Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Oak Hill, West Virginia (WV)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 15Number of bridges
  • 102ft / 31.4mTotal length
  • $6,448,000Total costs
  • 145,326Total average daily traffic
  • 15,557Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Oak Hill
  • No street view available for this location

New bridges in Oak Hill, WV - historical statistics
  • New bridges - historical statistics
  • 21910-1919
  • 21930-1939
  • 91960-1969
  • 22000-2009
Average Bridge Daily Traffic in Oak Hill, WV
Average Bridge Truck Traffic in Oak Hill, WV
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 14.3%Good
  • 28.6%Satisfactory
  • 28.6%Fair
  • 28.6%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 14.3%Good
  • 28.6%Satisfactory
  • 42.9%Fair
  • 14.3%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 28.6%Satisfactory
  • 42.9%Fair
  • 28.6%Poor
Find on map >>   Show street view

Structure Number: 10A092,  Location: 0.06 Miles S. of CR 19/43 (Lat: 37.986200,  Lng: -81.144100),  Route carried "on" structure: County highway 6128,  Year Built: 1965,  Status: Posted for load,  Structure Length: 5.66m (18.57ft),  Average Daily Traffic: 2,427 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,961 (year 2040),  Design Load: H 15,  Features Intersected: U.S. 19 NBL & SBL,  Facility Carried by Structure: COUNTY ROUTE 61/28
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.012,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 15.1m (49.5ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 5.67m (18.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $156,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 10A096,  Location: 0.54 Miles N. of CR 19/25 (Lat: 37.967769,  Lng: -81.147289),  Route carried "on" structure: State highway 1600,  Year Built: 1961,  Status: Open,  Structure Length: 6.14m (20.14ft),  Average Daily Traffic: 8,979 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 10,954 (year 2039),  Design Load: H 20,  Features Intersected: US 19,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.521,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 30.2m (99.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Poor,  Superstructure: Fair,  Substructure: Poor,  Operating Rating: 68.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: High priority of replacement,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 6.16m (20.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,448,000,  Roadway Improvement Cost: $949,000,  Total Project Cost: $2,398,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 10A097,  Location: 0.20 Miles S. of CR 17 (Lat: 37.976389,  Lng: -81.140539),  Route carried "on" structure: State highway 1600,  Year Built: 1960,  Status: Posted for load,  Structure Length: 7.26m (23.82ft),  Average Daily Traffic: 7,391 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 9,017 (year 2040),  Design Load: HS 20,  Features Intersected: US 19 NBL & SBL,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.969,  Lanes on structure: 3,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 15.9m (52.2ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 3,  Length of Maximum Span: 20.4m (66.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 15.9m (52.2ft),  Out-to-Out Width: 19.5m (64.0ft)

Condition: Deck: Poor,  Superstructure: Fair,  Substructure: Poor,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.25m (23.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $2,105,000,  Roadway Improvement Cost: $1,389,000,  Total Project Cost: $3,494,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 10A098,  Location: 0.13 Miles N. of CR 17/2 (Lat: 37.979831,  Lng: -81.138619),  Route carried "on" structure: State highway 1600,  Year Built: 1939,  Status: Open,  Structure Length: 1.00m (3.28ft),  Average Daily Traffic: 6,819 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,319 (year 2039),  Features Intersected: COUNTY RT 17,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.452,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 5 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.0m,  Curb-To-Curb Width: 10.7m (35.1ft),  Out-to-Out Width: 13.3m (43.6ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $113,000,  Roadway Improvement Cost: $112,000,  Total Project Cost: $248,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10A131,  Location: 0.10 Miles S. of CR 38/4 (Lat: 37.999400,  Lng: -81.142719),  Route carried "on" structure: County highway 3800,  Year Built: 1964,  Status: Open,  Structure Length: 5.53m (18.14ft),  Average Daily Traffic: 2,000 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,440 (year 2040),  Design Load: HS 20,  Features Intersected: US 19,  Facility Carried by Structure: COUNTY ROUTE 38
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.681,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 2,  Length of Maximum Span: 14.5m (47.6ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: December 2021,  Other Special Inspection Date: December 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 10A263,  Location: 0.01 Miles W. of WV 61 (Lat: 38.012389,  Lng: -81.203269),  Route carried "on" structure: Other road 96900,  Year Built: 1965,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 10 (year 2020),  Truck Traffic: 28%,  Average Future Daily Traffic: 12 (year 2040),  Features Intersected: LOOP CREEK,  Facility Carried by Structure: HARP ROUTE 969
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 3.0m (9.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.7m (25.3ft),  Curb-To-Curb Width: 3.6m (11.8ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Excellent,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.88m (2.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $55,000,  Roadway Improvement Cost: $54,000,  Total Project Cost: $152,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Deck Protection: Other
Find on map >>   Show street view

Structure Number: 10A295,  Location: 0.12 Miles W. of WV 16 (Lat: 38.007450,  Lng: -81.132319),  Route carried "on" structure: State highway 2118,  Year Built: 2007,  Status: Open,  Structure Length: 4.97m (16.31ft),  Average Daily Traffic: 2,100 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,562 (year 2040),  Features Intersected: US 19 NBL & SBL,  Facility Carried by Structure: COUNTY ROUTE 21/18
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.513,  Lanes on structure: 3,  Lanes under structure: 5,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 1,  Length of Maximum Span: 26.2m (86.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 0.0m,  Curb-To-Curb Width: 17.7m (58.1ft),  Out-to-Out Width: 20.2m (66.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 10A033,  Location: 0.14 Miles E. of CR 15/2 (Lat: 37.966039,  Lng: -81.221461),  Route carried "under" structure: State highway 61200,  Year Built: 1911,  Structure Length: 0. m,  Features Intersected: WV 612,  Facility Carried by Structure: NORFOLK SOUTHERN R
Minimum Vertical Clearance: 17.98m (58.99ft),  Kilometerpoint: 7.065,  Lanes under structure: 2,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 18.5m (60.7ft)

Find on map >>   Show street view

Structure Number: 10A054,  Location: 0.46 Miles E. of CR 15/6 (Lat: 37.971839,  Lng: -81.200631),  Route carried "under" structure: County highway 1502,  Year Built: 1911,  Structure Length: 0. m,  Features Intersected: CR 15/2,  Facility Carried by Structure: NORFOLK SOUTHERN R
Minimum Vertical Clearance: 19.81m (64.99ft),  Kilometerpoint: 2.511,  Lanes under structure: 2,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 19.2m (63.0ft)

Find on map >>   Show street view

Structure Number: 10A092,  Location: 0.06 Miles S. of CR 19/43 (Lat: 37.986178,  Lng: -81.144086),  Route carried "under" structure: US 1900,  Year Built: 1965,  Structure Length: 0. m,  Average Daily Traffic: 18,000 (year 0006),  Truck Traffic: 15%,  Features Intersected: U.S. 19 NBL & SBL,  Facility Carried by Structure: COUNTY ROUTE 61/28
Minimum Vertical Clearance: 4.52m (14.83ft),  Kilometerpoint: 13.245,  Lanes on structure: 2,  Lanes under structure: 4,  Length of Maximum Span: 15.1m (49.5ft)

Find on map >>   Show street view

Structure Number: 10A096,  Location: 0.54 Miles N. of CR 19/25 (Lat: 37.967778,  Lng: -81.147297),  Route carried "under" structure: US 1900,  Year Built: 1961,  Structure Length: 0. m,  Average Daily Traffic: 24,200 (year 0012),  Truck Traffic: 13%,  Features Intersected: US 19,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 9.96m (32.68ft),  Kilometerpoint: 10.879,  Lanes on structure: 2,  Lanes under structure: 4,  Length of Maximum Span: 30.2m (99.1ft)

Find on map >>   Show street view

Structure Number: 10A097,  Location: 0.20 Miles S. of CR 17 (Lat: 37.976392,  Lng: -81.140547),  Route carried "under" structure: US 1900,  Year Built: 1960,  Structure Length: 0. m,  Average Daily Traffic: 24,200 (year 0012),  Truck Traffic: 13%,  Features Intersected: US 19 NBL & SBL,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 4.37m (14.34ft),  Kilometerpoint: 12.167,  Lanes on structure: 3,  Lanes under structure: 4,  Length of Maximum Span: 20.4m (66.9ft)

Find on map >>   Show street view

Structure Number: 10A098,  Location: 0.13 Miles N. of CR 17/2 (Lat: 37.979833,  Lng: -81.138628),  Route carried "under" structure: County highway 1700,  Year Built: 1939,  Structure Length: 0. m,  Average Daily Traffic: 1,600 (year 0012),  Truck Traffic: 6%,  Features Intersected: COUNTY RT 17,  Facility Carried by Structure: WV 16
Minimum Vertical Clearance: 4.17m (13.68ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Lanes under structure: 2,  Length of Maximum Span: 9.1m (29.9ft)

Find on map >>   Show street view

Structure Number: 10A131,  Location: 0.10 Miles S. of CR 38/4 (Lat: 37.999400,  Lng: -81.142756),  Route carried "under" structure: US 1900,  Year Built: 1964,  Structure Length: 0. m,  Average Daily Traffic: 24,200 (year 0012),  Truck Traffic: 13%,  Features Intersected: US 19,  Facility Carried by Structure: COUNTY ROUTE 38
Minimum Vertical Clearance: 4.60m (15.09ft),  Kilometerpoint: 14.790,  Lanes on structure: 2,  Lanes under structure: 4,  Length of Maximum Span: 14.5m (47.6ft)

Find on map >>   Show street view

Structure Number: 10A295,  Location: 0.12 Miles W. of WV 16 (Lat: 38.007450,  Lng: -81.132325),  Route carried "under" structure: US 1900,  Year Built: 2007,  Structure Length: 0. m,  Average Daily Traffic: 23,400 (year 0012),  Truck Traffic: 6%,  Features Intersected: US 19 NBL & SBL,  Facility Carried by Structure: COUNTY ROUTE 21/18
Minimum Vertical Clearance: 5.94m (19.49ft),  Kilometerpoint: 16.351,  Lanes on structure: 3,  Lanes under structure: 5,  Length of Maximum Span: 26.2m (86.0ft)

Discuss Oak Hill, West Virginia (WV) on our hugely popular West Virginia forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.