  • National Bridge Inventory (NBI) Statistics
  • 27Number of bridges
  • 128ft / 38.9mTotal length
  • $2,666,000Total costs
  • 26,361Total average daily traffic
  • 1,558Total average daily truck traffic
  • 47,174Total future (year 2039) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Lynnville
  • No street view available for this location

New bridges in Lynnville, TN - historical statistics
  • New bridges - historical statistics
  • 61920-1929
  • 51930-1939
  • 11940-1949
  • 41950-1959
  • 31960-1969
  • 21970-1979
  • 21980-1989
  • 11990-1999
  • 22000-2009
  • 12010-2019
Reconstructed bridges in Lynnville, TN - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11940-1949
  • 01950-1959
  • 11960-1969
Average Bridge Daily Traffic in Lynnville, TN
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 46.7%Good
  • 53.3%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 46.7%Good
  • 33.3%Satisfactory
  • 20.0%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 6.7%Very good
  • 60.0%Good
  • 13.3%Satisfactory
  • 13.3%Fair
  • 6.7%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.7%Very good
  • 66.7%Good
  • 22.2%Satisfactory
  • 7.4%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 58.3%Good
  • 33.3%Satisfactory
  • 8.3%Poor
Find on map >>   Show street view

Structure Number: 28018910001,  Location: 7 M N OF PULASKI (Lat: 35.273625,  Lng: -87.042775),  Route carried "on" structure: County highway 1891,  Year Built: 1987,  Status: Open,  Structure Length: 4.66m (15.29ft),  Average Daily Traffic: 142 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 227 (year 2042),  Design Load: HS 20,  Features Intersected: RICHLAND CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.048,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 14.3m (46.9ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 28018930001,  Location: .25 M S OF LYNNVILLE (Lat: 35.373194,  Lng: -87.006611),  Route carried "on" structure: City street 1893,  Year Built: 1968,  Status: Open,  Structure Length: 3.63m (11.91ft),  Average Daily Traffic: 299 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 480 (year 2040),  Features Intersected: ROBERTSON FORK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.778,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $106,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $160,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28019080003,  Location: 1.5 M W OF LYNNVILLE (Lat: 35.372175,  Lng: -87.034592),  Route carried "on" structure: County highway 1908,  Year Built: 1956,  Status: Posted for load,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 496 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 794 (year 2041),  Design Load: H 15,  Features Intersected: FRY BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.739,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 23.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 0.88m (2.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $87,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $131,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0730001,  Location: 2 M W OF LYNNVILLE (Lat: 35.371678,  Lng: -87.042406),  Route carried "on" structure: County highway 73,  Year Built: 1984,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 190 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 304 (year 2040),  Design Load: HS 20,  Features Intersected: LYNN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.293,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 61.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 280A0820001,  Location: 2 M W OF LYNNVILLE (Lat: 35.382608,  Lng: -87.037572),  Route carried "on" structure: County highway 82,  Year Built: 1939,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 260 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 416 (year 2040),  Design Load: H 15,  Features Intersected: FRY BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.929,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 6.0m (19.7ft),  Out-to-Out Width: 6.4m (21.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.13m (3.71ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $151,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0820003,  Location: 3.5 M NW OF LYNNVILLE (Lat: 35.394633,  Lng: -87.039753),  Route carried "on" structure: County highway 82,  Year Built: 1939,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 260 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 416 (year 2040),  Features Intersected: FRY BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.330,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $87,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $131,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0820005,  Location: 4 M NW OF LYNNVILLE (Lat: 35.403603,  Lng: -87.042714),  Route carried "on" structure: County highway 82,  Year Built: 1939,  Year Reconstructed: 1974,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 260 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 416 (year 2040),  Features Intersected: FRY BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.359,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 41.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0920001,  Location: 1 M N OF LYNNVILLE (Lat: 35.390597,  Lng: -87.021761),  Route carried "on" structure: County highway 92,  Year Built: 2010,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 230 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 368 (year 2040),  Design Load: HS 20,  Features Intersected: EAST FORK OF LYNN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.879,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0960001,  Location: 8 M W OF LYNNVILLE (Lat: 35.383167,  Lng: -86.979083),  Route carried "on" structure: County highway 96,  Year Built: 1958,  Status: Posted for load,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 170 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 272 (year 2040),  Features Intersected: TRIGG BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.404,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 26.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $59,000,  Roadway Improvement Cost: $6,000,  Total Project Cost: $89,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A0960003,  Location: 8.5 M W OF LYNNVILLE (Lat: 35.387667,  Lng: -86.977944),  Route carried "on" structure: County highway 96,  Year Built: 1966,  Status: Posted for load,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 170 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 272 (year 2040),  Features Intersected: TRIGG BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.879,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 31.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $54,000,  Roadway Improvement Cost: $6,000,  Total Project Cost: $82,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 280A1010001,  Location: 3 M E OF LYNNVILLE (Lat: 35.384583,  Lng: -86.952944),  Route carried "on" structure: County highway 101,  Year Built: 2007,  Status: Open,  Structure Length: 1.74m (5.71ft),  Average Daily Traffic: 40 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 64 (year 2040),  Design Load: HS 20,  Features Intersected: ROBERTSON FORK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.403,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.5m (18.0ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 280A1100001,  Location: 1 M E OF LYNNVILLE (Lat: 35.377111,  Lng: -86.977278),  Route carried "on" structure: County highway 110,  Year Built: 1950,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 180 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 288 (year 2040),  Design Load: H 15,  Features Intersected: ROBERTSON FORK BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.3m (17.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Poor,  Channel: Good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $142,000,  Roadway Improvement Cost: $15,000,  Total Project Cost: $214,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 280A1100003,  Location: 2 M SE OF LYNNVILLE (Lat: 35.367167,  Lng: -86.974167),  Route carried "on" structure: County highway 110,  Year Built: 1950,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 180 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 288 (year 2040),  Features Intersected: TRADE BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.518,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.7m (8.9ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28F00530007,  Location: 12 M. N. PULASKI. (Lat: 35.328797,  Lng: -87.037794),  Route carried "on" structure: County highway 966,  Year Built: 1930,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 651 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,312 (year 2040),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.579,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $99,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $149,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28S62380001,  Location: 4.5 M. S. LYNNVILLE. (Lat: 35.330472,  Lng: -87.031833),  Route carried "on" structure: County highway 962,  Year Built: 1968,  Status: Open,  Structure Length: 3.35m (10.99ft),  Average Daily Traffic: 996 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,594 (year 2041),  Design Load: HS 20,  Features Intersected: ROBERTSON FORK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.032,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 12.0m (39.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 51.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2020,  Underwater Inspection Date: August 2018,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 28S62380003,  Location: 4.5 M. S. LYNNVILLE. (Lat: 35.324778,  Lng: -86.991500),  Route carried "on" structure: County highway 962,  Year Built: 1973,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 996 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,776 (year 2040),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.782,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020
Find on map >>   Show street view

Structure Number: 28SR0070043,  Location: 11.7 MI.N.OF PULASKI (Lat: 35.368586,  Lng: -87.034739),  Route carried "on" structure: US 31,  Year Built: 1927,  Status: Posted for load,  Structure Length: 2.83m (9.28ft),  Average Daily Traffic: 3,663 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 5,861 (year 2041),  Design Load: H 15,  Features Intersected: LYNN CREEK,  Facility Carried by Structure: FAP 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 52.240,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 38.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.83m (9.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $184,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $277,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28SR0070045,  Location: 13.5 MI.N.OF PULASKI (Lat: 35.391203,  Lng: -87.022514),  Route carried "on" structure: US 31,  Year Built: 1927,  Status: Open,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 3,056 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 5,536 (year 2040),  Design Load: H 15,  Features Intersected: EAST LYNN CREEK,  Facility Carried by Structure: FAP 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 55.088,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 73.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.44m (8.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $161,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $242,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28SR0070047,  Location: 15 NI.N.OF PULASKI (Lat: 35.412417,  Lng: -87.028181),  Route carried "on" structure: US 31,  Year Built: 1926,  Status: Posted for load,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 3,056 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 5,536 (year 2040),  Design Load: H 15,  Features Intersected: BRANCH,  Facility Carried by Structure: FAP 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 57.518,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 4 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 22.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $109,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $164,000 ( Estimate for 2020)
Find on map >>   Show street view

Structure Number: 28SR0070051,  Location: 8.9 MI.NORTH OF PULASKI (Lat: 35.327597,  Lng: -87.031631),  Route carried "on" structure: US 31,  Year Built: 1927,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 3,028 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 6,688 (year 2039),  Design Load: HS 20,  Features Intersected: BRANCH,  Facility Carried by Structure: FAP 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 47.685,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 32.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021
Find on map >>   Show street view

Structure Number: 28SR0070053,  Location: 2.5 MI S. MAURY CO LN (Lat: 35.396919,  Lng: -87.024497),  Route carried "on" structure: US 31,  Year Built: 1926,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 3,056 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,890 (year 2042),  Design Load: H 15,  Features Intersected: BRANCH,  Facility Carried by Structure: FAP 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 55.764,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021
Find on map >>   Show street view

Structure Number: 28SR1290001,  Location: 1.2 MI.WEST OF LYNNVILLE (Lat: 35.374894,  Lng: -87.030858),  Route carried "on" structure: State highway 129,  Year Built: 1945,  Status: Open,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 1,626 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 3,248 (year 2040),  Design Load: H 15,  Features Intersected: EAST FORK LYNN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.209,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.4m (24.3ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 47.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.04m (6.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Bridge Improvement Cost: $218,000,  Roadway Improvement Cost: $22,000,  Total Project Cost: $328,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 28SR1290003,  Location: 1.2 MI.W.OF MARSHALL CO. (Lat: 35.387125,  Lng: -86.949528),  Route carried "on" structure: State highway 129,  Year Built: 2003,  Status: Open,  Structure Length: 1.20m (3.94ft),  Average Daily Traffic: 892 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,408 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: CALVERT BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.918,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 16.7m (54.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Assigned rating based on Load Factor Design (LFD) reported in metric tons,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned rating based on Load Factor Design (LFD) reported in metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28SR1290005,  Location: 3 MI NE JCT ST7 (Lat: 35.379511,  Lng: -86.980922),  Route carried "on" structure: State highway 129,  Year Built: 1920,  Year Reconstructed: 1954,  Status: Posted for load,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,083 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,128 (year 2040),  Design Load: H 15,  Features Intersected: TRIGG BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.909,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 68.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Bridge Improvement Cost: $32,000,  Roadway Improvement Cost: $4,000,  Total Project Cost: $49,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 28SR1290007,  Location: 1.2 MI.W.OF MARSHALL CO. (Lat: 35.377375,  Lng: -87.004592),  Route carried "on" structure: State highway 129,  Year Built: 1996,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 1,083 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,080 (year 2040),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.688,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.1m (10.2ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 61.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 60018930003,  Location: 1 M S CULLEOKA (Lat: 35.434550,  Lng: -86.998900),  Route carried "on" structure: County highway 1893,  Year Built: 1975,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 148 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 272 (year 2040),  Design Load: HS 20,  Features Intersected: FOUNTAIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.816,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 52.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020
Find on map >>   Show street view

Structure Number: 600A3260001,  Location: 3.5 M. S. CULLEOKA. (Lat: 35.433817,  Lng: -86.977933),  Route carried "on" structure: County highway 326,  Year Built: 1935,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 150 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 240 (year 2040),  Design Load: H 15,  Features Intersected: CAMPBELL STATION BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.822,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.3m (17.4ft)

Condition: Channel: Satisfactory,  Culverts: Poor,  Operating Rating: 41.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.68m (5.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $332,000,  Roadway Improvement Cost: $34,000,  Total Project Cost: $499,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel