April 2021,  Bridge Improvement Cost: $170,000,  Roadway Improvement Cost: $168,000,  Total Project Cost: $338,000 ( Estimate for 2019),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A021,  Location: 0.18 mi. East jct CR 14 (Lat: 40.305781,  Lng: -80.561761),  Route carried "on" structure: County highway 7,  Year Built: 1995,  Status: Open,  Structure Length: 1.68m (5.51ft),  Average Daily Traffic: 450 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 671 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: Ebenezer Run
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.281,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Skew: 5 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.1m (23.3ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.93m (9.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $263,000,  Roadway Improvement Cost: $15,000,  Total Project Cost: $350,000 ( Estimate for 2019)
Find on map >>   Show street view

Structure Number: 5A022,  Location: 0.01 mi. East jct CR7/4 (Lat: 40.299850,  Lng: -80.532231),  Route carried "on" structure: County highway 7,  Year Built: 1989,  Status: Open,  Structure Length: 1.08m (3.54ft),  Average Daily Traffic: 150 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 224 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: Scott Run
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.435,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.3m (30.5ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 4.6m (15.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 60.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.86m (6.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $129,000,  Roadway Improvement Cost: $128,000,  Total Project Cost: $257,000 ( Estimate for 2019),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A023,  Location: 0.04 mi. South jct CR 7 (Lat: 40.306000,  Lng: -80.565650),  Route carried "on" structure: County highway 76,  Year Built: 1986,  Status: Open,  Structure Length: 3.78m (12.40ft),  Average Daily Traffic: 100 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 149 (year 2039),  Design Load: HS 20,  Features Intersected: Cross Creek,  Facility Carried by Structure: County Route 7/6
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.064,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 18.3m (60.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 52.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.78m (12.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $89,000,  Total Project Cost: $89,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A033,  Location: 0.02 mi. South jct CR 7 (Lat: 40.302181,  Lng: -80.545161),  Route carried "on" structure: County highway 275,  Year Built: 1996,  Status: Open,  Structure Length: 3.69m (12.11ft),  Average Daily Traffic: 300 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 447 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: Cross Creek,  Facility Carried by Structure: County Route 27/5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.235,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 17.7m (58.1ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Poor,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 61.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 3.72m (12.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $436,000,  Roadway Improvement Cost: $427,000,  Total Project Cost: $900,000 ( Estimate for 2020),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A076,  Location: 0.20 mi. West jct CR7/1 (Lat: 40.305450,  Lng: -80.577250),  Route carried "on" structure: County highway 7,  Year Built: 1998,  Status: Open,  Structure Length: 5.04m (16.54ft),  Average Daily Traffic: 950 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,416 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: Cross Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.076,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.7m (35.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.6m (34.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 4.91m (16.11ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $183,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $300,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A077,  Location: 0.03 mi. West jct CR18/1 (Lat: 40.304400,  Lng: -80.580789),  Route carried "on" structure: County highway 7,  Year Built: 1998,  Status: Open,  Structure Length: 4.34m (14.24ft),  Average Daily Traffic: 3,000 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 4,470 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: Cross Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.706,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.7m (35.1ft),  Skew: 9 degrees,  Material/Design: Steel continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 1,  Length of Maximum Span: 22.8m (74.8ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.6m (34.8ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 4.36m (14.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $136,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $186,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 5A08,  Location: 0.20 mi. South jct CR 7 (Lat: 40.302139,  Lng: -80.584139),  Route carried "on" structure: Other road 953,  Year Built: 1991,  Status: Posted for load,  Structure Length: 2.73m (8.96ft),  Average Daily Traffic: 100 (year 2019),  Truck Traffic: 3%,  Average Future Daily Traffic: 149 (year 2039),  Features Intersected: Cross Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 13.3m (43.6ft),  Curb-To-Curb Width: 4.8m (15.7ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Channel: Fair,  Operating Rating: 25.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 15.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: July 2021,  Other Special Inspection Date: July 2021,  Bridge Improvement Cost: $211,000,  Roadway Improvement Cost: $206,000,  Total Project Cost: $457,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 5A01,  Location: 0.23 mi. North jct CR 7 (Lat: 40.310389,  Lng: -80.601669),  Route carried "under" structure: State highway 2,  Year Built: 1902,  Structure Length: 0. m,  Features Intersected: West Virginia Route 2,  Facility Carried by Structure: Whg & Lake Erie RR
Minimum Vertical Clearance: 10.06m (33.01ft),  Kilometerpoint: 16.464,  Lanes under structure: 2,  Length of Maximum Span: 12.2m (40.0ft)

Find on map >>   Show street view

Structure Number: 5A018,  Location: 0.01 mi. East jct CR18/1 (Lat: 40.304800,  Lng: -80.580561),  Route carried "under" structure: County highway 7,  Year Built: 1902,  Structure Length: 0. m,  Features Intersected: County Rt. 7 & Cross Crk,  Facility Carried by Structure: Whg & Lake Erie RR
Minimum Vertical Clearance: 8.84m (29.00ft),  Kilometerpoint: 1.770,  Lanes under structure: 2,  Length of Maximum Span: 9.9m (32.5ft)

Find on map >>   Show street view

Structure Number: 5A031,  Location: 0.04 mi. South jct CR 7 (Lat: 40.301819,  Lng: -80.546200),  Route carried "under" structure: County highway 275,  Year Built: 1902,  Structure Length: 0. m,  Features Intersected: County Route 27/5,  Facility Carried by Structure: Whg & Lake Erie RR
Minimum Vertical Clearance: 3.81m (12.50ft),  Kilometerpoint: 3.187,  Lanes under structure: 2,  Length of Maximum Span: 11.4m (37.4ft)

Discuss Hooverson Heights, West Virginia (WV) on our hugely popular West Virginia forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.