Bridge Statistics for Columbia, Alabama (AL)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 15Number of bridges
  • 262ft / 80.2mTotal length
  • $23,043,000Total costs
  • 27,034Total average daily traffic
  • 2,728Total average daily truck traffic
  • 37,987Total future (year 2033) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Columbia
  • No street view available for this location

New bridges in Columbia, AL - historical statistics
  • New bridges - historical statistics
  • 71950-1959
  • 21960-1969
  • 31980-1989
  • 21990-1999
  • 12000-2009
Average Bridge Daily Traffic in Columbia, AL
Average Bridge Truck Traffic in Columbia, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 12.5%Very good
  • 50.0%Good
  • 25.0%Satisfactory
  • 12.5%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 12.5%Very good
  • 37.5%Good
  • 37.5%Satisfactory
  • 12.5%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 12.5%Very good
  • 50.0%Good
  • 37.5%Satisfactory
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 64.3%Good
  • 35.7%Satisfactory
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 71.4%Good
  • 14.3%Satisfactory
  • 14.3%Fair
Find on map >>   Show street view

Structure Number: 2138,  Location: CO RD 38 TO CO RD 42 (Lat: 31.250406,  Lng: -85.137775),  Route carried "on" structure: County highway ,  Year Built: 1987,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 135 (year 1993),  Truck Traffic: 1%,  Average Future Daily Traffic: 250 (year 2033),  Design Load: HS 20,  Features Intersected: WILSON CREEK,  Facility Carried by Structure: MACEDONIA CH RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 74.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.44m (4.72ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $358,000,  Roadway Improvement Cost: $36,000,  Total Project Cost: $394,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 3713,  Location: HENRY CO LINE TO AL52 (Lat: 31.304992,  Lng: -85.161467),  Route carried "on" structure: County highway 22,  Year Built: 1950,  Status: Posted for load,  Structure Length: 4.15m (13.62ft),  Average Daily Traffic: 675 (year 1990),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,200 (year 2033),  Features Intersected: HURRICANE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 35.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 5.12m (16.80ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2021,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $807,000,  Roadway Improvement Cost: $81,000,  Total Project Cost: $888,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 3714,  Location: HENRY CO LINE TO AL 52 (Lat: 31.295500,  Lng: -85.139731),  Route carried "on" structure: County highway 22,  Year Built: 1950,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 640 (year 1990),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,200 (year 2033),  Features Intersected: THOMAS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 83.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.25m (4.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $304,000,  Roadway Improvement Cost: $30,000,  Total Project Cost: $334,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 4397,  Location: ALA 52 TO CO RD 48 (Lat: 31.281758,  Lng: -85.152169),  Route carried "on" structure: County highway 54,  Year Built: 1952,  Status: Open,  Structure Length: 0.62m (2.03ft),  Average Daily Traffic: 655 (year 1993),  Truck Traffic: 7%,  Average Future Daily Traffic: 917 (year 2033),  Features Intersected: THOMAS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.1m (6.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.0m

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 86.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $237,000,  Roadway Improvement Cost: $24,000,  Total Project Cost: $261,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 59,  Location: .5 MILE WEST OF BROOKLYN (Lat: 31.312744,  Lng: -85.178589),  Route carried "on" structure: County highway 432,  Year Built: 1991,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 100 (year 2020),  Average Future Daily Traffic: 125 (year 2040),  Design Load: HS 20,  Features Intersected: PAGES CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $523,000,  Roadway Improvement Cost: $52,000,  Total Project Cost: $575,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 637,  Location: 4 MI. S. SR 52 (Lat: 31.234650,  Lng: -85.124117),  Route carried "on" structure: County highway 95,  Year Built: 1958,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 1.14m (3.74ft),  Average Daily Traffic: 700 (year 2011),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,090 (year 2033),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.839,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 79.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.82m (5.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $588,000,  Roadway Improvement Cost: $59,000,  Total Project Cost: $647,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 6627,  Location: 0.6 MI.E.SR.95 NORTH (Lat: 31.289617,  Lng: -85.103567),  Route carried "on" structure: State highway 52,  Year Built: 1959,  Status: Open,  Structure Length: 9.33m (30.61ft),  Average Daily Traffic: 5,850 (year 2013),  Truck Traffic: 9%,  Average Future Daily Traffic: 8,004 (year 2033),  Design Load: HS 20,  Features Intersected: CHATTAHOOCHEE RV. RELIEF
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 132.491,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.7m (44.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 9,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 44.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.28m (33.73ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $2,327,000,  Roadway Improvement Cost: $233,000,  Total Project Cost: $2,560,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 6628,  Location: ALA * GA STATE LINE (Lat: 31.285483,  Lng: -85.100822),  Route carried "on" structure: State highway 52,  Year Built: 1959,  Status: Open,  Structure Length: 34.81m (114.21ft),  Average Daily Traffic: 4,620 (year 2013),  Truck Traffic: 15%,  Average Future Daily Traffic: 6,321 (year 2033),  Design Load: HS 20,  Features Intersected: CHATTAHOOCHEE RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 133.014,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Navigation Control: Yes ( Vertical Clearance: 10.7m (35.1ft), Horizontal Clearance: 51.8m (169.9ft)),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 20,  Length of Maximum Span: 54.9m (180.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 47.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 34.81m (114.21ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 12 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Critical Feature Inspection Date: October 2021,  Underwater Inspection Date: December 2020,  Bridge Improvement Cost: $7,876,000,  Roadway Improvement Cost: $788,000,  Total Project Cost: $8,664,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 7052,  Location: .5 MI. EAST SR.#95 NORTH (Lat: 31.290650,  Lng: -85.104250),  Route carried "on" structure: State highway A0052,  Year Built: 1960,  Status: Open,  Structure Length: 3.84m (12.60ft),  Average Daily Traffic: 5,850 (year 2013),  Truck Traffic: 9%,  Average Future Daily Traffic: 8,004 (year 2033),  Design Load: HS 20,  Features Intersected: BAYLINE * C.O.G R.R.,  Facility Carried by Structure: SR 52 MP 82.257
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 132.380,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.7m (44.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.8m (42.0ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 55.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.78m (15.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,082,000,  Roadway Improvement Cost: $108,000,  Total Project Cost: $1,190,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 7881,  Location: RCDG BR. ON PAVED RD. 63 (Lat: 31.342058,  Lng: -85.177244),  Route carried "on" structure: County highway ,  Year Built: 1963,  Status: Posted for load,  Structure Length: 5.82m (19.09ft),  Average Daily Traffic: 150 (year 2014),  Truck Traffic: 1%,  Average Future Daily Traffic: 250 (year 2034),  Design Load: H 20,  Features Intersected: OMUSSEE CREEK,  Facility Carried by Structure: ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 4,  Length of Maximum Span: 16.8m (55.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 34.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: November 2020,  Underwater Inspection Date: December 2018,  Other Special Inspection Date: December 2021,  Bridge Improvement Cost: $1,128,000,  Roadway Improvement Cost: $113,000,  Total Project Cost: $1,241,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 12396,  Location: .4 mi.e. co. rd. 95 south (Lat: 31.292714,  Lng: -85.126222),  Route carried "on" structure: State highway 52,  Year Built: 1980,  Status: Open,  Structure Length: 6.80m (22.31ft),  Average Daily Traffic: 5,280 (year 2013),  Truck Traffic: 10%,  Average Future Daily Traffic: 7,224 (year 2033),  Design Load: HS 20,  Features Intersected: OMUSSEE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 130.156,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 3,  Length of Maximum Span: 36.9m (121.1ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.83m (25.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $2,471,000,  Roadway Improvement Cost: $247,000,  Total Project Cost: $2,718,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 12733,  Location: RCDG BRIDGE CO. RD.2 (Lat: 31.315906,  Lng: -85.154089),  Route carried "on" structure: County highway ,  Year Built: 1982,  Status: Open,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 30 (year 2014),  Average Future Daily Traffic: 50 (year 2034),  Design Load: HS 20,  Features Intersected: HURRICANE CREEK,  Facility Carried by Structure: CO.DIRT RD NO1027
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 52.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.96m (12.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $706,000,  Roadway Improvement Cost: $71,000,  Total Project Cost: $777,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 15223,  Location: 2.7 MI.N.OF COLUMBIA (Lat: 31.332767,  Lng: -85.104100),  Route carried "on" structure: State highway 95,  Year Built: 1990,  Status: Open,  Structure Length: 1.20m (3.94ft),  Average Daily Traffic: 1,020 (year 2013),  Truck Traffic: 16%,  Average Future Daily Traffic: 1,412 (year 2033),  Design Load: HS 20,  Features Intersected: BAKER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 41.948,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.9m (12.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 63.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $847,000,  Roadway Improvement Cost: $85,000,  Total Project Cost: $932,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 15887,  Location: .5 MI.N.FARLEY PLANT (Lat: 31.227283,  Lng: -85.124283),  Route carried "on" structure: County highway 95,  Year Built: 1958,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 700 (year 2011),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,090 (year 2033),  Design Load: HS 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.046,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.7m (8.9ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $349,000,  Roadway Improvement Cost: $35,000,  Total Project Cost: $384,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 18262,  Location: AL 52 TO CO RD 48 (Lat: 31.282517,  Lng: -85.183906),  Route carried "on" structure: County highway 54,  Year Built: 2002,  Status: Open,  Structure Length: 6.22m (20.41ft),  Average Daily Traffic: 629 (year 1992),  Truck Traffic: 9%,  Average Future Daily Traffic: 850 (year 2034),  Design Load: HS 20,  Features Intersected: HURRICANE CREEK,  Facility Carried by Structure: BILL YANCE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 75.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.26m (23.82ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $1,344,000,  Roadway Improvement Cost: $134,000,  Total Project Cost: $1,478,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Discuss Columbia, Alabama (AL) on our hugely popular Alabama forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.