Bridge Statistics for Cayuga, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 12Number of bridges
  • 121ft / 37.4mTotal length
  • $5,210,000Total costs
  • 13,750Total average daily traffic
  • 2,042Total average daily truck traffic
  • 22,000Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Cayuga
  • No street view available for this location

New bridges in Cayuga, OK - historical statistics
  • New bridges - historical statistics
  • 11930-1939
  • 21940-1949
  • 51960-1969
  • 22000-2009
  • 22010-2019
Average Bridge Daily Traffic in Cayuga, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 75.0%Good
  • 25.0%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 50.0%Good
  • 25.0%Satisfactory
  • 25.0%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 50.0%Good
  • 25.0%Satisfactory
  • 25.0%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 33.3%Very good
  • 16.7%Good
  • 16.7%Satisfactory
  • 33.3%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 12.5%Good
  • 62.5%Satisfactory
  • 25.0%Fair
Find on map >>   Show street view

Structure Number: 6969,  Location: 3.8NW OF SH 10&25 JCT (Lat: 36.641317,  Lng: -94.715589),  Route carried "on" structure: County highway N4650,  Year Built: 1939,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.68m (12.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $188,000,  Roadway Improvement Cost: $103,000,  Total Project Cost: $298,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 8165,  Location: 4.5 E. LN TURKEY FORD (Lat: 36.682511,  Lng: -94.635158),  Route carried "on" structure: County highway E0230,  Year Built: 1940,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 5.9m (19.4ft),  Out-to-Out Width: 6.2m (20.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 61.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $156,000,  Roadway Improvement Cost: $86,000,  Total Project Cost: $246,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 10513,  Location: 6.1 MI E US59 (Lat: 36.638031,  Lng: -94.707308),  Route carried "on" structure: State highway 10,  Year Built: 1946,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 4,100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 6,560 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.606,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 42.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.46m (4.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16657,  Location: 1.2E OF S.H. 10 (Lat: 36.667767,  Lng: -94.683364),  Route carried "on" structure: County highway E0240,  Year Built: 1966,  Status: Posted for load,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 960 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,536 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.092,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.9m (22.6ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 39.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16658,  Location: 2.0E OF S.H. 10 (Lat: 36.667789,  Lng: -94.666947),  Route carried "on" structure: County highway E0240,  Year Built: 1966,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 960 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,536 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.619,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 45.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 16673,  Location: 1.1E OF S.H. 10 (Lat: 36.667772,  Lng: -94.688625),  Route carried "on" structure: County highway E0240,  Year Built: 1966,  Status: Posted for load,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 960 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,536 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.931,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 34.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16674,  Location: 2.9E OF S.H. 10 (Lat: 36.667836,  Lng: -94.651308),  Route carried "on" structure: County highway E0240,  Year Built: 1966,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 960 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,536 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.068,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 43.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 16711,  Location: 1.2W OF TIFF CITY MO. (Lat: 36.667892,  Lng: -94.641036),  Route carried "on" structure: County highway E0240,  Year Built: 1966,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 960 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,536 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.033,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 6 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.2m (17.1ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 52.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.40m (14.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 29164,  Location: 1.35S OF OTTAWA C/L (Lat: 36.648056,  Lng: -94.706389),  Route carried "on" structure: State highway 10000,  Year Built: 2014,  Status: Open,  Structure Length: 25.91m (85.01ft),  Average Daily Traffic: 4,100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 6,560 (year 2040),  Design Load: HL 93,  Features Intersected: ELK RIVER,  Facility Carried by Structure: S.H. 10
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.246,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 9,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 16.5m (54.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 28.50m (93.50ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: June 2021,  Underwater Inspection Date: June 2020,  Bridge Improvement Cost: $777,000,  Roadway Improvement Cost: $1,333,000,  Total Project Cost: $2,222,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 29402,  Location: 2.5NE OF S.H. 10 (Lat: 36.625000,  Lng: -94.701389),  Route carried "on" structure: County highway E0270,  Year Built: 2008,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 66.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 30201,  Location: 8NE OF GROVE (Lat: 36.612222,  Lng: -94.657222),  Route carried "on" structure: County highway E0280,  Year Built: 2012,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 350 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 560 (year 2040),  Design Load: HS 20,  Features Intersected: CARR CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Total Project Cost: $225,000,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 30306,  Location: .1N OF E0240 (Lat: 36.669167,  Lng: -94.643333),  Route carried "on" structure: County highway N4690,  Year Built: 2008,  Status: Open,  Structure Length: 0.62m (2.03ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: TRIB TO ELK RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.7m (8.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 93.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Total Project Cost: $225,000
Discuss Cayuga, Oklahoma (OK) on our hugely popular Oklahoma forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.