Bridge Statistics for Rushford, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 17Number of bridges
  • 85ft / 25.6mTotal length
  • $14,558,000Total costs
  • 12,847Total average daily traffic
  • 1,880Total average daily truck traffic
  • 15,047Total future (year 2037) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Rushford
  • No street view available for this location

New bridges in Rushford, NY - historical statistics
  • New bridges - historical statistics
  • 51960-1969
  • 31970-1979
  • 11980-1989
  • 31990-1999
  • 42000-2009
  • 12010-2019
Reconstructed bridges in Rushford, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11990-1999
  • 12000-2009
Average Bridge Truck Traffic in Rushford, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 25.0%Excellent
  • 33.3%Very good
  • 33.3%Good
  • 8.3%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 23.1%Excellent
  • 15.4%Very good
  • 46.2%Good
  • 7.7%Satisfactory
  • 7.7%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 15.4%Excellent
  • 15.4%Very good
  • 46.2%Good
  • 15.4%Satisfactory
  • 7.7%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 11.8%Excellent
  • 5.9%Very good
  • 17.6%Good
  • 47.1%Satisfactory
  • 17.6%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 25.0%Good
  • 50.0%Satisfactory
  • 25.0%Fair
Find on map >>   Show street view

Structure Number: 104284,  Location: 0.2 MI NW OF RUSHFORD (Lat: 42.397961,  Lng: -78.255839),  Route carried "on" structure: State highway 243,  Year Built: 1965,  Status: Open,  Structure Length: 1.62m (5.31ft),  Average Daily Traffic: 2,235 (year 2017),  Truck Traffic: 18%,  Average Future Daily Traffic: 2,248 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: INDIAN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.693,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.3m (24.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $746,000,  Roadway Improvement Cost: $437,000,  Total Project Cost: $1,183,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 104285,  Location: .8 MILE EAST OF RUSHFORD (Lat: 42.387497,  Lng: -78.242181),  Route carried "on" structure: State highway 243,  Year Built: 2005,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 2,988 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 3,006 (year 2040),  Design Load: H 20,  Features Intersected: BOONE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.399,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.9m (35.8ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 85.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $664,000,  Roadway Improvement Cost: $389,000,  Total Project Cost: $1,052,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 106198,  Location: 2.7 mi SE Jct CL & Rt 243 (Lat: 42.412492,  Lng: -78.274031),  Route carried "on" structure: State highway 243,  Year Built: 1969,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 2,235 (year 2017),  Truck Traffic: 18%,  Average Future Daily Traffic: 2,248 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: Indian Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.328,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.5m (18.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 75.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 29.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $331,000,  Roadway Improvement Cost: $194,000,  Total Project Cost: $524,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 121493,  Location: 1.6 MI NW OF RUSHFORD (Lat: 42.410661,  Lng: -78.265406),  Route carried "on" structure: Bypass Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 84 (year 2018),  Truck Traffic: 10%,  Average Future Daily Traffic: 118 (year 2038),  Features Intersected: INDIAN CREEK,  Facility Carried by Structure: BROOKSIDE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.032,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.9m (12.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 89.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.88m (2.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $140,000,  Roadway Improvement Cost: $82,000,  Total Project Cost: $222,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 221494,  Location: .2 MILE WEST OF RUSHFORD (Lat: 42.392314,  Lng: -78.254064),  Route carried "on" structure: Other road ,  Year Built: 1966,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 287 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 402 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: INDIAN CREEK,  Facility Carried by Structure: WEST BRANCH ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.032,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 9.7m (31.8ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 78.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $519,000,  Roadway Improvement Cost: $304,000,  Total Project Cost: $823,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221495,  Location: 3.1 MI SE OF RUSHFORD (Lat: 42.351992,  Lng: -78.217172),  Route carried "on" structure: Other road ,  Year Built: 1986,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 12 (year 2018),  Average Future Daily Traffic: 17 (year 2038),  Design Load: HS 20,  Features Intersected: RUSH CREEK,  Facility Carried by Structure: BARBER HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.124,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $442,000,  Roadway Improvement Cost: $259,000,  Total Project Cost: $701,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221496,  Location: 3.0 MI SE OF RUSHFORD (Lat: 42.349214,  Lng: -78.227819),  Route carried "on" structure: Other road ,  Year Built: 2016,  Status: Open,  Structure Length: 1.31m (4.30ft),  Average Daily Traffic: 7 (year 2018),  Average Future Daily Traffic: 10 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: RUSH CREEK,  Facility Carried by Structure: BARBER ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.048,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.31m (4.30ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Critical Feature Inspection Date: June 2020,  Bridge Improvement Cost: $399,000,  Roadway Improvement Cost: $234,000,  Total Project Cost: $633,000 ( Estimate for 2021),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221498,  Location: 2.4 MI NORTH OF RUSHFORD (Lat: 42.424278,  Lng: -78.246669),  Route carried "on" structure: Other road ,  Year Built: 1992,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 126 (year 2018),  Truck Traffic: 2%,  Average Future Daily Traffic: 176 (year 2038),  Design Load: HS 20,  Features Intersected: TRIB CANEADEA CRK,  Facility Carried by Structure: E CENTERVILLE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.331,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 9.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $665,000,  Roadway Improvement Cost: $390,000,  Total Project Cost: $1,055,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 225582,  Location: 1.5 MI N OF RUSHFORD (Lat: 42.414236,  Lng: -78.241069),  Route carried "on" structure: Other road ,  Year Built: 1977,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 50 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 70 (year 2038),  Features Intersected: CENTERVILLE CREEK,  Facility Carried by Structure: ORCHARD ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.467,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.0m (32.8ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $363,000,  Roadway Improvement Cost: $212,000,  Total Project Cost: $575,000 ( Estimate for 2021),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 225597,  Location: 2.0 MI NORTH OF RUSHFORD (Lat: 42.419564,  Lng: -78.262444),  Route carried "on" structure: Other road ,  Year Built: 1977,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 41 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 57 (year 2038),  Design Load: HS 20,  Features Intersected: BROOKSIDE CREEK,  Facility Carried by Structure: MEADOWVIEW ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.097,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Very good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Inventory Rating: 66.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.76m (2.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $223,000,  Roadway Improvement Cost: $130,000,  Total Project Cost: $353,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 332129,  Location: 4.1 MI SE OF FARMERSVILLE (Lat: 42.358547,  Lng: -78.308883),  Route carried "on" structure: County highway ,  Year Built: 1994,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 695 (year 2017),  Truck Traffic: 14%,  Average Future Daily Traffic: 973 (year 2037),  Design Load: HS 25 or greater,  Features Intersected: BR CANEADEA CRK,  Facility Carried by Structure: RAWSON ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.920,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.4m (40.7ft),  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 86.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $934,000,  Roadway Improvement Cost: $547,000,  Total Project Cost: $1,481,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 333044,  Location: 4 MI SW OF RUSHFORD (Lat: 42.364017,  Lng: -78.298058),  Route carried "on" structure: County highway ,  Year Built: 2003,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 623 (year 2018),  Truck Traffic: 7%,  Average Future Daily Traffic: 872 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: CANEADEA CREEK,  Facility Carried by Structure: COUNTY ROAD 7B
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.030,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.9m (35.8ft),  Curb-To-Curb Width: 9.5m (31.2ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.15m (3.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $519,000,  Roadway Improvement Cost: $304,000,  Total Project Cost: $824,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 333045,  Location: 0.5 MI SW OF RUSHFORD (Lat: 42.382733,  Lng: -78.254164),  Route carried "on" structure: County highway ,  Year Built: 1992,  Status: Open,  Structure Length: 2.56m (8.40ft),  Average Daily Traffic: 1,194 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 1,672 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: CANEADEA CREEK,  Facility Carried by Structure: COUNTY ROAD 7B
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.342,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.2m (82.7ft),  Curb-To-Curb Width: 9.3m (30.5ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 49.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.56m (8.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $700,000,  Roadway Improvement Cost: $410,000,  Total Project Cost: $1,110,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 333046,  Location: In Rushford (Lat: 42.389039,  Lng: -78.250192),  Route carried "on" structure: County highway ,  Year Built: 2004,  Status: Open,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 647 (year 2018),  Truck Traffic: 12%,  Average Future Daily Traffic: 906 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: INDIAN CREEK,  Facility Carried by Structure: COUNTY ROAD 7E
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.338,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.5m (64.0ft),  Curb-To-Curb Width: 9.5m (31.2ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 48.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 31.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 2.01m (6.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $626,000,  Roadway Improvement Cost: $367,000,  Total Project Cost: $993,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 333047,  Location: 3.2 SE OF RUSHFORD (Lat: 42.359675,  Lng: -78.203669),  Route carried "on" structure: County highway ,  Year Built: 1964,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 297 (year 2018),  Truck Traffic: 7%,  Average Future Daily Traffic: 416 (year 2038),  Design Load: H 20,  Features Intersected: RUSH CREEK,  Facility Carried by Structure: COUNTY ROAD 49
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.988,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $379,000,  Roadway Improvement Cost: $222,000,  Total Project Cost: $600,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 333048,  Location: 1.0 MI E OF RUSHFORD (Lat: 42.386844,  Lng: -78.228817),  Route carried "on" structure: County highway ,  Year Built: 1962,  Status: Open,  Structure Length: 3.44m (11.29ft),  Average Daily Traffic: 521 (year 2018),  Truck Traffic: 22%,  Average Future Daily Traffic: 729 (year 2038),  Design Load: HS 20,  Features Intersected: CANEADEA CREEK,  Facility Carried by Structure: COUNTY ROAD 49
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.177,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 16.4m (53.8ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Very good,  Operating Rating: 52.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.44m (11.29ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $890,000,  Roadway Improvement Cost: $521,000,  Total Project Cost: $1,411,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 333049,  Location: IN RUSHFORD (Lat: 42.391828,  Lng: -78.253503),  Route carried "on" structure: County highway ,  Year Built: 2005,  Status: Open,  Structure Length: 1.71m (5.61ft),  Average Daily Traffic: 805 (year 2018),  Truck Traffic: 13%,  Average Future Daily Traffic: 1,127 (year 2038),  Design Load: HL 93,  Features Intersected: INDIAN CREEK,  Facility Carried by Structure: COUNTY ROAD 7B
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.372,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.2m (53.1ft),  Curb-To-Curb Width: 10.1m (33.1ft),  Out-to-Out Width: 11.2m (36.7ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 86.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.70m (5.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $642,000,  Roadway Improvement Cost: $376,000,  Total Project Cost: $1,018,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other