Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Baring, Washington (WA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 14Number of bridges
  • 180ft / 55.4mTotal length
  • $29,123,000Total costs
  • 67,875Total average daily traffic
  • 6,933Total average daily truck traffic
  • 96,721Total future (year 2038) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Baring
  • No street view available for this location

New bridges in Baring, WA - historical statistics
  • New bridges - historical statistics
  • 21930-1939
  • 91980-1989
  • 22000-2009
  • 12010-2019
Average Bridge Daily Traffic in Baring, WA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 14.3%Very good
  • 64.3%Good
  • 7.1%Satisfactory
  • 14.3%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 78.6%Good
  • 14.3%Satisfactory
  • 7.1%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 7.1%Very good
  • 78.6%Good
  • 7.1%Satisfactory
  • 7.1%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 50.0%Very good
  • 25.0%Good
  • 25.0%Satisfactory
Find on map >>   Show street view

Structure Number: 2059A,  Location: 23.7 E JCT SR 203 (Lat: 47.802306,  Lng: -121.516000),  Route carried "on" structure: US 2,  Year Built: 1936,  Status: Open,  Structure Length: 7.83m (25.69ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,408 (year 2039),  Design Load: H 15,  Features Intersected: BNRR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 62.137,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 5 degrees,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 23.5m (77.1ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 7.83m (25.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $1,850,000,  Roadway Improvement Cost: $370,000,  Total Project Cost: $3,701,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 12746A,  Location: 2.3 E SNOHOMISH CO (Lat: 47.752944,  Lng: -121.459472),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 10.82m (35.50ft),  Average Daily Traffic: 6,516 (year 2019),  Truck Traffic: 12%,  Average Future Daily Traffic: 9,200 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: BNRR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 69.266,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 37.5m (123.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 27.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 21.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.82m (35.50ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: July 2018,  Bridge Improvement Cost: $2,982,000,  Roadway Improvement Cost: $596,000,  Total Project Cost: $5,964,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077A,  Location: 24.1 E JCT SR 203 (Lat: 47.797111,  Lng: -121.514417),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,408 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: EAGLE FALLS CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 62.716,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 81.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2019,  Bridge Improvement Cost: $616,000,  Roadway Improvement Cost: $123,000,  Total Project Cost: $1,232,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077B,  Location: 25.2 E JCT SR 203 (Lat: 47.785642,  Lng: -121.499472),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 2.68m (8.79ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,408 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 64.503,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.3m (83.0ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.68m (8.79ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $774,000,  Roadway Improvement Cost: $155,000,  Total Project Cost: $1,549,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077C,  Location: SNOHOMISH CO LINE (Lat: 47.777778,  Lng: -121.492333),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,199 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 65.549,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: April 2019,  Bridge Improvement Cost: $602,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $1,204,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077D,  Location: 0.3 E SNOHOMISH CO (Lat: 47.774917,  Lng: -121.488639),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,199 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 65.967,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.7m (67.9ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: April 2019,  Bridge Improvement Cost: $594,000,  Roadway Improvement Cost: $119,000,  Total Project Cost: $1,187,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077E,  Location: 0.7 E SNOHOMISH CO (Lat: 47.770333,  Lng: -121.482917),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 6,834 (year 2019),  Truck Traffic: 15%,  Average Future Daily Traffic: 9,649 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 66.643,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $602,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $1,204,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13077F,  Location: 2.0 E SNOHOMISH CO (Lat: 47.756083,  Lng: -121.464583),  Route carried "on" structure: US 2,  Year Built: 1986,  Status: Open,  Structure Length: 1.77m (5.81ft),  Average Daily Traffic: 6,516 (year 2019),  Truck Traffic: 12%,  Average Future Daily Traffic: 9,200 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 68.735,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.4m (57.1ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $499,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $998,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13391A,  Location: 3.1 E SNOHOMISH CO (Lat: 47.745778,  Lng: -121.446139),  Route carried "on" structure: US 2,  Year Built: 1988,  Status: Open,  Structure Length: 1.86m (6.10ft),  Average Daily Traffic: 6,516 (year 2019),  Truck Traffic: 12%,  Average Future Daily Traffic: 9,200 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 70.602,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.6m (61.0ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 61.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.86m (6.10ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $524,000,  Roadway Improvement Cost: $105,000,  Total Project Cost: $1,049,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13391B,  Location: 3.7 E SNOHOMISH CO (Lat: 47.740861,  Lng: -121.437139),  Route carried "on" structure: US 2,  Year Built: 1988,  Status: Open,  Structure Length: 1.86m (6.10ft),  Average Daily Traffic: 6,516 (year 2019),  Truck Traffic: 12%,  Average Future Daily Traffic: 9,200 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 71.487,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.6m (61.0ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 68.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.86m (6.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $524,000,  Roadway Improvement Cost: $105,000,  Total Project Cost: $1,049,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 16276A,  Location: 25.0 E JCT SR 203 (Lat: 47.786556,  Lng: -121.501167),  Route carried "on" structure: US 2,  Year Built: 2003,  Status: Open,  Structure Length: 5.43m (17.81ft),  Average Daily Traffic: 5,807 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,408 (year 2039),  Design Load: HL 93,  Features Intersected: BARCLAY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 64.325,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 52.7m (172.9ft),  Curb-To-Curb Width: 10.9m (35.8ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.43m (17.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $1,353,000,  Roadway Improvement Cost: $271,000,  Total Project Cost: $2,706,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 6050500000341,  Location: ROAD 6024, MP 0.2 (Lat: 47.773614,  Lng: -121.484722),  Route carried "on" structure: Federal lands road 60240,  Year Built: 2006,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 50 (year 0000),  Average Future Daily Traffic: 75 (year 2042),  Design Load: HS 25 or greater,  Features Intersected: BARCLAY CREEK TRIB,  Facility Carried by Structure: BARCLAY CREEK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.320,  Lanes on structure: 1,  Owner: U.S. Forest Service,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.8m (48.6ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 29.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 60506000015788,  Location: 0.9 MILE FROM COUNTY ROAD (Lat: 47.728842,  Lng: -121.423322),  Route carried "on" structure: Federal lands road 60300,  Year Built: 2011,  Status: Open,  Structure Length: 2.76m (9.06ft),  Average Daily Traffic: 5 (year 1995),  Average Future Daily Traffic: 7 (year 2042),  Design Load: HL 93,  Features Intersected: MONEY CREEK,  Facility Carried by Structure: ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.440,  Lanes on structure: 1,  Owner: U.S. Forest Service,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 26.7m (87.6ft),  Curb-To-Curb Width: 4.3m (14.1ft),  Out-to-Out Width: 4.3m (14.1ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 34.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Designated Inspection Frequency: Every 48 months,  Inspection Date: July 2021,  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 79794,  Location: 0.1 MI S OF SR-2 (Lat: 47.765306,  Lng: -121.480500),  Route carried "on" structure: County highway 89670,  Year Built: 1930,  Year Reconstructed: 1952,  Status: Posted for load,  Structure Length: 10.36m (33.99ft),  Average Daily Traffic: 80 (year 2018),  Average Future Daily Traffic: 160 (year 2038),  Design Load: H 10,  Features Intersected: SKYKOMISH RIVER-S FORK,  Facility Carried by Structure: NE INDEX CK RD
Minimum Vertical Clearance: 6.71m (22.01ft),  Kilometerpoint: 0.001,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Wood or Timber,  Design/Construction: Suspension,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 4,  Length of Maximum Span: 82.9m (272.0ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 2.5m (8.2ft),  Out-to-Out Width: 3.2m (10.5ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Poor,  Channel: Good,  Operating Rating: 9.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 5.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 10.67m (35.01ft),  Designated Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Other Special Inspection Date: August 2021,  Bridge Improvement Cost: $3,640,000,  Roadway Improvement Cost: $728,000,  Total Project Cost: $7,280,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber