Bridge Statistics for Dalton, Massachusetts (MA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 12Number of bridges
  • 102ft / 31.3mTotal length
  • $19,707,000Total costs
  • 60,501Total average daily traffic
  • 5,576Total average daily truck traffic
  • 82,046Total future (year 2032) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Dalton
  • No street view available for this location

New bridges in Dalton, MA - historical statistics
  • New bridges - historical statistics
  • 11900-1909
  • 11920-1929
  • 11930-1939
  • 11940-1949
  • 31950-1959
  • 11970-1979
  • 11990-1999
  • 22000-2009
  • 12010-2019
Reconstructed bridges in Dalton, MA - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11940-1949
  • 11950-1959
  • 01960-1969
  • 01970-1979
  • 11980-1989
Average Bridge Daily Traffic in Dalton, MA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 8.3%Very good
  • 33.3%Good
  • 25.0%Satisfactory
  • 33.3%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 16.7%Very good
  • 25.0%Good
  • 33.3%Satisfactory
  • 25.0%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 16.7%Very good
  • 41.7%Good
  • 33.3%Satisfactory
  • 8.3%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 8.3%Very good
  • 66.7%Good
  • 16.7%Satisfactory
  • 8.3%Fair
Find on map >>   Show street view

Structure Number: D0100100WMUNNBI,  Location: .3MI S OF RT 9 @OLD S. ST (Lat: 42.468456,  Lng: -73.181950),  Route carried "on" structure: City street ,  Year Built: 1957,  Status: Posted for load,  Structure Length: 3.26m (10.70ft),  Average Daily Traffic: 6,572 (year 2018),  Truck Traffic: 1%,  Average Future Daily Traffic: 9,002 (year 2032),  Design Load: H 20,  Features Intersected: WATER E BR HOUSATONIC R,  Facility Carried by Structure: HWY SOUTH ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.0m (59.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 38.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.30m (10.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $1,543,000,  Roadway Improvement Cost: $155,000,  Total Project Cost: $2,315,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D0100200UMUNNBI,  Location: .5 M E OF RTE 9 (Lat: 42.470756,  Lng: -73.168944),  Route carried "on" structure: City street ,  Year Built: 1924,  Year Reconstructed: 1989,  Status: Posted for load,  Structure Length: 4.66m (15.29ft),  Average Daily Traffic: 7,198 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 12,319 (year 2032),  Design Load: H 15,  Features Intersected: WATER E BR HOUSATONIC R,  Facility Carried by Structure: HWY HOUSATONIC
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.853,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Truss - Deck,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 32.0m (105.0ft),  Curb-To-Curb Width: 7.0m (23.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 26.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 4.70m (15.42ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Critical Feature Inspection Date: June 2021,  Bridge Improvement Cost: $1,404,000,  Roadway Improvement Cost: $141,000,  Total Project Cost: $2,107,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D0100400VMUNNBI,  Location: .5 MILES SOUTH OF ROUTE 9 (Lat: 42.477222,  Lng: -73.145000),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Posted for load,  Structure Length: 2.60m (8.53ft),  Average Daily Traffic: 1,300 (year 2011),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,053 (year 2032),  Design Load: H 15,  Features Intersected: WATER E BR HOUSATONIC R,  Facility Carried by Structure: HWY ORCHARD RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 16.2m (53.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 26.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 15.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 2.70m (8.86ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $987,000,  Roadway Improvement Cost: $99,000,  Total Project Cost: $1,481,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D010050BGDOTNBI,  Location: AT DEPOT ST INTERSECTION (Lat: 42.474119,  Lng: -73.156797),  Route carried "on" structure: State highway 8,  Year Built: 1902,  Year Reconstructed: 1954,  Status: Open,  Structure Length: 2.71m (8.89ft),  Average Daily Traffic: 5,850 (year 2017),  Truck Traffic: 10%,  Average Future Daily Traffic: 6,001 (year 2032),  Design Load: H 20,  Features Intersected: WATER E BR HOUSATONIC R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 67.108,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.9m (85.0ft),  Curb or Sidewalk Widths: Left: 2.0m (6.6ft),  Right: 2.0m (6.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 30.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 10.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 2.80m (9.19ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 36 months,  Inspection Date: July 2021,  Underwater Inspection Date: September 2020,  Bridge Improvement Cost: $1,826,000,  Roadway Improvement Cost: $183,000,  Total Project Cost: $2,740,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: D01006045MUNNBI,  Location: 1M E OF JCT RT8&9 (Lat: 42.473703,  Lng: -73.141261),  Route carried "on" structure: City street ,  Year Built: 1973,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 1,069 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 2,527 (year 2032),  Design Load: H 20,  Features Intersected: WATER E BR HOUSATONIC R,  Facility Carried by Structure: HWY OLD WINDSOR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.6m (44.6ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 31.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.50m (4.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $790,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $1,186,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D01007AR2DOTNBI,  Location: 0.3 MI N OF HINSDALE TL (Lat: 42.457417,  Lng: -73.130206),  Route carried "on" structure: State highway 8,  Year Built: 2009,  Status: Open,  Structure Length: 1.97m (6.46ft),  Average Daily Traffic: 8,535 (year 2014),  Truck Traffic: 10%,  Average Future Daily Traffic: 12,003 (year 2031),  Design Load: HS 25 or greater,  Features Intersected: WATER E BR HOUSATONIC R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 63.632,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.5m (34.4ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.0m (59.1ft),  Curb-To-Curb Width: 10.5m (34.4ft),  Out-to-Out Width: 11.5m (37.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Inventory Rating: 64.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.00m (6.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $547,000,  Roadway Improvement Cost: $55,000,  Total Project Cost: $821,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D0100800TMUNNBI,  Location: BETWEEN EAST ST & ROUTE 8 (Lat: 42.466958,  Lng: -73.142036),  Route carried "on" structure: City street ,  Year Built: 1941,  Status: Open,  Structure Length: 2.56m (8.40ft),  Average Daily Traffic: 7,198 (year 2018),  Truck Traffic: 11%,  Average Future Daily Traffic: 7,344 (year 2032),  Design Load: H 20,  Features Intersected: WATER E BR HOUSATONIC R,  Facility Carried by Structure: HWY E HOUSATONIC
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 16.5m (54.1ft),  Curb or Sidewalk Widths: Left: 1.9m (6.2ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 47.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.60m (8.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $1,257,000,  Roadway Improvement Cost: $126,000,  Total Project Cost: $1,886,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D01009AV9DOTNBI,  Location: 500' N OF INT. W/ HOUSATO (Lat: 42.467919,  Lng: -73.142458),  Route carried "on" structure: State highway 8,  Year Built: 2009,  Status: Open,  Structure Length: 3.60m (11.81ft),  Average Daily Traffic: 8,535 (year 2014),  Truck Traffic: 10%,  Average Future Daily Traffic: 12,003 (year 2031),  Design Load: HS 25 or greater,  Features Intersected: WATER E BR HOUSATONIC R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 65.418,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.5m (34.4ft),  Skew: 5 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 32.0m (105.0ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 0.0m,  Curb-To-Curb Width: 10.5m (34.4ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Inventory Rating: 71.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.70m (12.14ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $1,012,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $1,519,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D010100B7DOTNBI,  Location: 1.8 MI W OF WINDSOR TL (Lat: 42.484272,  Lng: -73.148494),  Route carried "on" structure: State highway 9,  Year Built: 1930,  Year Reconstructed: 1955,  Status: Open,  Structure Length: 2.18m (7.15ft),  Average Daily Traffic: 9,000 (year 2018),  Truck Traffic: 12%,  Average Future Daily Traffic: 11,845 (year 2032),  Design Load: H 20,  Features Intersected: WATER WAHCONAH FALLS BRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.233,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.1m (43.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 13.3m (43.6ft),  Out-to-Out Width: 16.0m (52.5ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 46.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $1,383,000,  Roadway Improvement Cost: $139,000,  Total Project Cost: $2,075,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D01011046MUNNBI,  Location: 200 FT WEST OF RTE 9 (Lat: 42.485875,  Lng: -73.137208),  Route carried "on" structure: City street ,  Year Built: 1990,  Status: Posted for load,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 129 (year 2018),  Truck Traffic: 10%,  Average Future Daily Traffic: 158 (year 2033),  Design Load: HS 20,  Features Intersected: WATER WAHCONAH FALLS BRK,  Facility Carried by Structure: HWY HOLIDY CTTG
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.7m (58.1ft),  Curb-To-Curb Width: 3.4m (11.2ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 36.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.80m (9.19ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Critical Feature Inspection Date: Febuary 2022,  Bridge Improvement Cost: $1,658,000,  Roadway Improvement Cost: $166,000,  Total Project Cost: $2,488,000 ( Estimate for 2022),  Deck Structure Type: Steel plate,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: D01012B54MUNNBI,  Location: .2 MI S OF RTE 9/8A (Lat: 42.486211,  Lng: -73.128019),  Route carried "on" structure: City street ,  Year Built: 2013,  Status: Open,  Structure Length: 1.80m (5.91ft),  Average Daily Traffic: 240 (year 2013),  Truck Traffic: 6%,  Design Load: HL 93,  Features Intersected: WATER WAHCONAH FALLS BRK,  Facility Carried by Structure: HWY CLEVELAND RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.6m (28.2ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.7m (54.8ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 77.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 38.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $430,000,  Roadway Improvement Cost: $44,000,  Total Project Cost: $646,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D010190B6DOTNBI,  Location: 0.5 MI E OF ORCHARD RD (Lat: 42.487222,  Lng: -73.131667),  Route carried "on" structure: State highway 9,  Year Built: 1952,  Status: Open,  Structure Length: 2.56m (8.40ft),  Average Daily Traffic: 4,875 (year 2021),  Truck Traffic: 12%,  Average Future Daily Traffic: 6,791 (year 2032),  Design Load: H 20,  Features Intersected: WATER WAHCONAH FALLS BRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.697,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.3m (69.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 63.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.60m (8.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $295,000,  Roadway Improvement Cost: $30,000,  Total Project Cost: $443,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous